PMP Questions 1 Flashcards

1
Q

A project is…

A

something temporary in nature that delivers a product service or result.
Has start and finish,
Creates something new or improves on what exists.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Predictive Projects

A

Deliverable at the end with the goal of controlling the scope, costs, and schedule. Little change or change adverse. (Waterfall, traditional)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Adaptive Projects

A

Incremental, Iterative, and Agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Incremental projects deliver…

A

products or value in “batches” or increments with the goal of speed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Iterative projects embrace…

A

change by getting customer feedback to make changes over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Agile projects are…

A

iterative and incremental with the desire to get customer feedback and generate value as early as possible while providing continuous improvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What comprises the scope baseline?

A

Scope Statement, WBS, WBS Dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is needed before you can determine a schedule, budget, or resources?

A

The scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The Scope Management Planning creates…

A

the Scope Management Plan and the Requirements Management Plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The Scope Management Plan explains…

A

how you will develop, maintain and control the Scope Statement and WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Collecting the requirements involves…

A

creating the Requirements Traceability Matrix and Requirements Documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Defining the scope means…

A

creating the Scope Statement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The Scope Statement is…

A

what the Product and Project will be
what the Product & Project won’t be
What variations, tolerances, thresholds, and alternatives there are
The Acceptance criteria of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Create a WBS…

A

Highest Level = Planning Package (where the PM manages the project from) = Control Accounts
Lowest Level = Work Package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Work packages get decomposed when…

A

defining activities (Schedule Management)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Predictive Estimating tool: Analogous (Top-Down) =

A

Using past experience or lessons learned to form your estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Predictive Estimating Tool: Parametric =

A

Using a historical and multiplying it by the amount of times you have to repeat it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Predictive Estimating Tool: Bottom-Up =

A

Most accurate, but most timely
A way to determine how to get back on track

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Sequencing activities and estimating activity duration happen…

A

at the same time and end up on the Network Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Schedule Management/Network Diagramming: Forward Pass

A

Largest number wins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Schedule Management/Network Diagramming: Backwards Pass

A

Critical Path Wins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

In Project Network Diagramming, Slack, Float, and Total Float…

A

are all the same thing - the amount of time an activity can be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is free float?

A

The amount of time that an activity can use without affecting the successor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are schedule compression options?

A

Crashing: Adds resources to an activity to get it done faster. Only crash the critical path.
Fast-Tracking: increased risk (never add risk without approval)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Early Start ….
Late Start ….

A

Early Finish
Late Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Cost Baseline

A

Time phased spending of money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Budget at Completion

A

Aggregated costs + contingency reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

The contingency reserve is for…

A

things in the risk register (you knew, you planned, and you thought it might happen)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Management reserve is for…

A

things I did not plan for. Must ask senior management for the money.
(You didn’t know, you couldn’t have planned for, you are surprised, or was unexpected)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

SV +$

A

Ahead of Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

SV -$

A

Behind Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

CV +$

A

Under Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

CV -$

A

Over Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

CPI > 1

A

Under Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

CPI <1

A

Over Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

TCPI =

A

(BAC-EV)
_________
(BAC-AC)

or
EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Earned Value (EV)

A

How much has been completed to this point?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Actual Costs (AC)

A

How much have you spent so far?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Estimate at Completion (EAC)

A

How much you will spend by the end?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Estimate to Complete (ETC)

A

How much do you have left to spend?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Variance at Completion (VAC)

A

What is the difference in saving or losses from your original budget?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

TCPI

A

<1 = Good
>1 = Bad
Measure of Efficiency for the remainder of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Resource Management Plan

A

How to manage people, equipment, materials, and supplies.
Creates Team Charter

44
Q

Estimate Activity Resources requires

A

Activity list

45
Q

Responsibility Assignment Matrix (RAM)

A

RACI
Responsible, Accountable, Consulted, Informed
RASI
Responsible Accountable, Supported, Informed

46
Q

Communication Channels equation

A

(N(N-1))/2

47
Q

What are the two required parts of communication security?

A
  1. List of people who have access
  2. Specified Technology to use
48
Q

What is the communication Model?

A

Sender “Encodes”
Receiver “Decodes”
Only the intended receiver can decode a message

49
Q

Osmotic Communication

A

Communication in the background that is picked up by the team due to environmental/working conditions (co-location)

50
Q

High bandwidth communication

A

Face to Face comms
Most preferred.

51
Q

Hierarchical Communication Dimension is…

A

Upward, Downward, and horizontal.

52
Q

Risk management plan risk definitions should…

A

have clear definitions to ensure everyone knows what high, medium, and low is.

53
Q

What should be taken and documented in the Risk Management plan to ensure we can meet expectations.

A

An evaluation of Stakeholder’s risk tolerance

54
Q

A Risk is…

A

something positive or negative that may impact your project and has a risk response planned (annotated on the risk register).

55
Q

An Issue is…

A

something that may impact your project, is ALWAYS negative. (annotated and tracked on the issue log).

56
Q

Before creating a workaround…

A

check the risk register to see if a risk response was already planned.

57
Q

If an issue is not on the risk register (did not plan for it)…

A

the create a workaround for the issue.

58
Q

Management reserve is used for…

A

unanticipated issues (issues not on the risk register).

59
Q

Contingency reserve is used for…

A

anticipated risks (on the risk register).

60
Q

Burn down chart

A

Used to measure the remaining tasks and can forecast estimated time for completion

61
Q

Burn up chart

A

Used to measure work completed and can forecast estimated time for completion

62
Q

Kanban Board

A

Information Radiator that shows the work in progress and uses a Pull method. Aids in identifying bottlenecks and delays.

63
Q

Information Radiators

A

Visual tools used to display the status or information of the project.
Agile Artifacts that project the status of the project so it is visible and transparent.
Kanban boards
Backlogs
Burnup/Burn-down charts
Flowcharts
Roadmaps
Vision Statements

64
Q

Quality Reports

A

Used to determine if desired quality is being achieved

65
Q

Work performance data

A

the raw observations of the project work

66
Q

Work Performance Information

A

The analysis of the observations made compared to the plan

67
Q

Work Performance Report

A

Reports providing context on the current status of the project for stakeholders

68
Q

Stakeholder analysis

A

To identify stakeholders. Categorized stakeholders into groups, identify expectations, and requirements of each stakeholder or group of stakeholders

69
Q

Ways to assess stakeholders

A

Power/Interest Grid
Power/Influence Grid
Salience Model

70
Q

Stakeholder Register

A

List of all stakeholders with expectations, requirements, importance, influence, and support.
Updated throughout project.

71
Q

Stakeholder Engagement Plan

A

Ensures a plan of action for dealing with stakeholders based on expectations of the project and established requirements. Includes SEAM

72
Q

Stakeholder Engagement Assessment Matrix (SEAM)

A

shows current state vs desired state for each stakeholder or group

73
Q

Kaizen

A

change is good

74
Q

Cost of conformance

A

Prevention costs vs appraisal cost

75
Q

cost of non-conformance

A

internal vs external failure

76
Q

What is needed for quality to take place?

A

the organization needs to have a shared culture of quality

77
Q

Why should you conduct audits?

A

to ensure your processes work and your people are following the process

78
Q

Inspect deliverables to ensure…

A

they meet requirements specifications.

79
Q

Look for opportunities to…

A

improve, become more efficient, save costs, and shorten the time it takes to reach the customer’s hands.

80
Q

Deliverables workflow…

A

Collect Requirements
Create Scope Baseline
Do the Work
Internal Inspection - Quality Control
Verified deliverables to customer for inspection - Validate Scope
Accepted Deliverables -> Close out project/phase
Admin/Legal/Financial

81
Q

Project Baseline Performance Tracking

A

Baselines, Work performance ->
Control Scope/Schedule/Costs ->
Current State & Forecasts

82
Q

What kind of activity is ‘Identifying Stakeholders’?

A

Continuous Activity

83
Q

Organizational Structures

A

Functional
Matrix
Projectized

84
Q

Organizational Structure - Functional

A

PM Authority - little to none
Resource availability - little to none
Who Manages? Functional Manager
PM role? Part time
PM Admin Staff? Part time

85
Q

Organizational Structure - Matrix

A

Weak - Balanced - Strong
PM Authority: Low, Mod, High
Resources: Low, Mod, High
Manager?: Funct. Mng, Mixed, PM
PM Role: Part time, full, full
PM Admin Staff: part, part, full

86
Q

Organizational Structure - Projectized

A

PM Authority: High, almost total
Resources?: High to almost total
Manager?: PM
PM Role?: Full-time
PM Admin Staff?: Full-time

87
Q

Predictive Project Artifacts

A

Business Documents: Business Case, Business Needs Document, Benefit Management Plan
Project Charter: Names the Project Manager, and provides authority. Signed by the sponsor.

88
Q

McGregor’s Theory X

A

Lack Integrity
Avoid Responsibility
Work as little as possible
Prefer direction

89
Q

McGregor’s Theory Y

A

Have Integrity
Work towards objectives
Wants to achieve
Will make decisions

90
Q

McClelland’s Achievement Theory

A

Achievement
Power, Emotional Needs, Affiliation

91
Q

Frederick Herzberg’s Two Factor Theory - Job Dissatisfaction

A

Hygiene Factors
Working Conditions
Coworker relations
Policies and rules
Supervisor quality
Base wage and salary
Status

92
Q

Frederick Herzberg’s Two Factor Theory - Job Satisfaction

A

Motivation Factors
Achievement
Recognition
Responsibility
Work Itself
Advancement
Personal Growth

93
Q

Maslow’s Hierarchy of Needs

A

Self-Actualization - desire to become the most one can be
Esteem - respect, self-esteem, status, recognition, strength, freedom
Love and belonging - friendship, intimacy, family, sense of connection
Safety needs - personal security, employment, resources, health, property
Physiological needs - air, water, food, shelter, sleep, clothing, reproduction

94
Q

Tuckman’s Ladder Model of Team Development

A

Forming
Storming
Norming
Performing
Adjourning

95
Q

Forming - Team Leader Role

A

Outlines mission; Looks for agreement on team roles, rules, and guidelines for decision making

96
Q

Storming - Team Leader Role

A

Team deals with confusion and conflict over goals, decision-making, roles and control
TL Facilitates discussion; ensures common understanding of agreements

97
Q

Norming

A

Team accepts goals, roles, rules, works positively
TL - Encourages norming process; supports and coaches, celebrates success

98
Q

Performing

A

Team focuses on achieving goals; personal growth for team members; conflict handled positively
TL - Encourages high performance; facilitates communication; celebrates success

99
Q

What is the worst conflict management approach?

A

Withdraw/Avoid

100
Q

What is the best conflict management approach?

A

Collaborate/Problem Solve (takes time)

101
Q

Conflict Management Approaches

A

Withdraw/Avoid (Worst)
Smooth/Accommodate (giving in rather than addressing issue)
Compromise/Reconcile (Both sides lose something)
Force/Direct (When resolution needs to be immediate)
Collaborate/Problem Solve (Best but takes time)

102
Q

Active Listening - Reflecting

A
  • Repeat the gist of the message
  • Verify your understanding of the message
103
Q

Active Listening - Attending

A
  • Lean slightly toward the speaker
  • Stay at eye-level
  • Maintain eye contact without staring
104
Q

Active Listening - Following

A
  • Respond with non-verbal gesture or verbal response
  • Ask questions
  • Allow speaker moment to collect their thoughts
105
Q

Servant Leadership Duties

A
  • Shield the team from interruptions
  • Remove impediments to progress
  • Communication (and re-communicate) the project vision
    Carry food and water (have essential resources to nourish the team)
106
Q

Leadership Tasks

A
  • Practice Transparency through visualization
  • Create a safe environment for experimentation
  • Experiment with New Techniques and processes
  • Share Knowledge through collaboration
  • encourage emergent leadership via a safe environment
107
Q
A