Practice: Organizing Flashcards

1
Q

Here are three roles relating to the NowByou Project. Which individual (A-F) would be most appropriate for each role according to the ‘organizing’ practice?
Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.
1. Project Manager
2. Project Executive
3. Senior Supplier

A. Chief Executive Officer
B. Graduate Trainees
C. Chief Finance Officer
D. Marketing Agency Director
E. Head of Publicity and Social Media
F. Head of IT

A
  1. Project Manager - B. Graduate Trainees
  2. Project Executive - C. Chief Finance Officer
  3. Senior Supplier - D. Marketing Agency Director
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

NowByou has just made the decision to run the 6-month campaign as a project. As a result, the Director of Campaigns has appointed the Chief Finance Officer (CFO) as the project executive so that the ‘starting up a project’ process can commence.
Is this appointment an appropriate application of the �organizing� practice, and why?

A

A. Yes, Because the CFOM should be in a position to ensure that the project contributes to the financial standing of the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NowByou has just made the decision to run the 6-month campaign as a project. As a result, the Chief Executive Officer (CEO) has appointed the Director of Campaigns as the project executive so that the ‘starting up a project’ process can commence. One of the graduate trainees is likely to be appointed as the project manager.
Is the appointment of the Director of Campaigns appropriate according to the �organizing� practice, and why?

A

B. Yes because the Director of Campaigns should be well suitable to represent the interest of the CEO on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The business layer is [?] for the benefits management approach (post-project)

A

Accountable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The project executive [?] the project manager (if not done by the business)

A

Appoints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Senior User ensures project and stage (?) remain consistent with the user perspective

A

Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The Senior supplier provides people and (?) to perform supplier quality activities

A

Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The Project manager consults with (?) to prepare and maintain the risk management approach

A

Stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The team manager implements the issue and change control (?) agreed in the team plans

A

Procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Project assurance (?) the business case against project progress and external events.

A

Oversees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project Support (?) specialist tools to support the data management approach, (such as planning, control and reporting tools.)

A

Checks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The project executive (?) the development of a viable business case, ensuring the project is aligned with business objectives.

A

Administer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The senior user advises on the (?) aspects of the user communicate, for example, who the key influencers are.

A

Complaint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The senior supplier assists the project manager in preparing project and (?) plans

17
Q

The Project manager consults with stakeholders to capture and document the user’s quality (?) and acceptance criteria in the project’s product description.

A

Expectations

18
Q

The team manager participates in the identification, assessment and control of (?)

19
Q

Project assurance confirm the to the project board that the risk management approach (?) with business policies.

20
Q

Project support maintain the project (?)

21
Q

This is essential to how the Project Board Exerts Control (3 words)

A

Manage by Exception

22
Q

Missing word - The project executive and project manger roles cannot be [?]

23
Q

The number of organizational levels in any PRINCE2 Project

24
Q

If the Project Manager comes from the suppliers organization the customer is likely to increase regour in this role (2 words)

A

Project Assurance

25
In a programme which role may take the role fo the Project Executive? (2 words)
Programme Manager
26
One of four characteristics of a Project Board
Availability
27
The ability to approve or reject requests for change on behalf of th Project Board, delegated by the Project Board (2 words)
Change Authority
28
This role is held accountable for the realization of benefits (2 words)
Senior User
29
Missing word - Project Assurance responsibilities should not be assigned to project [?] members
Team
30
A Role who contributes to stakeholder analysis (2 Words)
Project Manager
31
Ultimately accountable for the project's success
Proejct Executive
32
This group represent the three project interests (2 words)
Project Board
33
This role may take the role of a Team Manager (2 words)
Project Manager
34
Project Board members need to have the right level of this given the nature and scale of the project
Authority
35
This is the level in the team structure where the Project Manager carries out day-to-day management of the project
Managing