Possible General Questions Flashcards
At what depth is considered to be a Deep diving?
a. 50m
b. 100m
c. 150m
d. 180m
d
DMAC 20 Rev 1 Provides Guidance on Bell Lockout durations state maximum period that the divers will remain in saturation is….
This is normally 28 days including decompression.
What is the maximum allowed time a diver can spend in the water and how long the bell run should last?
No diver should spend more than 6 hours in water out of the bell. After 2 hours work he should be given the opportunity to return to the bell for refreshment.
A bell run should not last more than 8 hours from seal to seal.
When a diving project is considered finished?
When all divers have returned to atmospheric pressure and remained in close proximity to a recompression chamber for a specified time in case there is a need for treatment of decompression symptoms.
What is the absolute minimum team size to support divers during a closed bell operation and 24 hours life support operations?
9
➢ Diving supervisor ➢ Two life support supervisors ➢ Two life support technicians ➢ Two divers in the bell ➢ Standby diver on the surface ➢ Tender for the standby diver
Regards to valves in the Diving Bell, what you should know? with what type of valves?
The circuit supplying the diver’s gas should be fitted with a non-return valves and clearly labelled externally and internally.
O2 lines fitted with needle valves which are normally open.
Valves (except those carrying oxygen at more than 15 bar absolute), should be fitted with a quarter turn valve and are normally open.
At all times the diving supervisor shall have the control of the bell blow down supply to the bell.
In case of Emergency Isolation of Gas Circuits in the Event of a Ruptured Bell Umbilical, AODC009 recomends?
- Every bell carries an emergency waterproof checklist of all valves that must be closed or opened. A duplicate should be kept in dive control.
- The contingency plan with procedure for completing this checklist and confirming the operation with the Diving Supervisor via through water communications.
- Photographs of all internal and external bell valves should be available in dive control.
What you should be aware of regarding to on board gas in the Diving Bell?
- designed to supply the diver if the surface supply fails. It is normally arranged to come on-line automatically if the surface supply pressure drops below a set level. It usually incorporates an audible and visual indication.
- There must be an emergency supply of gas sufficient to support each working diver plus the bellman outside the bell for a minimum of 30 minutes at a breathing rate of 40 litres (1.5 ft3) per minute at the maximum depth of the diving operation.
- Sufficient O2 must be available for metabolic consumption by the maximum number of divers at 0.5 litres/minute per diver for at least 24 hours at the end of a bell run.
In case of Emergency, the diving bell should be fitted with a minimum equipment required. What are they?
- Lifting equipment suitable for lifting an injured or unconscious diver into the bell.
- Must be equipped with a location transponder using the internationally agreed frequency of 37.5 kHz.
- An internationally agreed common manifold block for attachment of an emergency umbilical.
- On-board gas supplies and survival systems must be capable of sustaining the divers for at least 24 hours. Personal survival equipment should be provided for each diver.
- Adequate supplies of soda lime.
- several means of communication: helium scramble, sound powered phone, through water communications, Tapping code.
AODC 061 considers that the release of the bell weights is the least desirable option.
True or False?
True
Wet transfers to another bell, is one of the ways to recovery of stranded divers.
True or false?
True
In a Emergency situation with a tapping code you open communication procedures with the bell (3.3.3). The diver answer with (1.2.3).
What that means?
(1.2.3) Do increase your pressure.
PS: have a good look in tapping code procedures.
What are the types of cursos in the bell handling system? Explain them.
Passive: simply rests on the bell and moves with it up or down the guide rails. The bell winch takes the weight of both the bell and the cursor.
Active: has its own winch, separate from the bell winch, and during deployment and recovery through the vessel moonpool the bell is locked inside the cursor. The cursor winch takes the weight of both the bell and the cursor.
What are the methods used on cross hauling systems? Explain them.
Static Line: Necessary to have sufficient water depth to adequately compensate for the length of the cross-haul wire rope sling (the static line). The water depth at the cross-haul location needs to be accurately determined. The sling should in turn be of the correct length to enable it to be run underneath/along the vessel/barge or across the structure to reach the remote point at which the load transfer commences underneath the bell launch position.
Winch Operated: The winch operated method allows the cross-haul wire (winch wire) to be adjusted up or down during the cross haul operation.
According to IMCA D050, what is the minimum quantities of gas for saturation diving?
a. Sufficient mixed gas to carry out the intended bell run.
b. Sufficient mixed gas to pressurise all deck chambers required for the operation to the maximum intended storage depth.
c. Sufficient gas to allow a full decompression from the storage depth to the surface.
d. Sufficient oxygen to allow for metabolic consumption (0.5l/m) by each diver plus that required to maintain the ppO2 during decompression.
All of the above stated should be double!!
In the chamber what is the minimum gas should be available for Bibs in case of contaminated atmosphere?
For all mixed gas diving there must be sufficient gas available to allow every diver in the chamber 4 hours breathing on the BIBS on storage depth.
Before start a saturation project, what should be the minimum amount of calibration gas available?
There should be a minimum of 3 weeks supply of calibration and zero gas for the analysers. This reserve should be maintained during the saturation.
The minimum duration of oxygen required for the bell onboard O2 supply, at the end of the bell run is?
24h
DMAC 04 Recommends in Open Circuit Bail-out Bottles for Heliox Saturation Diving the oxygen content should be?
Maximum of 1.4 bar
Minimum of 0.4 bar
PS: In closed bell & diving from a wet-bell, the volume of available gas in the bailout is based on a requirement of 10 metres of umbilical can be deployed for every full minute of bailout bottle duration,
Who is directly responsible for the control of the TUP operation?
Diving Supervisor
What you should know about bell checks?
a. Must be carried out before every bell run
b. Usually valid for 6 hours.
What the parameters of PPO2 it should be maintain in the chamber and in the bell?
Chamber: 0.35 - 0.5 (normally 0.4bar)
Bell: 0.6 - 0.9 bar
According to IMCA international code of practice for offshore diving must contain a minimum percentage of oxygen, which is?
2%
What are the potential hazards it can be found in diver gas recovery system?
a. Failure of the exhaust line which could cause a pressure drop in the diver’s helmet and a squeeze.
b. Excessive levels of contaminants in the recovered gas.
c. Unsafe ppO2. The diver’s gas supply needs to be monitored by an oxygen analyser with an audible and visual hi-lo alarm
State the outlines for decanting procedures for mixing gases.
a. Calibrated accurate gauges with small divisions.
b. new mix must be left for a MINIMUM OF 24 HOURS to complete homogenisation.
c. Accurate final mix analysis must be done and the cylinder clearly marked and colour coded
Depth gauge connection and the analysis valves are usually small bore.
True or false
True
Crossover systems are widely used on analysis lines on saturation systems, with one analyser switched between several chambers.
True or False
True
Crossover systems, in which one gauge serves two chambers and is switched between them is widely used.
True or False
False
They are potentially very dangerous and must never be used.
What are the requirements for Oxygen and Decompression?
The ppO2 is raised to a higher level before starting decompression
The required pp02 is then maintained during the decompression
Every time gas is vented out of a chamber, the ppO2 will drop and more oxygen must be added to maintain the correct ppO2
As the chamber gets shallower, the oxygen represents a higher percentage of the total volume, and the volume of oxygen coming out increases
BIBS masks requirements are?
Suitable stowage
Immediately available
Oxygen clean
What are the Environmental control units made for?
They can be internal and external
- Carbon dioxide scrubbing
- Heating
- Cooling
- Humidity
- Moisture is extracted condensation
What is used to remove Carbon Dioxide (CO2) from chambers ?
Carbon Dioxide (CO2) is removed from chambers using a chemical absorbent
The most commonly used chemical is soda lime or sodium hydroxide
About CO2 removal, how much 1 kg of soda lime will absorb?
1 kg of soda lime will absorb about 120 litres of carbon dioxide
This is about 0.72m3 or 720 litres per day
A diver in a chamber produces as much carbon dioxide as the oxygen he uses
Just like metabolic oxygen use, carbon dioxide production is not affected by depth
1 kg of soda lime will last a diver for 4 hours
6 kg of soda lime will last a diver for 24 hours
About Chemical sampling tubes, what the supervisor should be aware of?
- The True % could be called the True PPM or True PP depending on the measurement in use
- The True reading refers to the reading one would get from an analyser reading at surface in the control room
- Consider the True Percentage is the reading on the surface analyser
- True percentage% = Scale reading/
Absolute pressure
What is the maximum allowed SEP in the Bell and DDC?
In a bell is 2% or partial pressure of 20 mb or 20000ppm
In a DDC is 0.5% or partial pressure of 5mb or 5000ppm
About Gas supplies, the supervisor should always be aware of?
- For all mixed gas diving IMCA D050, there must be sufficient gas available to allow every diver in the chamber 4 hours breathing on the BIBS in case the chamber atmosphere becomes contaminated.
- Sufficient mixed gas to carry out the intended bell run, plus the same quantity as a reserve.
- Sufficient mixed gas to pressurise all deck chambers required for the operation to the maximum intended storage depth, plus at least an equal amount in reserve
- During the operation, the reserve of gas sufficient to completely pressurise the chambers must be maintained
- Sufficient gas to allow a full decompression from the storage depth to the surface twice, allowing for the normal daily consumption (This quantity to be doubled for safety reasons)
- Sufficient oxygen to allow for metabolic consumption by each diver plus that required to maintain the ppO2 during decompression (This quantity to be doubled for safety reasons)
- Gas reserves for the diver should be based on gas recovery systemnot operating
- Before a saturation dive there should be a minimum of 3 weeks supply of calibration & zero gas for analysers
- This reserve needs to be maintained during the saturation
Chamber Hygiene and bedding change should be perform how often?
Bedding changed every 3 days or twice per week.
General cleaning, pipework, walls, etc - every 3 days or twice per week
During a Saturation, you experience a rapid loss of chamber pressure. What are the consequences and what action the LST should perform?
Divers may suffer from decompression sickness, barotrauma and hypoxia as the PO2 drops
Major leak - considerable noise - communication difficult
Misting will occur as the temperature drops
Doors between chambers may seal
The divers should attempt to evacuate the leaking chamber and close the door
Diver’s should go on BIBS as the atmosphere maybe hypoxic or hyperoxic
They may need to evacuate to the bell or to a hyperbaric rescue vessel
Note: The LST should pressurise the system in an attempt to maintain pressure and other members of the surface should attempt to locate the leak
DMAC 028 recommends that every saturation system should provide a facility where an injured diver can be given medical treatment while under pressure. Designating one chamber.
What are the requirements of this chamber?
A minimum internal diameter of 1.8 metres (6 feet)but DMAC recommends 2.15m
The ability to remove or move out of the way, bunks and other equipment normally fitted to the chamber but not needed directly for a medical emergency
A bunk for the patient which should:
Be waist high
have access from at least one side and one end have a firm base
be able to tilt the patient to 30⁰ both at the foot and head ends
A working surface for medical instruments
A means for suspending IV drips overhead the patient
A convenient medical lock of at least 300mm diameter
During a saturation pressurization certain basics procedures should be followed, what are they?
- The divers must be on BIBS for at least the first 10 msw (33 fsw)
- The pressurisation must be stopped at about 1 msw (3 fsw) to check for leaks
- Typical pressurisation rate is 2 meters per minute
- Maximise circulation
- Run ECU at full speed
- Use emergency scrubber
- Divers to wave towels around
- Run any other internal fans
- BIBS mixes breathable mix online
- Follow pressurisation rates
- Pressurisation rest periods may be required
What are the living parameters for a Environmental typical Heliox saturation?
Humidity: 50% - 70% PO2: 0.35 - 0.5bar Temperature: 25 - 33 C CO2: Less than 5mb (0.005ata) N2: less than 1000mb (1ata) Depth: 0.3m (1ft) of specified depth
In a split level saturation, what are the main concerns about it safety?
Leaks through the doors seals
Unbreathable atmosphere
Common lines
For how long a HES should be able to maintain pressure and support for the divers?
Maintaining the divers at the correct pressure and with life support for a minimum of 72 hours
What is the stand for HES, HRU, HRC, SPHL, LSP and HRF?
HRU: Hyperbaric Rescue Unit = is a general term for evacuation systems
HRC: Hyperbaric Rescue Chamber = is a floating chamber without a supporting crew
SPHL: Self Propelled Hyperbaric Lifeboat is a floating chamber with a support crew, usually contained in a conventional lifeboat
LSP Life Support Package
HRF: Hyperbaric Reception Facility is a chamber system located at a ‘safe location where the SPHL / HRC can be
Explain the 4 phases of Operational Emergency form launch divers to decompress?
Phase A:
Transfer of the divers into the HRU
Make it ready for launch
Maximum time to undertake this - 15 minutes
Phase B:
The launch of the HRU it to be 100m clear of the vessel/installation being evacuated
Maximum time to undertake this - 30 minutes
Time starts when the instruction to launch the HRU is given
Phase C:
The transit of the HRU to the reception site
Planning should be based on arrival at the safe haven within 75% of the HRU designed endurance
The safe haven is where the HRU arrives on completion of transit
Phase D:
Safe decompression of the divers
Who is the decision of decompress diver on HRU using LSP?
The decision to decompress the divers in the HRU using an LSP or providing a HRF medical treatment should be based on a full risk assessment involving the client
According to IMCA D014 rescue drills and HRU launch should be perfom?
Rescue drills - 14 days and Practice deployment every 6 months (IMO)
What are the minimum supervisory requirements for single bell operation, twin bell operation (with bottom turnaround) and Life support supervisors?
Single Bell: 2 supervisors per shift, if there is a trainee he should be in addition to it
Twin Bell: 3 supervisors per shift, one for each diving ops and a third one acting as relieve
LSS: at least 1 LSS and 1 LST per shift
PS: Divers from both bells are not permitted to work simultaneously
According to IMCA D002-10 the supervisor should be in control of the bell blowdown at all times, what are the main reasons?
a. contaminated bell atmosphere, supervisor enable to flush or vent
b. rapid internal pressure loss, enable to intervene.
c. divers became incapacitated
d. supervisor responsible for the course of the bell run
ABCD
- Through water comms must be tested?
a. at surface before bell launch
b. during the bell run
c. at working depth prior the diver lockout
d. at working depth post the diver lockout
C
Note: D022 states
‘‘Through water communications should be tested at the end of every dive, in preparation for the next dive, and recorded as a pre-dive check’’.
- If through water comms cannot be established diving operations should not proceed until the unit is operational again.
True or False?
True
According to IMCA D009 all quads should be fitted with their own permanent sling sets which should be correctly fitted to the designated attachment points on the frame.
What type of quads can you find offshore?
Type 1 (Vertical Quads) – The valves, fittings and pipework are all grouped together on the top face of the quad. Such quads typically contain 12 or 16 cylinders.
Type 2 (Horizontal Quads) – The valves, fittings and pipework are all grouped together on one end face of the quad. Such quads typically contain 45, 48 or 64 cylinders.
What ASOG stand for?
Acitivity Specific Operating Guidelines
About the chain hoist equipment, the stopper at the end of the chain should be capable of withstanding a load test of at least?
a. 2 times the maximum tension
b. 2.5 times the maximum tension
c. 150% of the WLL
d. 250% of the WLL
B
IMCA recommends that manufacture attachment points of lifting bags are designed with a MBF not less than…
a. 1.5 times
b. 2 times
c. 2.5 times
d. 3 times
A
What is the most common method to test equipment for oxygen cleaning?
Visual Inspection using UV light (3600 to 3900 angstrom)
Note: Tests are limited to determine the presence of contaminants, not the absence.
What is the most common method of approving materials for oxygen compatibility?
Bomb test
For how long is the medical examination pre-saturation valid?
a. 8h
b. 12h
c. 24h
d. 48h
C
One of the main items prohibited to take in Hyperbaric conditions is?
a) Battery Charges
b) Camera
c) Portable Computers
d) Toothbrush
A
The term “High Voltage” is used to refer to any voltage above?
a) 110V
b) 220V
c) 440V
d) 1000V
D
The term “ Low Voltage” is used to refer to any voltage below?
a) 24V
b) 50V
c) 110V
d) 220V
B
What is the maximum operating voltage of the system which safety can be assured for divers working in the vicinity of impressed current systems.
a. 30v
b. 50v
c. 110v
d. 24v
A
Flexible pipes carry out 25% or more of oxygen is limited to ….. of length.
a. 2 meters
b. 2.5 meters
c. 5 meters
d. 10 meters
C
Pressure of all Onboard gases (heliox and oxygen) must be reduced to a maximum of …… before entering the bell interior.
a. 6 bar plus ambient
b. 10 bar plus ambient
c. 30 bar over ambient
d. 40 bar maximum
C
What is the minimum diameter of a chamber manufactured after 1 January 2015 usef for hyperbaric evacuation system?
a. 1500mm or 60 inches
b. 1750mm or 69 inches
c. 1800mm or 72 inches
d. 2000mm or 80 inches
B
What is the recommended specification of “maximum detectable range” of a Helle Locator?
a. 200 meters
b. 300 meters
c. 400 meters
d. 500 meters
D
After decompression from 1,000 fsw to 400 fsw, the maximum downward excursion of a diver is 105 fsw. How long does the diver have to wait for a full upward excursion is permitted?
a. 12h
b. 24h
c. 48h
d. Diver has a free excursion.
C
According to HSE ACoP, how many diving supervisors can be appointed at any one time?
a. 1 supervisor
b. 2 supervisors
c. 2 supervisors and a trainee
d. 1 Superintendent
A
Following the BS EN 12021 - Breathing Gas Standards. What is the maximum allowed of Carbon Monoxide for Oxygen and Helium gas Mixtures?
a. 2 ppm
b. 3 ppm
c. 5 ppm
d. 0.2 ppm
D
Following the BS EN 12021 - Breathing Gas Standards. What is the maximum allowed of Carbon Monoxide for Nitrox mixtures?
a. 2 ppm
b. 3 ppm
c. 5 ppm
d. 0.2 ppm
B
A Certified David can be used as suspension point for cross hauling static line?
True or False
True
Bell tapping Code is to be located in a fixed position…
a. Only Outside of the Bell
b. Only Inside of the Bell
c. In the Diving Control Room
d. Outside and Inside of the Bell
D
Calibration of gases in the Dive Control and Saturation Control, should be done by the supervisor every…
a. 8 hours
b. 12 hours
c. 24 hours
d. Every Bell turn around
B
D022 - Analysers should be calibrated before every sat and every shift change thereafter or as indicated in company manuals.
The reasons of a Recovery system filters are to remove
a. Moisture and solid particles
b. Carbon Dioxide
c. Trace gases and bacteria
d. All of the above
D