PMP Simulation Test – 5 Flashcards
_____are the outcomes of the project and can include components of the project management plan
a. Activity List
b. Deliverables
c. Milestone List
d. Work Performance Data
Deliverables
During project execution, the management requested to reduce project delivery time due to new strategy requirements. They offered extra costs and resources to make it happen. Which Schedule compression technique would you use?
a. Resource smoothing
b. Resource optimization
c. Crashing
d. Fast tracking
Crashing
You are performing Monitor and Control Project Work process. Which is not an input for the process?
a. Work performance information
b. Agreements
c. Work performance data
d. Milestone list
Work performance data
Juan is leading a project with ABA Enterprise. He receives a question on some project deliverables from an external stakeholder. Which of the following could Juan use to answer?
a. RBS
b. WBS
c. OBS
d. SOW
WBS
After developing the project schedule, some of the project critical resources left the company, which limited the available resources. To adjust the schedule to become realistic according to the new limitation. Which Schedule technique would you use?
a. Resource smoothing
b. Resource leveling
c. Crashing
d. Fast tracking
Resource leveling
If a project SPI = 1.05, CPI =1.1, BAC is $150k, EV =$50k. How the project is performing?
a. Under planned cost
b. On planned cost
c. Over planned cost
d. On schedule
Under planned cost
CPI =1.1 then the project is under planned cost.
Garry is performing earned value analysis. The project earned value is $30,000, planned value is $20,000 and actual cost is $25,000. The project cost performance index is_____
a. 0.80
b. 1.20
c. 1.25
d. 1.50
“1.20”
cost performance index=EV/AC= 30/25=1.2
_____includes information on how a seller is performing by comparing the deliverables received, the technical performance achieved, and the costs incurred and accepted against the SOW budget for the work performed.
a. Closed procurements
b. Procurement documentation updates
c. Work performance information
d. Change requests
Work performance information
Rupert has developed the quality management plan. He is trying to translate it into executable quality activities that incorporate the organization’s quality policies into the project. Which process is he performing?
a. Control Quality
b. Validate Quality
c. Manage Quality
d. Plan Quality Management
Manage Quality
Which bid document commonly used when there is a problem in the project and the solution is not easy to determine?
a. Request for bid (RFB)
b. Request for information (RFI)
c. Request for quotation (RFQ)
d. Request for proposal (RFP)
Request for proposal (RFP)
Sam’s project team shows a tendency to work together and adjust their work habits and behaviors to support each other. At which stage does this team stand?
a. Forming
b. Storming
c. Norming
d. Performing
Norming
Sid Corporation contracted Adam to lead an initiative aims to improve the company’s operations efficiency. The company management agreed with Adam that they would measure his success by the initiative’s ability to deliver its intended benefits to the company and by its efficiency and effectiveness in delivering those benefits. What type of OPM will Adam lead?
a. Project
b. Program
c. Portfolio
d. Organizational operations
Program
Samantha is collaborating with her project team to decide whether it is better for the project to be managed by a predictive or adaptive approach and what phases should comprise the project life cycle. Which Project Integration Management Considerations for tailoring is she studying?
a. Project life cycle
b. Management approaches
c. Knowledge management
d. Governance
Project life cycle
Bryan is leading a project that contains some well-known elements with fixed requirements and other elements still unclear, and should be uncovered during execution. Which development life cycles should he use?
a. Predictive life cycle
b. Adaptive life cycle
c. Iterative life cycle
d. Hybrid life cycle
Hybrid life cycle
Axel is analyzing diversity background of the team and their physical location. This is an example of_____
a. Evolving trends in Project Resource Management processes
b. Considerations for tailoring Project Resource Management processes
c. Considerations for agile environments
d. Evolving trends in Project communication Management processes
Considerations for tailoring Project Resource Management processes
Jack is working on Project Knowledge management process and seeking to use effective tools and techniques to share tacit knowledge within the project. Which is not one of these tools and techniques?
a. Communities of practice
b. Knowledge fairs and cafés
c. Project management information system
d. Workshops
Project management information system
While performing manage quality process, the project manager used a technique to identify opportunities for process improvements. Which technique did he use?
a. Root cause analysis
b. Process analysis
c. Document analysis
d. Alternatives analysis
Process analysis
_____includes which deliverables have been accepted and which have not been accepted and the reasons why.
a. Accepted deliverables
b. Acceptance criteria
c. Work performance information
d. Requirements documentation
Work performance information
Bryan is studying the influence of rules, standards, and guidelines specific to the project application-area on control quality process. Under which category does these elements fall?
a. Emerging practices
b. Enterprise environmental factors
c. Organizational process assets
d. Expert judgement
Enterprise environmental factors
_____is compared to actual results to determine if a change, corrective action, or preventive action is necessary.
a. Scope baseline
b. Requirements traceability matrix
c. Scope management plan
d. Change management plan
Scope baseline
A project activity duration based on analysis of the best-case scenario is 20 days, based on analysis of the worst-case scenario and duration of the activity is 28 days, based on realistic effort assessment for the required work is 23 days. Based on triangular distribution, what is the activity duration?
a. 23.67
b. 23.33
c. 26.33
d. 25.33
“23.67”
Triangular distribution.
cE = (cO + cM + cP) / 3= 20+23+28=23.67
Which scope statement element does include project management reports and documentation?
a. Product scope description
b. Deliverables
c. Acceptance criteria
d. Project exclusions
Deliverables
_____are also known as tally sheets.
a. Spreadsheets
b. Checklists
c. Check sheets
d. All of the above
Check sheets
You are directing and managing project work and need to review the links between product requirements and the deliverables that satisfy them. Which document should he review?
a. Requirements traceability matrix
b. Requirements documentation
c. Product scope
d. Requirements management plan
Requirements traceability matrix