Practice Exam Flashcards
To learn about the design operations and maintenance of building systems part I
A real estate developer purchased a building and site near a local college. He had the building razed and replaced with a new one in hopes of attracting leases from various college departments. This is an example of _______ development.
a. speculative
b. build-to-suit
c. entrepreneurial
d. contract
a. speculative
A development company is looking to build a retail space in a growing suburb. The company will need to complete a needs assessment in order to analyze its _______ requirements for the building.
a. performance
b. financial
c. space
d. legal
c. space
Richard keeps zoning codes in mind when designing buildings. That is because these codes control a building’s height, mass, and ________.
a. construction material
b. tax assessment
c. use
d. max. capacity.
Use
When she needs to review the written descriptions of every component of the buildings her team is designing, Ashley's best choice is to look at the \_\_\_\_\_\_\_\_. a blue prints b. working drawings c. conditions of the contract d. specifications
d. specifications
elizabeth, as the building owner, opted for a(n) _______ contact, even though it required more time and cost to develop, solicit, and evaluate the bids. Given the limited funds she has available for the project, she chose this type of contract because it requires firm assurance of final cost and minimum follow-up on her part. It also provides mas incentive to the contractor for the quickest completion of the project at the lowest cost.
a. cost-plus
b. unit price
c. lump sum
d. GMP-CM
c. lump sum
After the contract was awarded and signed by both parties, the general contractor sent a written request to Rita, the building owner, for clarification on some of the terms found in the contracts documents. This is a request for________
a. proposal
b. qualifications
c. information
d. quotation
c information
George’s building has previously been commissioned; however he is having the systems checked and retested against the checklists and procedures used during the commissioning process. This process of revisiting the buildings systems at regular intervals is referred to as _______?
a. new construction commissioning
b. retro-commissioning
c. recommissioning
d. continuous commissioning
c. recommissioning
Insulating the attic is a challenging task for Carl because of it’s awkward shape. He elects to use ______ insulation so he can blow it on the area to be insulated.
a. foam
b. sprayed-on
c. reflective
d. blanket
b. sprayed-on
Rick pays careful attention to aggregates when he evaluates concrete for use in building construction. This is because the aggregate in concrete typically constitutes _________percent of the concrete’s volume and has an impact on the properties of the concrete.
a. 0 - 20
b. 20 to 40
c. 40 to 60
d. 69 to 80
D. 60 to 80
Aware of the need for a radiation shield in rooms in a medical office buildings containing X-ray equipment, Chris recommends that ________ be used in the construction of the walls.
a. aluminum
b. steel
c. brass
d. lead
lead
Maria does not plan on using plastics in the construction of the building she is designing. This is because some plastics eak down when exposed to:
a. strong winds
b. acid rain
c. ultraviolet rays
d. air pollution.
Ultra violet rays
A combination steel and concrete framing approach will be used in building Rhonda is constructing. The advantages of steel for construction include all of the following except it ____________.
a. high elasticity
b. high strength
c. low fire proofing costs
d. uniformity over time
c. low fire proofing costs
Bruce has determined that the transportation of piles for construction of his building would be a problem. As the building engineer, he is best advised to consider all of the following for concrete piling except:
a. caissons
b. tapered piles
c. precast piles
d. angered in place piles.
c. precast tiles
The inspection team noted that pieces of concrete had broken off due to the pressure created by moisture that had frozen within the concrete over the past winter this is an example \_\_\_\_\_\_\_\_\_\_\_ a. cracking b. spalling c disintegration d. corrosion
b. spalling
When designing curtain walls, especially in northern climates, Carla knows that it is important to consider their ability to transmit heat, measured by the ________.
a. dynamic rate
b. static rate
c. U-value
d. P-value
c. U- value
The architectural design committee chose a(n) _______ type of curtain wall when renovating their old concrete building, since it is an attractive proprietary system with total installation provided by the manufacturer.
a. exterior insulation finish system
b. stucco
c. masonry veneer
d. metal
a. exterior insulation finish system
Before starting his building retrofit project, rob would like to analyze the energy use in the building to reveal potential energy savings and explore the substitution of alternative systems. This process is called:
a. building simulation
b. commissioning
c. a consumption audit
d. an energy survey
a. buidling simulation
One of the most significantly used window joint sealants is ___________, due to its good adhesive qualities and good performance in elongation and compression.
a. silicone
b. oil-based caulk
c. acrylic
d. butyl
a. silicone
it is important to Helen that the materials comprising the flat roof on the building she is designing are flexible, elastic, and resistant to Ozone and ultraviolet rays, have few visible seams, and are cost-effective and easy to repair. Thus, she determines the building should have a __________ roof.
a. shingle
b. shake
c. metal
d. single-ply membrane
d. single-ply memebrane
Louis knows the the membrane, perimeter walls, and metal accessories on the roof of the building he is retrofitting each expand and contract at different rates. Hoping to avoid a break in the waterproof membrane as a result of the forces of expansion, Louis plans to ______these roofing components.
a. isolate
b. combine
c. replace
d. remove
a. isolate