Final questions Flashcards
Adding one additional person to 11 member team ads 11 additional communication channels which can increase complexity 11 members at 55 communication channels and 12 members have 66 communication channels. What is the formula to determine this?
N * (N-1) / 2 = # communication channels
What is a method to build a project schedule network diagram used by the majority of project management software applications?
Precedence Diagraming
Which document evolves throughout the risk management process?
Risk register
What document shows the individuals and their responsibilities?
Responsibility Assignment Matrix (RAM)
What are the cost categories for a project and their definitions? Which two would you consider as a first option for cost reduction?
1 variable costs- depends on the amount of work performed by resources
2. Fixed.
3. Indirect.
4. Direct costs - cost belong to project resources which can be skilled down or reduced.
What is a tool and technique for validate scope process?
Inspection
The dependency between two activities is what type of dependency?
Finish to start
What are the stages of team development according to Tuckman?
Storming, Norman, performing, adjourning, and forming
The cost baseline is developed during which process?
Determine budget
Critical path can have a zero, positive, or negative float. T or F
Can have all three but typically it has a negative float.
What is the planning method that involves planning near term items and greater detail than those that are farther often time?
Rolling Wave Planning
When looking at the best path to use in a crash, cost situation add up the cost of crashing the project if it meets the time savings required.
Add up the time savings that you need to shave on the project. And this equals the same number of weeks. Then add up the crash cost to see which one is less.
As a project manager, you were using a fishbone diagram to find the potential risk on your project. What process are you in?
Identify risk
In the plan quality management process, which of the following is not attributable to the cost of nonconformance? 1. Rework. 2. Quality measures. 3. Warranty. 4. Downtime.
- Quality measures.
What allows the team to analyze the variance between what the existing and desired engagement levels of stakeholders are and is used and planned stakeholder engagement?
Stakeholder engagement assessment Matrix (SEAM)