PMP Simulation Test – 4 Flashcards
_____is about using project processes effectively. It involves following and meeting standards to assure stakeholders that the final product will meet their needs, expectations, and requirements.
a. Plan Quality
b. Manage Quality
c. Quality assurance
d. Control Quality
Quality assurance
_____is a significant point or event in a project.
a. Phase
b. Gate
c. Activity
d. Milestone
Milestone
A project manager needs to know how the Control Quality process will verify compliance to it. Which input should he review?
a. Quality management plan
b. Quality measurement metrics
c. Quality metrics
d. Test and evaluation documents
Quality metrics
_____contains information about requirements, including how to validate them.
a. Requirements documentation
b. The requirements traceability matrix
c. The requirements management plan
d. The scope baseline
The requirements traceability matrix
A project manager is working on influencing team behavior, managing conflict, and resolving its issues. Which process is he performing? Acquire Resources b. Develop Team c. Manage Team d. Control Resources
Manage Team
_____is a projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.
a. EAC
b. ETC
c. VAC
d. BAC
VAC
Alex is comparing the processes used to create the quality measurements and validate actual measurements to determine their level of correctness. Which input is he reviewing?
a. Quality metrics
b. Quality control measurements
c. Quality reports
d. Quality management plan
Quality control measurements
Michael intends to procure part of his project with well-defined requirements with no expected significant changes to the scope. Which contract type best matches Michael’s project?
a. Fixed-Price Contracts
b. Cost-Reimbursable Contracts
c. Time and Material Contracts
d. None of the Above
Fixed-Price Contracts
Company XYZ assigned Keith to manage a construction project. This is his first project in this field. While he tries to sequence project activities, he seeks advice on preferred logic of some project activities from a colleague. Which of the following Keith is trying to identify?
a. Internal Dependencies
b. External Dependencies
c. Mandatory Dependencies
d. Discretionary Dependencies
Discretionary Dependencies
A project manager is performing “Close project” process. As he needs to review the versions and baselines of all official organizational standards, policies, procedures, and other project documents. Which of the following he should review first?
a. Business documents
b. Procurement documentation
c. Configuration management knowledge base
d. Project documents
Configuration management knowledge base
A project manager is working on “Close project” process. Which of the following is not an output he should expect?
a. Accepted deliverables
b. Final product
c. Final report
d. Organizational process assets update
Accepted deliverables
_____is a measure of the cost performance that must be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the budget available.
a. CPI
b. SPI
c. TCPI
d. BAC
TCPI
During project review the following performance data were revealed, VAC= 0k and AC=200k. What is the EV?
a. 200k
b. 250k
c. 190k
d. Cannot say
200k
EV=AC= 200k
Jack is performing Develop Team process and he needs to identify the team and members’ roles and responsibilities. Which input should he review?
a. Team charter
b. Resource management plan
c. Project team assignments
d. Resource calendars
Project team assignments
_____specifies the acceptable range used in determining realistic activity duration estimates and may include an amount for contingencies.
a. Units of measure
b. Control thresholds
c. Level of accuracy
d. Level of precision
Level of accuracy
According to the Tuckman ladder model order, the project team moved to Performing stage. Before moving, what was stage of the team?
a. Performing
b. Forming
c. Norming
d. Storming
Norming
During the project closure, Stephan is preparing a presentation to justify the project and explain the benefits the project will generate against the costs the project consumed. Which document should he review?
a. Project charter
b. Project management plan
c. Business documents
d. All of the above
Business documents
_____is a financial analysis tool used to estimate the strengths and weaknesses of alternatives in order to determine the best alternative in terms of benefits provided.
a. Trend analysis
b. Earned value analysis
c. Cost-benefit analysis
d. Cost of quality (COQ)
Cost-benefit analysis
Billy is working on estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work. Which process is he performing?
a. Plan Resource Management
b. Estimate Activity Resources
c. Manage team
d. Control Resources
Estimate Activity Resources
A project manager is working to identify the need for team development strategies based on variations, if any, during the project execution. Which input should he review?
a. Team charter
b. Project schedule
c. Project team assignments
d. Resource calendars
Project schedule
Project x is under review, the project performance data are as follows, AC 150k, EV 140, PV 130. How the project is performing?
a. Project is behind schedule
b. Project is ahead schedule
c. Project is on schedule
d. Cannot say
Project is ahead schedule
Which of the following deliverables fulfillment of project objectives may produce?
a) Unique capability
b) Unique product
c) Unique result
d) All of the above
All of the above
Michael is managing a project with well-defined requirements and no significant changes to the scope are expected. Which of the following best matches Michael’s project?
a) Fixed-Price Contracts
b) Cost-Reimbursable Contracts
c) Cost-Reimbursable Contracts Time and Material Contracts
d) None of the Above
Fixed-Price Contracts
Steve is analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives numerically. Which process is he performing?
a. Plan Risk Management
b. Identify Risks
c. Perform Qualitative Risk Analysis
d. Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis