PMP part 2 Flashcards

1
Q

Ann control chart a source of variation that is intermittent not inherent in the system and is not predictable as known as
1. Common or typical cause. 2. Specific assignment. 3. Normal or common cause 4. Special or assignable cause.

A

On a controlled chart, a source of variation that is intermittent not inherit in the system and not predictable is called a special or sable cause which is an unusual event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is one of the tools and technique used in the determined budget process that will reconcile the availability of funds with their expenditure, and it will necessitate the scheduling work to be adjusted to smooth or regulate the expenditures?

A

Funding limit reconciliation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

You were preparing for your meeting with the customer so they can validate the work done so far. What do you need to do to ensure is ready and completed before the meeting begins?
1. The work deliverables have been accepted.
2. Listed change request is available.
3. The deliverables have been tested and verified.
4. The organizations process assets are available.

A

You need to ensure that the deliverables have been tested and verified. The idea is that you never want to show the customer a deliverable that hasn’t first been tested and shown to meet its requirements before asking them to accept it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Should activity duration estimates include any lag or lead information?

A

Activity, duration, estimates or quantitative assessments of the likely work. To complete an activity. They should not include any lag or lead information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In order to be on the safe side, the best option is to choose the resource who is working on an activity with the greatest float to the least minimal impact on that activity. True oe False

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the components of the schedule baseline?

A

Project schedule, milestones, and critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the three main elements of the scope baseline?

A

Project scope statement, work breakdown structure (WBS), and WBS dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the elements of the scope management plan

A

Process for collecting requirements, scope, definition, creation of the word, breakdown, structure, scope, verification, scope, control, rules, and responsibilities, tools, and techniques, and scope baseline maintenance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

As a project manager and a buyer organization, you extended formal imitation that contains a scope of work that seeks a response that will describe the mythology and results that will be provided to your organization. What is this? 1. Request for proposal.2. Request for bid. 3. Request for information. 4. Invitation to bed.

A

Request for proposal since you were sending out a scope along with the invitation, and you were going to give the potential sellers and methodology of the project execution and the results, they should provide you with the proposal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

As the project manager currently involved in the scope management plan processes, you have obtained the large number of ideas during the sessions together, product and project requirements. Which of the following techniques is best suited to have these ideas sorted into groups for review and analysis? 1. Affinity diagrams. 2. Brainstorming. 3. Facilitated workshops. 4. Mind mapping.

A

Affinity diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What type of contract gives the highest possible incentive for a contractor?

A

The cost plus percentage of cost as an award fee type of contract, the contractor has the highest possible incentive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What if an SPI is greater than one?

A

This means the project is ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What if an SPI is greater than one?

A

This means the project is ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What if the CPI is greater than one?

A

The project is under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which one of the following is not part of the executing process group? 1. Acquire resources. 2. Develop team. 3. Manage communications. 4. Cost budgeting.

A

Cost budgeting