PQP-IDP Flashcards

1
Q

Stages of IDP

A

Design, Construction, Commissioning/Testing, O&M, On going education

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the benefits of implementing IDP credits?

A

Establish a more collaborative and iterative design process, Encourage construction activitiies that value workers welfare, quality and sound environmental management, prepare the ground for good O&M where the user plays an infomed active role

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What document must be accompanied with IDP-R2?

A

Lease documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the importance of IDP-R2?

A

To formally communicate to the future tenants and their design and development teams the requirements for the project in relation to sustainable design and construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

IDP-R2 is applicable only to what projects?

A

Core and Shell projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is required of Independent Cx Agent as part of IDP-R3?

A

Report to the project owner; Engaged as part of design team; Min 2 years experience; Can be an employee of one of the companies in the project as long as not involved in the project design and/or contruction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Comprehensive Cx requirements should be included in what documetnts?

A

Project specifications and construction contracts or provide a Cx Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is Cx Plan provided?

A

At building construction completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who commission the building at completion stage?

A

Independent Cx engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is included in Cx Plan?

A

OPR, BOD narrative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are included in the final Cx report?

A

OPR, Project cx specifications, Verification of installation, O&M Manual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

At what ratng do Cx plan and Cx report submitted?

A

Cx Plan- Design Rating; Final Cx Report-Construction Rating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Cx in terms of effort?

A

It is a collaborative effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Roles played by independent Cx agent

A

Oversee and lead Cx process; Review design and construction documentations; Prepare or review Cx plan; Review and approve the results of Cx system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Roles of the contractor in Cx

A

Employ independent Cx contractor; Commence development of BLB

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Minimum required systems for Cx process

A

HVAC-R, onsite energy generation(cogen), Lighting and Lighting controls, Domestic hot and cold water systems, on-site water treatment systems including swimming pools, auto control features such as blinds

17
Q

When should be the right stage to start LCC analysis?

A

During concept design

18
Q

What is the purpose of LCC analysis?

A

Evaluate and compare various design options

19
Q

The guest Worker Accomodation Plan should address what?

A

Provision for accomodation; On going maintenance plan; Inspection schedule and auditing mechanism; formal protocol

20
Q

What is required of CEMP?

A

Prepared according to EAD-CEMP Technical Guidance Document and either approved by EAD or peer reviewed by EAD approved and registered consultant

21
Q

When is the implementation of IDP-5?

A

Re-commissioning after 1 and 2 years

22
Q

What should be provided in order to attain additional credit point for IDP-6 aside from Occupant handbook?

A

Occupant feedback