6 Schedule Management Terms Flashcards
Activity list
The primary output of breaking down the
WBS work packages.
Alternative analysis
The identification of more than one
solution. Consider roles, materials, tools,
and approaches to the project work.
Analogous estimating
A somewhat unreliable estimating
approach that relies on historical
information to predict what current activity
durations should be. Analogous
estimating is more reliable, however, than
team member recollections. Analogous
estimating is also known as top-down
estimating and is a form of expert
judgment.
Bottom-up estimating
The most accurate time-and-cost
estimating approach a project manager
can use. This estimating approach starts
at “the bottom” of the project and
considers every activity, its predecessor
and successor activities, and the exact
amount of resources needed to complete
each activity.
Control account
A WBS entry that considers the time,
cost, and scope measurements for that
deliverable within the WBS. The
estimated performance is compared
against the actual performance to
measure overall performance for the
deliverables within that control account.
The specifics of a control account are
documented in a control account plan.
Control threshold
A predetermined range of acceptable
variances, such as +/–10 percent off
schedule. Should the variance exceed
the threshold, then project control
processes and corrected actions will be
enacted.
Crashing
A schedule compression approach that
adds more resources to activities on the
critical path to complete the project
earlier. When crashing a project, costs
are added because the associated labor
and sometimes resources (such as faster
equipment) cause costs to increase.
Critical path
The path in the project network diagram
that cannot be delayed, otherwise the
project completion date will be late. There
can be more than one critical path.
Activities in the critical path have no float.
Discretionary dependencies
These dependencies are the preferred
order of activities. Project managers
should use these relationships at their
discretion and should document the logic
behind the decision. Discretionary
dependencies allow activities to happen
in a preferred order because of best
practices, conditions unique to the project
work, or external events. Also known as
preferential or soft logic.
Early finish
The earliest a project activity can finish.
Used in the forward pass procedure to
discover the critical path and the project
float.
Early start
The earliest a project activity can begin.
Used in the forward pass procedure to
discover the critical path and the project
float.
External dependencies
As the name implies, these are
dependencies outside of the project’s
control. Examples include the delivery of
equipment from a vendor, the deliverable
of another project, or the decision of a
committee, lawsuit, or expected new law.
Fast tracking
A schedule compression method that
changes the relationship of activities.
With fast tracking, activities that would
normally be done in sequence are
allowed to be done in parallel or with
some overlap. Fast tracking can be
accomplished by changing the relation of
activities from FS to SS or even FF or by
adding lead time to downstream
activities. However, fast tracking does
add risk to the project.
Finish-to-finish
An activity relationship type that requires
the current activity to be finished before
its successor can finish.
Finish-to-start
An activity relationship type that requires
the current activity to be finished before
its successor can start.
Fragnet
A representation of a project network
diagram that is often used for outsourced
portions of a project, repetitive work
within a project, or a subproject. Also
called a subnet.
Free float
This is the total time a single activity can
be delayed without affecting the early
start of its immediately following
successor activities.
Hard logic
Logic that describes activities that must
happen in a particular order. For
example, the dirt must be excavated
before the foundation can be built. The
foundation must be in place before the
framing can begin. Also known as a
mandatory dependency.