PMI Q&A Flashcards

1
Q

The team uses something similar to estimate, like data
from a similar project

(Estimating)

A

Analogous

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A builder uses a measurement to estimate, like $55 a
meter or $100 an hour

(Estimating)

A

Parametric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The team adds together the smallest pieces in the WBS to
get an overall estimate

(Estimating)

A

Bottom-up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A team takes the average of the Optimistic, Most Likely
and Pessimistic estimates

(Estimating)

A

3-point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The team need to see their project activities visually
on a calendar

(Project Tools)

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A project manager wants to see the number of items
completed each day

(Project Tools)

A

Throughput Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

An agile team wants to show the planned trend of
work, versus actual trend of work

(Project Tools)

A

Burndown Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Business Analyst needs to show how customer
requirements meet their completed deliverables

(Project Tools)

A

Requirements Traceability
Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly