PMP test 3 Flashcards
What best describes a contents of the scope baseline?
Project scope statement and WBS
Does a project manager have more power in a strong, matrix org, weak matrix org, functional org, or never has more power than a functional manager?
Strong matrix
Which structured technique in the manage quality process involves finding a long lasting solution for a discovery issue? 1. Problem-solving. 2. Design for X 3. Performance reviews. 4. Route cause analysis.
Problem solving. Performance reviews as a tool and technique of the control quality. Design for X, root cause analysis and problem-solving are all managed quality techniques. However, designed for X involves optimizing around and identified variable and root causes. Analysis helps reveal the issue, but does not go so far as to work towards and find a solution. Problem-solving involves finding solution, analyzing it, and choosing the best solution of the alternatives and putting the solution into action.
Your team is currently in the process of controlling and verifying the quality of the deliverables on your project. Which two tools would they not be utilizing to accomplish this? 1. Quality audits. 2. Statistical sampling. 3. Design for X. 4. Control chartS
Quality audits, and design for X would not be used during control quality. They would be utilized during the manage quality process.
If there are a number of wrists that have been identified in your project, however, the team has elected, not to change the project plan to deal with the risk, but they have established a contingency reserve in the event that some of these risk or triggered. This is an example of what type of risk mitigation technique? 1. Avoidance. 2. Passive acceptance. 3. Active acceptance. 4. Contingent response strategy
Active acceptance. Recognizing the risk, not changing the plan, but making some contingencies in the event the risk is triggered, as an example of active acceptance. Passive acceptance would be if no contingencies were put in place and avoidance would be correct if the project plan or modified to accommodate the risks.
On a control chart, a source of variation that is intermittent, not inherited the system, and is not predictable as known as: 1. Common or typical cause 2. Specific assignment. 3. Normal or common cause. 4. Special or assignable cause.
On a controlled chart, a source of variation that is intermittent, not inherit in the system, and not predictable, is called a special assignable cause which is an unusual event
You were in the process of closing your project and you were looking at different documents which you have in your archive as project manager. There is an untitled document in which threw out various project meetings. You have documented differences in opinion, situations to be investigated, and emerging or an unanticipated responsibilities. If you want to pick a title for this document, which one of the following would it be? 1. Meeting minutes 2. Risk register. 3. Issue log. 4. Project performance report.
The issue log is a tool used in the managed team process. According to the PM Bach guide an issue, log is used to the document and monitor who is responsible for Rizzoli specific issues by a target date.
Large fluctuations in the periodic expenditure of funds are undesirable for organizational operations. Therefore, the expenditure of funds is frequently reconciled with the dispersement of funds for the project. This is known as: 1. Dispersement reconciliation. 2. Expenditure reconciliation. 3. Funding limit reconciliation. 4. Budget reconciliation.
- Funding limit reconciliation.
What are the different types of leadership styles and their definitions?
- Transformational. Empowers, encourages, and inspires.
- Transactional: performance. Goal objective oriented.
- Servant leader. Leads through empowerment and coaching. The focus is on relationships and collaboration.
- Interactional. Combined transactional, transformational, and charismatic qualities to suit the group dynamics.
- Laissez-Faire: allows a team to make their own decisions.
- Charismatic. Energetic, inspiring, and passionate about convictions, but may be motivated by personal goals.
The project sponsor gives you a project charter and ask you to start working on the project immediately and to provide him with a schedule. What should you do first?
Begin creating a project scope statement. There’s no mention in the question that the schedule is required on an urgent basis, so you need to follow the steps to get to the project schedule. The project scope statement and other planning activities must be completed before the schedule can be created.
Your project is running slightly over budget. You mentioned this to another project manager, who suggest you shift some of your expenses to indirect costs that are not charged to your budget for the project. What do you do? 1. According to the other project manager, examine the project expenses to see if there are any indirect expenses that could be taken off your project. 2. Crash the project. 3. Re-estimate the project cost. 4. Use your contingency reserves.
Re-estimating of the project cost is probably required, but it is not a direct response to the budget overrun problem. Indirect expenses are cost associated with the project and it is not truthful to get them off the project reports. Crashing is not relevant in the situation because there’s no mention of schedule delays. Therefore, you should use your project reserves to cover the budget overruns.
Is a project manager assigned before or after a charter is created?
A project manager is assigned during the project initiating so the project manager will NOT be assigned after the project charter.
True or false… The project manager may initiate changes to the project scope.
True
What are you doing if your manager presents your project is on time and within budget but it’s actually not?
Notify the appropriate management immediately
You’re a manager of sports complex construction project. During the planning phase of the project one of the team members who was asked to prepare activity duration estimate send you an email, including duration estimate for two activities as follows:
A. 15 days plus a lag of four days
B. One month plus a lead of two weeks.
What would be your possible objection to these estimates?
1. The activity duration estimate should have also mentioned the predecessor or successor activity to which the lag or lead is attached.
2. The team member presented the standard deviation of the estimations.
3. Activity duration estimate should not include any lag lead information.
4. All the estates should have the same units to measure.
- Activity duration estimate should not include any information.