PMP Udemy Exam Prep Test Flashcards
While working on a complex software development project, the team is having a difficult time understanding a process used to code a particular report. They find the process to have many different paths and if/then scenarios. They have asked the project manager for a tool that can help them see the process on a large white board or on paper. What’s the best tool the project manager can recommend for the team to help visualize the process?
Flowchart
Explanation
A flowchart is a tool that is used to help visually display a process. It can show decision points, loops, or paths. A scatter diagram is used to show a relation between two variables. A fishbone diagram is used to help identify potential causes for defects, and a histogram is a bar chart that shows the frequency of things, such as a Pareto chart.
When an organization is considering a project, what are some of the factors that can influence why a project should get done?
Meeting regulatory, legal, or social requirements.
Explanation
Reasons a project should get done include meeting regulatory, legal, or social requirements, satisfying stakeholders’ needs, and implementing business changes. The other choices pertain to operational work, which is more day-to-day and ongoing.
A project manager wants to ensure that the new cell phone the project is creating will beat or match the performance of new cell projects by other companies. What tool would be the best for the project?
Benchmark
Explanation
Benchmarking is a tool in plan quality that is used to compare best practices to other projects, either within or outside of the organization. Plan quality is a process, not a tool. Meetings are tools used by the project manager to interact with the project team and solve problems. Collecting requirements is a process, not a tool.
The project team is having a very difficult time deciding what method they should use when programming the new functions in the application. They can choose between four different methods, and the team is evenly split regarding which method to choose. The project manager has decided that he will choose the method for them and will take the responsibility in case it is not the best way to program functions. What best describes this technique?
Autocratic
Explanation
In autocratic decision making, an individual makes the decision for the team and takes responsibility for the decision. Voting is when the team votes on a potential decision, and multi-criteria decision is when they use a different criteria are used to evaluate a decision. Leadership refers to skills for managing the team.
Your company has just started a project to allow remote workers to join the network using a virtual private network (VPN). During the execution of the project, one of the VPN servers completely fails, and the team will need to replace it as soon as possible. Fortunately, the project team anticipated that this might happen and has a plan for replacing the server. What should the project manager do next?
Implement Risk Response
Explanation
Implement risk response is a process in the executing process group, where the project manager implements the preplanned responses to any risks that may have taken place. Plan risk responses is done to determine the team’s response if a risk happens, perform qualitative risk analysis is used to rank risks, and conduct risk response is not a PMBOK process.
The project manager and team are currently working to create a list of activities needed to complete the project. They have come to one particular work package that they cannot decompose because they do not know enough about the work yet. They have decided that midway through the project, they will decompose this particular work package. What tool or technique are they using?
Rolling Wave Planning
Explanation
Rolling wave planning is a tool used in the process of define activities to break work down in the future. Forward planning and requirements future planning are not real tools used in the process of define activities. Decomposition is a tool used to break down the current activities.
The project manager is currently analyzing the requirements for the project. He has noticed that the stakeholders will be very disappointed if there are defects in the deliverables. He decides to ensure that the project team receives the right training and the best equipment available to build the deliverables correctly. This will in turn increase the overall cost of the project, but stakeholders do not mind the increase in cost. What best describes this increase in cost?
Cost of Quality
Explanation
The cost of quality includes the cost of conformance, which includes funds spent to ensure the project meets the quality requirements. This generally includes the cost of better materials, more expert team members, and better equipment. Cost of resource requirements and activity costs are not valid elements. Expert judgement involves hiring subject matter experts to help plan a particular process.
Which of the following is a method that will be used to conduct frequent verification and validation that can be done every second on the project?
Pair Programming
Explanation
Pair programming is defined as when one programmer writes the code another inspects the code as it’s been written. This leads to the codes being inspected in seconds.
The project manager has to present the risk assessment to the senior management and has decided to take the most graphical representation of the probability and impact assessment. What tool should the project manager use?
Bubble Chart
Explanation
Bubble charts are tools in the perform quantitative risk analysis process and can show the probability, impact, and ranking of risk. The risk register is not graphical. Pareto charts are used for quality and not risk. Risk summary charts is a made-up term.
A project manager decided to ensure that all team members on the project do not work on more than one activity at a time. This way, the team doesn’t get burned out and can work at a steady pace. The schedule may increase due to this policy, which is okay with the sponsor. What technique best describes this action?
Resource Leveling
Explanation
Resource leveling is done when resources on a project are over-allocated; it removes resources that are working on two activities at the same time.
The project manager has released the project team, completed the final lesson learned, and then completed the final report. The PMO has informed the project manager that it is not happy with this approach. What has the project manager done wrong?
Releasing the Team and then doing the Lessons Learned.
Explanation
Lessons learned should be done with the team and not just by the project manager. The steps in closing usually involve conducting the lesson learned, releasing the team, and then writing the final report.
The project team is working with the customers to write the user stories. The customers have refused as they claim this would add no value to the project. What would be the best step to resolve this?
Educate the users on why the user stories are valuable.
Explanation
When managing an agile project user stories will produce a lot of value to both the team members and the customers, as such it would be best to educate them on the value of the user stories.
While working with the project team and conducting a brainstorming session, the project manager noticed that a lot of the ideas the team was coming up with were not organized. What tool can best be used by the team to visually organize their ideas?
Mind Mapping
Explanation
Mind mapping is a way to visually organize data. A matrix diagram is used to show the relationship between two or more groups. A flowchart shows a graphical representation of a process. A Pareto diagram displays Pareto’s 80/20, rule usually in a histogram.
While working on a project, you realize that you will not be able to install the server and the workstations at the same time. In fact, the team has alerted you that after the server installation is done, you should wait an additional 4 days before installing the workstations. This is due to the updates the server will need, which is an automated process. What do you need to add to the schedule in order to account for this delay?
Lag
Explanation
A lag is a delay between activities. A lead is an overlap between activities. Slack and floats refer to the same thing: the amount of time you can delay an activity without delaying the project.
While planning the risk responses for a construction project, the project manager and project team have decided they will have to choose a new electrical contractor due to the fact that the recommended contractor has legal issues with the local building department. The legal issues could cause the project to be delayed. What risk response does this represent?
Avoid
Explanation
Avoidance is when you go down a different path all together. The risk is eliminated and cannot happen. Since they choose another contractor, they cannot get delayed by that particular contractor. Acceptance is taking no action against the risk and accepting the outcome. Mitigation is done to reduce the risk probability and/or impact. Exploit is for a positive risk that will ensure the risk takes place.
The project team has been working very hard over the last 4 months to program the financial application and has completed it. The project manager has informed the team that the quality control team will be inspecting it next. What process group best describes what the team has done so far?
Executing
Explanation
In the executing process group, the team completes the deliverables. During the monitoring and controlling processes, the deliverables are accepted by the stakeholders. During the planning process, the project management plan is created. During the closing process, the project or phase is brought to formal closure.
What is the main difference between the product scope and the project scope?
The product scope describes the features and functionality of a product, whereas the product scope describes how to get the features and functionality from the product.
Explanation
The product scope describes the features and functionality of the product, whereas the project scope describes how to get the features and functionality from that product.
While working with the system administrator, the project manager identifies many different types of resources required for the project to be completed successfully. The project manager classifies them as HR, material, equipment, and consumable resources. Where can the project manager best document these resources?
Resource Breakdown Structure
Explanation
The resource breakdown structure is a breakdown of the resources by categories or types. The resource register and resource category matrix are made-up terms. The resource requirements describe all the resources needed to complete an activity.
While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?
Independent Estimate
Explanation
An independent estimate is usually done by an outside entity to help give the project manager a more independent understanding of what certain project work will cost. Inspections and audits are done after the seller is selected to ensure the work stays on contract. Screening and weighing systems are done to help select sellers.
While managing the project team the agile project manager is having a very difficult time understanding why team members are always frustrated when communicating with him. What critical soft skills does this project manager lack?
Emotional Intelligence
Explanation
Emotional intelligence is defined as the skill to identify, assess, and influence emotions of ourselves and others around us.
You’re currently working on a large new building development project. The project team is currently breaking down the deliverables listed in the project scope statement into work that is more manageable. What process best describes this scenario?
Create WBS
Explanation
During the create WBS process the project team will use the tool of decomposition to break down the project deliverables into work packages. These work packages will then be used to help estimate the time and cost of the project. Define activities is a process of decomposing the work packages into activities, not the deliverables. Define scope is used to create the scope statement which will have a list of the deliverables. Define WBS is not a process.
Over the last three weeks the project team has finally been able to establish a shared vision of what the product would look like when it is complete. This is an example of?
Progressive Elaboration
Explanation
Progressive elaboration occurs when more information in detail emerges over time.
What is the difference between the product backlog and the iteration backlog?
Product backlog contains all the work needed to be completed on the project and iteration backlog will contain all the work that will get done in the next iteration.
Explanation
The product backlog will contain all the work needed to complete the project, while the iteration backlog will contain the work that will get done in the next iteration.
The project was executed about 3 weeks ago, and the project team seems to be having a lot of difficulties getting along with each other. They are always having conflicts about how to proceed on certain activities, and the project manager has to step in in order to solve these conflicts. What process is the project manager performing?
Manage Team
Explanation
In the process of manage team, the project manager has to resolve issues and conflicts among the project team. This is done using the tool interpersonal and team skills, particularly conflict management. Acquire team is not a process in the PMBOK. Control resources is a process that involves physical resources, not human resources. Control scope is about preventing scope creep and ensuring the project meets the scope.
While monitoring and controlling a project, the project manager has been comparing the work performance data to the project management plan to see if there are any variance. What process did the project manager finish to get the work performance data?
Direct and manage project work.
Explanation
Work performance data is an output of the integration process of direct and manage project work.
A change request has been requested by a senior stakeholder to add a new reporting function to the current financial software development project. The change was assessed by the project team and approved by the sponsor. What process should the project manager do next?
Direct and manage project work.
Explanation
Once a change has been approved, it is time to execute the change, which is done in the executing process of direct and manage project work. Control quality is done to check the deliverables to ensure they meet the quality requirements. Validate scope is done to get formal acceptance from the stakeholders. Perform integrated change control is done to assess and approve a change request.
The project manager has taken all the work performance information that has been created so far on the project. He has started to create the overall project status report to present to the project stakeholders. What process is the project manager conducting?
Monitor and control project work.
Explanation
Monitor and control project work process has an input of work performance information and an output of work performance report. No other choice has the output of work performance report.
Project manager Mary was informed by the team that the constant conflicts in the project have slowed down the team so that they are now behind in the work. Mary is not sure what she did wrong while planning the project. She used a RACI chart to assign roles to each team member. She has assigned each activity to at least two people who will be held accountable for the work. What best explains the conflicts in the project?
Only one person should be accountable for an activity when using a RACI Chart.
Explanation
When using a RACI chart, only one person should be held accountable per task on the chart, which applies to using a kind of tool to assign resources. When more than one person is held accountable, the team members will blame each other for work that was done incorrectly or not at all.
The project team has just started to code the redesigned accounting application when a key stakeholder asks for the application in order to include a very specific report to the company’s expenses. The stakeholder has submitted a change request to the project manager. What would be the most important input to consider for this change request?
Work performance reports
Explanation
Work performance reports is an input to the process of performing integrated change control, as it will show the overall status of the project. The other choices are not inputs to this process.
While working on a project schedule, the project manager notices that activities A, B, and C all have a duration of 4 days. The project manager also notices that activities F and G have a duration of 7 days. Activities A, C, F, and G have a slack of 1 day. Activity B is the only one on the critical path. What is the slack on activity B?
O days
Explanation
If an activity is on the critical path, it will have zero slack. Non-critical path activities will have a slack of at least 1 day.
The project team is currently working on a project to upgrade all the servers across the organization. Before they are able to get the financial server, the vendor calls and says the server delivery has been delayed 2 weeks. What documents should the project manager update immediately?
Issue Log
Explanation
The issue log is used to keep track of all issues in the project. The delay of a server will mean the project might be delayed, so it should be entered into the issue log immediately. After that the project manager might implement a change request to extend the schedule baseline and update the project management plan. The work breakdown structure does not show work by time.
A company has completed building a new datacenter. The project has many changes that were submitted to the change control board. Most changes were approved, and some were not. Which of the following is not a purpose of the change control board?
Deny changes whenever possible.
Explanation
The change control board’s purpose is to manage changes to the project, which include assessing changes and stopping unnecessary changes. The change control board is not there to deny changes unless it has been assessed and deemed unnecessary in the project.
The project manager has calculated the SPI of the project to be .7 and the CPI is .9. When reporting the progress of the project to the company stakeholders, what should the project manager say about the project to the stakeholders?
The project is delayed and over budget
Explanation
A CPI and SPI of under 1 are bad. A CPI of under 1 represents a project that is over budget. An SPI of under 1 represents a project that is behind schedule.
The project manager has acquired the project team members and is starting to work with them to complete the project work. During this process the project manager has utilized a variety of rewards and recognition theories to keep the team motivated. What is the output of this process?
Team performance assessments
Explanations
The process being completed in this question is develop team. The output is team performance assessments. All other choices are tools in this process.
The deliverables for the office relocation project were accepted by the company stakeholders, and all office staff were very happy with the work of the movers. The office manager requested to close the project immediately due to year-end budgetary closeouts. The movers filed a claim for an additional $300 for moving a copier that was not part of the plan. What should the project manager do next?
Keep the project open and inform claims administration.
Explanations
A project can only be closed once all claims have been settled. Claims should be sent to claims administration, where negotiation would be the preferred way to resolve them.
While building the agile space for new agile team which of the following tools should the project manager insurer is available to all of them?
A whiteboard
Explanation
The use of high touch low-tech tools such as a whiteboard is vital in an agile environment to ensure collaboration and engagement of all team members.
While analyzing the budget of a project, the project manager notices that the current CPI of the project is .93 and the SPI is 1.1. What best describes what is taking place on this project?
Crashing
Explanation
Crashing involves adding more resources to a project to decrease the schedule. In this scenario, the project is 7% over budget but is 10% ahead of schedule. Fast tracking and resource leveling generally do not increase costs. Best tracking is a made-up term.
While developing complex software for an organization, the project team creates a computer-generated model of what it will look like when it is done. This model is given to the customers for their feedback. What best describes this model?
Prototypes
Explanation
A prototype is generally a mock-up or functional product that is given to the customers for feedback. Data representation and data analysis are tools used to analyze data and present them in various forms, such as graphs or charts. Screenshots are pictures taken from a screen of an application, not a model of how the application will work.
There have been many disputes on the project with the current contractor. The contractor claims the project team is always asking that work not be listed in the contract, and the team claims that the contractor has not been doing the work listed in the contract. What should the project manager do first?
Review the contract
Explanation
The first step would be to review the contract to ensure he understands what the original agreement was, and then he should meet with the team and contractor. If needed, he should then contact the claims administration.
While conducting a risk assessment on a project, the project manager has identified a new regulatory risk. If the project is not completed by July 31, the company will have to scrap the project. What best describes this?
Project constraint
Explanation
There are 6 constraints on a project,: scope, cost, time, resources, risk, and quality. This project is constrained by time. The other choices are project requirements, not constraints.
When using different prioritization technique what is the most important aspect that the agile project manager should communicate to the customers?
Do not worry too much about the specifics, it is more important to get the relative prioritization correct.
Explanation
When using any prioritization technique is important to ensure the customer understands not to worry too much about the specifics of the technique but to understand that it is done prioritize the features based on relative value.
Your company has decided to roll out a new Wi-Fi network for the staff. The sponsor has informed you that encryption on the network is mandatory. Where will the project manager document that the encryption was mandated by the sponsor?
Requirements traceability matrix
Explanation
The requirements traceability matrix will trace the requirements back to their origins. The project scope statement, scope baseline, and requirements documentation will not include where requirements came from.
The project sponsor has signed off on the project charter and has spoken to the project manager, who then has to keep the cost down on the project. The project manager agrees to try his best to keep cost down and to finish the project under budget. What should the project manager do next?
Meet with stakeholders to gather their requirements.
Explanation
Once the project charter is created, the next step would be to collect the requirements and then create the scope statement and the WBS. You cannot meet with the team to reduce cost if you don’t know the requirements. There is no such thing as a cost reduction program in PMBOK.
The project team has completed the server deployment project. They have tested the server to ensure that it works according to the requirements given to them, and it seems to be functioning correctly. What process group has the team just completed?
Executing
Explanation
The outputs of all the executed processes combined, including directly executing the process and managing project work, are the project deliverables. The output for planning would be the project management plan. The output for closing would be the final product service or result transition and the final report. The output for monitoring and controlling would be the accepted deliverables and the work performance reports.
While managing the stakeholders’ engagement, the project manager notices that some of the team members are not respectful to other team members. This has led to a few conflicts between the members. What can the project manager best do about this?
Implement ground rules
Explanation
Ground rules are usually set within the team charter and are the general rules that the team will follow in order to effectively work with each other. These generally include behavioral rules. Before releasing the team, the project manager should try to resolve the problem. Conflicts within a project team should not be a reason to stop a project. If you were to inform the sponsor, they would generally tell you to solve this problem.
The product owner has requested to be showing how much work there remains to be done on the project. What would be the best agile tool to display this?
Burndown Chart
Explanation
A burn down chart displays work that remains to be done.
While working on a project with a budget of $5,000, the project manager determines that the earned value on the project so far is $1,750. So far, the project team has spent $2,900. What should the project manager report as the status of the budget?
The project is over budget by 40%.
Explanation
In this situation, you would need to find out the CPI of the project, which is EV/AC. That would equal 1750/2900 = .6. A CPI of .6 represents that the project is 40% over budget. Remember that if the CPI is 1, then the project is on budget. Anything under 1 represents being over budget, and anything over 1 represents being under budget.
The project manager is having a difficult time keeping the project on plan. There are many changes regarding the project scope, which has led to an increase in the project budget. Management would like a reason why there have been so many scope changes on this project. What would most likely cause many scope changes on a project?
Did not gather detailed requirements.
Explanation
Generally, if a project manager finds themselves with many scope changes when the project is executed, it’s most likely that they did not gather the requirements adequately from the customers. The other choices cannot be selected because the question does not give enough information regarding them.
During a new smartphone development project, the customers are given a prototype of the smartphone for them to try. They inform you that the phone constantly reboots, and sometimes the touch screen does not work. What tool can the project team use to find the reasons for these defects?
Ishikawa (Fishbone) Diagram
An Ishikawa diagram, also known as a cause-and-effect diagram, is used to list the many different probabilities for a project’s defect. Assumptions analysis involves analyzing assumptions, histograms are used to show the frequency of defects, and inspections are used to see if a deliverable has met its requirements.
A project manager is having difficulties communicating with the project team; there always seem to be misunderstandings and conflicts. What interpersonal and team skills should the project manager improve on?
Active Listening
Explanation
Active listening helps to reduce misunderstandings and improves communications and knowledge sharing. Selective listening and passive listening are not terms used in PMBOK. The lessons learned register is not an interpersonal and team skills tool.
Senior management has requested an update to the current product upgrade project. The project manager knows she has to keep the information high level and as short as possible. Which resource would be the best to show senior management?
Milestone Chart
Explanation
A milestone chart shows only the major start and end of the major deliverables. All other choices such as the WBS, WBS dictionary, and the network diagram are very detailed.
While working on a project, the sponsor makes it clear that he does not want any of the team members to be overworked. This means that no team member is allowed to work overtime. The sponsor is okay with the project being delayed due to this. What technique can the project manager best implement to ensure that no team member is overworked?
Resource Leveling
Explanation
Resource leveling is a technique used when resources are limited or over-allocated. Resource leveling ensures that no resource is assigned to more than one activity at a time, ensuring that no resource is overworked. Resource smoothing may accomplish the same task, but it only works if there is slack available on the activities. Free float is the amount of time you can delay an activity without delaying the next activity. Lag is the amount of time you need to delay an activity before the next activity starts.
Which of the following is not a principle of agile planning?
Conduct most of the planning at the beginning.
Explanation
On the traditional project most of the planning is done on the beginning, while agile projects are planned throughout the project with the help of all stakeholders.
While managing a product development project, the project manager met with the team to determine some of the key tasks that will ensure they produce a high-quality product. What should they consider the most important concept in quality?
Quality is about prevention
Explanation
Quality management is about preventing defects from getting into the hands of the customers. It’s more important to have high quality than high grade. More prevention will lead to less inspection. The cost of quality includes all prevention and inspection costs.
After a project manager is assigned to the project with the project charter, he continues to identify the stakeholders on the project. In this process, he creates the stakeholder register. Which of the following statement is false about the stakeholder register?
It is only updated in the initiating phase of the project.
Explanation
The stakeholder register is updated throughout the project, not just during the initiation phase of the project. All other choices are true.
The agile project team has determined that many of its processes has a lot of waiting and would like to remove all of the waste in the processes. What would be the best tool the agile team can use to improve their processes?
Value stream map.
Explanation
A value stream map is a visual representation of the flow of information through a process in which you can identify waste such as waiting time and optimize the process.
The project manager is having a very difficult time collecting the requirements from the customers. The customers are having a difficult time putting the requirements into logical groupings. What tool can best help them group the requirements?
Affinity Diagram
Explanation
An affinity diagram is used to group large numbers of ideas to be analyzed. A prototype is a functional model of a product given to customers for their feedback. Decomposition is a tool used to break work down into more detailed activities. The requirements documentation would be the output of the process of collect requirements, not a tool.
A project manager working in a large multinational corporation has been assigned to upgrade the company’s website. This project will require inputs for many functional managers across the organization from different countries. Each functional manager would like one of their representatives to be present on the project team. What would be the best tool or technique for handling this scenario in a cost-effective way?
Using Virtual Teams
Explanation
Virtual teams are used in the acquire resources process. Virtual teams are a cost-effective way to build multinational teams. Collocation is when you bring everyone into a single space to accomplish work. Although this may sound like a good solution, it is not cost-effective to have everyone fly to one location. If you were to visit each functional manager, this would not solve the problem of having the functional managers’ representatives on your project.
The project manager has met with the project team and has informed them that his team performance assessments are done, and he would like to speak with each of them individually about the results. What process group is this?
Executing
Explanation
During the executing process group, the project manager will assess the team’s performance and try to improve it through the executing process of developing and managing the team.
While working on a new server upgrade project, the project manager calculates the SPI of the project to be 1.3. The project sponsor would like an explanation for why the SPI is that high. What would be the project manager’s best response?
The project team where able to finish the work faster than anticipiated and this is what led to the project being ahead of schedule.
Explanation
An SPI of 1.3 shows that the project is ahead of schedule by 30%. This could be because the project team is finishing the work faster than originally scheduled. The other choices involve the project being either behind schedule or on schedule, but in this situation, the project is ahead of schedule.
Senior management in the organization would like your project to have as few risks as possible. Which of the following contracts best meet their criteria?
Fixed Price
Explanation
A fixed price contract will have the lowest risk for the project, since the costs of the labor and material are known up front. All other contracts, such as cost reimbursable and time and material will have more risks for the buyers than the sellers. A cost plus fixed fee contract is a type of cost reimbursable contract.
A major portion of a large construction development project was completed by a contractor. The contractor has completed all the work listed in the agreement but also completed other work the contractor felt had to be done. The contractor is asking for more money that was not listed in the agreement, and the project manager feels that what they’re asking for is too much for the additional work that was completed. What should the project manager do next?
Contact claims administration
Explanation
When there is a dispute between a buyer and a seller for additional funds, the dispute should be resolved by going to the claims administration, who can then facilitate the dispute. The other choices will not resolve the dispute between the buyer and the seller.
While working on an agile project, a customer has requested for the team to deploy the software as soon as the iteration is done. The customer has already checked the completed part of the software and has accepted it. The team has refused to deploy the software. What work best explains the team’s refusal?
The iteration is part of the release.
Explanation
Iterations are part of a product that is inspected by the customers. An iteration may not be something that can be released to users since it only represents a few weeks’ worth of work. A release usually includes multiple iterations that are releasable to the customers. In this question the customer has already accepted the iteration, which means there are no errors in it.
The project team has been brought together for the first time to work on the network upgrade project. They were able to learn about the functions they will doing on the project and what their roles will be. What will the team do next, according to Tuckman’s ladder?
Storming
Explanation
The team is currently in the forming stage and will move next to the storming stage. The stages are forming, storming, norming, performing and adjourning.
A project manager is having a very difficult time negotiating with a functional manager. The project manager would like to have Peter, the system administrator, work on the project full time, but the functional manager needs Peter full time to work on the servers throughout the day in case one goes down. After a few days of negotiating, the project manager has determined that he will have Peter from Monday to Wednesday, and the functional manager can have Peter on Thursday and Friday. Although this solution is not the most ideal scenario for the project manager and functional manager, it will have to work for now. What conflict resolution technique was used?
Compromising
Explanation
Compromising is when both sides in a conflict give up something to come up with a solution. Smoothing is when the problem is pushed aside, and forcing is when one side completely wins and the other side completely loses. Problem-solving is the best way, but that would require both sides to come up with a solution in which they both win.
While constructing a new office space, the sponsor has requested the project manager complete the project sooner. While analyzing the work, the project manager has noticed that some of the work can start before the predecessor work is done. What can the project manager do in this scenario to complete the project sooner?
Add lead times between project activities.
Explanation
A lead is an overlap between project activities. This means that work will start before the predecessor work is done. Lag time will add a delay between activities. Slack is the amount of time you can delay an activity without delaying the project. Reserves are the additional time added to the activities for risk.
The project team has finished 60% of the deliverables when management informs the project manager that the project will be canceled immediately and the team will be reassigned to work on a new project that management feels is more important. What should the project manager do right away?
Inform project team, conduct a lessons learned session, and formally release the team from the project.
Explanation
If a project is terminated before completion, the project manager should immediately move to the close project or phase process and formally close the project. The other choices do not involve the activities in the close project or phase process.
When managing risks on a project, the project manager should be aware of the individual project risks and which other project risks?
Overall project risks.
Explanation
Risk generally falls into two levels on a project: individual project risks and overall project risks. All other terms are not different types of risks.
While working on a project, the CEO of the company has informed you that he would like to terminate the project and have you work on a few others projects. What kind of influence does this best represent?
Upwards
Explanation
Upwards influence is for stakeholders above you such as senior management. Downward influence is for those below you such as team members. Sideways influence is for those who are your peers such as other project managers. Outwards influence is for those who are external, such as vendors.
The risk management plan generally outlines the steps the project will take to conduct risk management processes on the project. Which of the following will the risk management plan not include?
Positive risks that could affect the project.
Explanation
The risk register lists both positive and negative risks, not the risk management plan. The risk management plan includes the risk breakdown structure that categorizes risks, roles, and responsibilities for the team members and the methodology they would use to perform the risk processes on the project.
While working on a network upgrade project, a team member installed the network connection and is now configuring the router in order to work with the network connection. The network connection must be done before the router can be configured. This is an example of what kind of dependency?
Mandatory dependency
Mandatory dependency is when activities must be done in a certain order. For example, you must complete A then complete B. Internal dependencies are things that are under the control of the project team, and external dependencies are things that are outside the control of the project team, such as getting a permit. Discretionary dependency is when two activities can be done in any order and they’re not dependent upon each other.
The project manager and the team have worked endless hours to calculate the amount of time it will take to conduct each activity. They would like to document some of the assumptions they made and the constraints they may face when the project is executed. What document will they use for this?
Basis of estimates
Explanation
The basis of estimates documents what they used estimate the activities, such as assumptions, constraints, range of estimates, and the confidence level of the estimates. The duration and cost estimates will not have these components. The project schedule will outline how long the project will take, which includes a network diagram, Gantt chart, and the milestone chart.