PMP FORMULAS Flashcards
PERT
(P+4M+O)/6
STANDARD DEVIATION
(P-O)/6
VARIANCE
[(P-O)/6]SQUARED
FLOAT OR SLACK
LS (LATE START)-ES (EARLY START) AND LF (LATE FINISH)- EF (EARLY FINISH)
CV (COST VARIANCE) FORMULA
EV (EARNED VALUE)-AC (ACTUAL COST)
SV (SCHEDULE VARIANCE) FORMULA
EV (EARNED VALUE) -PV (PLANNED VALUE)
CPI (COST PERFORMANCE INDEX) FORMULA
EV (EARNED VALUE)/AC (ACTUAL COST)
ETC (EST TO COMPLETE) FORMULA
EAC (ESTIMATE AT COMPLETE) - AC (ACTUAL COST)
PERCENT COMPLETE
EV/BAC (BUDGET AT COMPLETE)
EAC (ESTIMATE AT COMPLETE) FORMULA
BAC/CPI
AC+ETC
AC+BAC-EV
AC+(BAC-EV)/CPI
ETC (ESTIMATE TO COMPLETE)
EAC (EST AT COMPLETE)- AC (ACTUAL COST)
VAC (VARIANCE AT COMPLETION)
BAC - EAC
TCPI (TO COMPLETE PERFORMANCE INDEX)
TCPI < 1.0 IS GOOD. EFFICIENCY TO COMPLETE IS LESS THAN PLANNED
(BAC - EV) / (BAC - AC)
NPV (NET PRESENT VALUE)
BIGGER IS BETTER
IRR (INTERNAL RATE OF RETURN)
BIGGER IS BETTER
BENEFIT COST RATIO
BIGGER IS BETTER
PAYBACK PERIOD
LESS IS BETTER
NET INVESTMENT/AVG ANNUAL CASH FLOW
ORDER OF MAGNITUDE ESTIMATE
- 25% + 75%
PMBOK -50% + 100%
BUDGET ESTIMATE
- 10% + 25%
DEFINITIVE ESTIMATE
-5% + 10%
COMMUNICATION CHANNELS
N(N-1)/2
EXPECTED MONETARY VALUE
PROBABILITY * IMPACT
POINT OF TOTAL ASSUMPTION
(CEILING PRICE - TARGET PRICE)/BUYER’S SHARE RATIO + TARGET COST
1SIGMA
68.27%
2SIGMA
95.45%
3SIGMA
99.73%
6SIGMA
99.99985%
RETURN OF SALES (ROS)
NET INCOME BEFORE TAXES (NEBT)/TOTAL SALES
OR
NET INCOME AFTER TAXES (NEAT)/TOTAL SALES
ROA (RETURN OF ASSETS)
NEBT/TOTAL ASSETS
OR
NEAT/TOTAL ASSETS
ROI (RETURN OF INVESTMENT)
NEBT / TOTAL INVESTMENT
OR
NEAT / TOTAL INVESTMENT
SPI (SCHEDULE PERFORMANCE INDEX)
SPI = EV/PV (EARNED VALE / PLANNED VALUE)
% COMPLETE
EV / BAC X 100
TOTAL COST
CONTRACT INCENTIVES
ACTUAL COST + CONTRACT COST
CONTRACT COST
CONTRACT INCENTIVES
BONUS + FEE
BONUS
cONTRACT INCENTIVES
SAVINGS x PERCENTAGE
SAVINGS
CONTRACT INCENTIVE
TARGET COST - ACTUAL COST
MODE
THE “MOST FOUND” NUMBER
MEAN
AVERAGE
RANGE
LARGEST - SMALLEST MEASURE
MEDIUM
NUMBER IN THE MIDDLE
OR
AVERAGE OF 2 MIDDLE NUMBERS
COQ (COST OF QUALITY)
REVIEW EFFORTS + TEST EFFORTS + TRAINING EFFORTS + REWORK EFFORTS + EFFORTS OF PREVENTION/TOTAL EFFORTS) X 100%
PDM
P 177
TAKE LONGEST DURATION OF EACH ACTIVITY AND ADD.
CRITICAL PATH
NO FLOAT AND LONGEST DURATION OF ACTIVITIES.
P 177
FOR ESTIMATING DURATION WITHOUT WEIGHT USE WHAT?
USE SIMPLE AVERAGE
ROR = Rate of Return
(total return/initial invenstment)*100/years
SPI formula
EV/PV
EV Formula
SPI*PV
EXPECTED PROFIT FORUMLA
EACH ALTERNATIVE =PERCENTAGE*DOLLAR AMOUNT OF PROFIT
THEN ADD ALL ALTERNATIVES
P 339
FFP = FIRM FIXED PRICE
CONTRACT TYPE FOR FIXED - SCOPE PROJECT
FPIF=FIXED PRICE INCENTIVE FEE
CONTRACT TYPE WHEN SCOPE IS FIXED BUTH NEED FLEXIBILITY FOR PERFORMANCE GOALS
COST REIMBURSABLE
CONTRACT TYPE WHEN SCOPE CANNOT BE PRECISELY DEFINED