PMP Acronyms Flashcards
AC
Actual Cost
The actual costs incurred for the work performed during a specific time period [Earned Value Mngt, Cost/Sched Mngt]
ACR
Approved Change Request
A formal proposal to modify a document, deliverable, or baseline that has been approved [All PMP]
BAC
Budget at Completion
The sum of all budgets for the work to be performed [Earned Value Mngt, Cost/Sched Mngt]
BCR
Benefit Cost Ratio
The relationship between the cost and benefits of a proposed project [Integration Mngt]
CCB
Change Control Board
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating those decisions. [Integration Mngt]
COQ
Cost of Quality
All costs incurred over the life of the product by investment in preventing non conformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements. [Earned Value Mngt, Cost/Sched Mngt]
CPAF
Cost Plus Award Fee
A category of contract that involves payments to the seller for all legitimate actual costs incurred for completed work, plus an award fee representing seller profit [Procurement Mngt]
CPFF
Cost Plus Fixed Fee
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (defined by the contract) plus a fixed amount of profit (fee) [Procurement Mngt]
CPI
Cost Performance Index
The measure of cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.[Earned Value Mngt, Cost/Sched Mngt]
CPIF
Cost Plus Incentive Fee
A type of cost-reimbursable contract where the buyer reimburses the seller for the seller’s allowable costs (defined by the contract) and the seller earns its profit if it meets defined performance criteria [Procurement Management]
CPM
Critical Path Method
A method used to estimate the minimum project duration and determine the amount of schedule flexibility on the logical network paths within the schedule model [Schedule Management]
CR
Change Request
A formal proposal to modify a document, deliverable, or baseline [All]
CV
Cost Variance
The amount of budget deficit or surplus at any given point in time. [Earned Value Mngt, Cost/Sched Mngt]
DPMO
Defects Per Million Opportunities
The average number of defects per unit observed during an average production run divided by the number of opportunities to make a defect on the product under study during that run normalized to one million. [ Quality Management]
EAC
Estimate at Completion
The expected total cost of completing all the work which includes all costs incurred thus far on the project and all expected cost estimates to complete the project. [Earned Value Mngt, Cost/Sched Mngt]
EEF
Enterprise Environmental Factors
Conditions, not under immediate control of the team, that influence, constrain, or direct the project, program, or portfolio. [All]
EF
Early Finish Date
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints. [Schedule Management]
EMV
Expected Monetary Value
The value (expressed as a monetary value) assigned to a risk based on the probability of occurrence multiplied times estimated financial impacts [Risk Management]
ES
Early Start Date
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints [Schedule Management]
ETC
Estimate to Completion
The expected total cost to finish the remainder of the work on the project [ Earned Value Mngt, Cost/Sched Mngt]
EV
Earned Value
The measure of all work performed on a project at a specific point in the project. [Earned Value Mngt, Cost/Sched Mngt]
EVM
Earned Value Management
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress. [Earned Value Mngt, Cost/Sched Mngt]
FF
Finish to Finish
A logical Relationship in which the successor activity cannot finish until a predecessor has finished [Schedule Management]
FFP
Firm Fixed Price
A type of fixed price contract where the buyer pays the seller a set amount (defined by the contract) regardless of the seller’s costs. [Procurement Management]
FPEPA
Fixed Price with Economic Price Adjustment
A fixed price contract, but with special provision allowing for predefined final adjustments to the contract price due to changed conditions, such as inflation changes, or cost increases (or decreases) for specific commodities. [Procurement Management]
FPIF
Fixed Price Incentive Fee
A type of contract where the buyer pays the seller a set amount (defined by the contract), and the seller can earn an additional amount if the seller meets predefined performance criteria. [Procurement Management]
FS
Finish to Start
A logical relationship in which the successor activity cannot start until a predecessor has finished. [Schedule Management]
IFB
Invitation for Bid
Generally, this term is equivalent to Request for Proposal. However, in some application areas, it may have a narrower or more specific meaning. [Procurement Management]
IRR
Internal Rate of Return
The discount rate that makes the NPV equal to zero. [Integration Management]