PMP Simulation Test – 1 Flashcards
You are creating a project schedule for your web site development project. Your first milestone is “Delivery of Screen Visual Designs”. What should be the duration for this milestone?
A-) Total time spent for development of all screens’ visual designs
B-) Time spent for development of last screen’s visual design
C-) Milestone duration should be asked to developers who designed screens
D-) Zero
Zero
In your project, you establish clear expectations regarding acceptable behavior by project team members. You believe that early commitment to clear guidelines will decrease misunderstanding and increase productivity. These expectations and guidelines are also known as: A-) Ground rules B-) Code of conduct C-) Communication rules D-) Team base rules
Ground rules
All of the following are types of contract EXCEPT: A-) Fixed Price B-) Cost Reimbursable C-) Reciprocal D-) Time and Material
Reciprocal
There are 3 types of contract in procurement management:
Fixed Price Contract Cost Reimbursable Contract Time and Material Contract
You are managing a project which is for manufacturing wiper rubbers for an automobile. You use control charts as a quality management tool. The optimum length of the wiper rubbers should be 40.00 cm and allowable limits are 39.95cm and 40.05cm. Following table shows the measurements made at the end of the process:
A-) Process is out of control
B-) Process is in control
C-) Number of measurements is not sufficient
D-) Control charts as a quality management tool is not appropriate for this process
Process is out of control
You know that making early scope definition is critical since the ability to influence cost is:
A-) Greatest at the middle of the project
B-) Greatest at the early stages of the project
C-) Greatest at the end of the project
D-) Changing due to environmental factors
Greatest at the early stages of the project
Your colleague Lisa, a junior project manager, is about to complete her project. Her customer requests an additional item to be delivered in the project. What would you recommend to Lisa?
A-) Deliver the additional requested item, because you will satisfy the customer
B-) Deliver the additional requested item, because customer might not accept the final product
C-) Explain the customer that requested additional item does not have a business sense
D-) Process the requirement through the integrated change control process
Process the requirement through the integrated change control process
In your project, you identified the fire risk at storage, which may cause you to lose some of the materials needed for your project. During meetings, the project team decided to acknowledge the risk and sponsor recommended creation of a contingency reserve ( with %7 of the project budget) which could be used in case of fire at storage. Which of the following strategies has been used for this risk? A-) Risk mitigation B-) Risk acceptance C-) Risk avoidance D-) Risk transfer
Risk acceptance
In order to provide required information to project stakeholders on time, you have completed Manage Communications process. Which of the following is NOT an output of the Manage Communications process: A-) Feedback from stakeholders B-) Stakeholder notifications C-) Lessons learned documentation D-) Change requests
Change requests
Due to the potential for change, the development of the project management plan is an iterative activity and is progressively elaborated throughout the project’s life cycle. Project management plan is updated in all of the following process EXCEPT: A-) Develop Project Management Plan B-) Close Project or Phase C-) Direct and Manage Project Work D-) Monitor and Control Project Work
Close Project or Phase
Your Company will subcontract one of its software projects to a vendor. Thus, you have determined the technical criteria to evaluate the vendors. This is an example of: A-) Project statement of work B-) Source selection criteria C-) Constraint D-) Risk
Source selection criteria
All of the following are strategies for positive risks or opportunities EXCEPT: A-) Exploit B-) Enhance C-) Share D-) Mitigate
Mitigate
Using appropriate interpersonal skills allow project managers to capitalize on the strengths of all team members. All of the following are interpersonal skills that a project manager uses EXCEPT: A-) Leadership B-) Influencing C-) Socializing D-) Effective decision making
Socializing
Which of the following knowledge areas include processes belonging to five Project Management Process Groups: Initiating, Planning, Executing, Monitoring & Controlling, Closing? A-) Procurement Management B-) Stakeholder Management C-) Integration Management D-) Quality Management
Integration Management
Your Company is a vacuum cleaner manufacturer. A recently produced model of the vacuum cleaner has been sold a lot and current capacity of the manufacturing lines cannot reach the demand of the market. Your company decided to create new manufacturing lines in order to produce more vacuum cleaners and assigned you as the project manager for this project. Who is the user for this project?
A-) Future users of vacuum cleaners which will be produced from new manufacturing lines
B-) Workers who will use new manufacturing lines
C-) Project Sponsor
D-) Project Team
Workers who will use new manufacturing lines
All of the following are part of Direct and Manage Project Work activities EXCEPT:
A-) Change control meetings
B-) Manage sellers and suppliers
C-) Manage stakeholders and their engagement
D-) Create project deliverables
Change control meetings
Which of the following describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services or results? A-) Project Statement of Work B-) Procurement Statement of Work C-) Project Scope Statement D-) Scope Baseline
Procurement Statement of Work
The procurement statement of work describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services or results
Project scope statement includes the description of the project scope. Project scope statement also includes: A-) Scope Baseline B-) Assumptions C-) WBS D-) WBS Dictionary
Assumptions
The Project scope management includes the description of the project scope, major deliverables, assumptions, and constraints.
You are managing a software project. A junior software developer, David, in your project informs you that his first screen development task will take 9 days, and this will exceed the planned time for this activity which was 5 days. In order to check status of other developers, you ask for the status reports and forecasts. Which process group are you in? A-) Initiating B-) Monitoring and Controlling C-) Executing D-) Planning
Executing
You are the project manager of a hydroelectric power plant construction project. The government has regulations that ensure the neighborhood is not adversely affected by the plant of your project. For your project, this regulation is considered as a/an: A-) Assumption B-) Ethical Practice C-) Activity D-) Constraint
Constraint
All the following statements regarding the creation of duration estimates are correct EXCEPT:
A-) Mathematical analyses like CPM, GERT, and PERT indicate the dates on which the activity can be scheduled, given resource limits and other constraints.
B-) Duration compression techniques, including fast-tracking and crashing, can help in decreasing the project schedule
C-) The duration of the project is the sum of the duration of all the tasks in the project.
D-) WBS classification allows for useful activity ordering and sorting.
The duration of the project is the sum of the duration of all the tasks in the project.
You are a project manager. You have completed the project. While reviewing the costs, you observed that most of the project`s budget was utilized for activities performed in the processes of one particular process group. This Process Group is:
A-) Planning Process Group
B-) Executing Process Group
C-) Monitoring and Controlling Process Group
D-) Closing Process Group
Executing Process Group
You are currently in the execution phase of your project. You will be doing all of the following EXCEPT:
A-) Expending most of the project budget
B-) Implementing planned methods and standards with the team
C-) Reviewing all prior information from the previous phase closures.
D-) Managing risks and implementing risk response activities with the team
Reviewing all prior information from the previous phase closures.
In your project, you are in the Identify Risks process and trying to determine and document the risks and their characteristics. Who should be part of this process?
A-) Project Manager and Relevant managers from customer
B-) Project Manager, project team members, subject matter experts and customer
C-) Project Manager and senior team members
D-) All relevant stakeholders
All relevant stakeholders
All of the following are constraints in Estimate Activity Durations process EXCEPT: A-) Available skilled resources B-) Contract terms C-) Contract requirements D-) Availability of information
vailability of information