PMI - Planning and Managing the Project Budget Flashcards
the basics of creating budgets and estimating and controlling costs. You'll explore cost forecasts, estimating using methods like estimate to complete (ETC), estimate at completion (EAC), cost performance index, and bottom-up and analogous estimating.
Budget at completion (BAC)
Definition
The total authorized budget for the project. (at start of project)
Actual Cost (AC)
Definition
The total cost actually incurred for work performed for an activity, AC is simply the amount of money you’ve spent so far.
Planned Value (PV)
Definition
The budgeted amount assigned to the work scheduled to have been completed. The assumption is that the work is planned in a uniform manner.
Planned Value (PV)
Formula
Budget at completion (BAC) × (time passed ÷ total schedule time) = Planned value (PV)
BAC × (time passed ÷ total schedule time) = PV
Earned Value (EV)
Definition
The value of completed work, expressed in terms of the budget assigned to that work.
Earned Value (EV)
Formula
Budget at completion (BAC) × (work completed ÷ total work required) = Earned Value (EV)
BAC × (work completed ÷ total work required) = EV
Schedule Variance (SV)
Definition
The difference between the budgeted value a project has earned through completed work and the planned value of this work. This value indicates whether project work is proceeding as planned in the schedule.
Schedule Variance (SV)
Formula
Earned Value (EV) - Planned Value (PV) = Schedule Variance (SV)
EV - PV = SV
Cost Variance (CV)
Definition
The difference between earned value and actual costs, which indicates cost performance.
Cost Variance (CV)
Formula
Earned Value (EV) - Actual Cost (AC) = Cost Variance (CV)
EV) - AC = CV
Schedule Performance Index (SPI)
Definition
The ratio between earned value and planned value, which represents schedule performance.
- An SPI of 1 indicates the project is on schedule.
- A value greater than 1 indicates it is ahead of schedule.
- A value less than 1 indicates it is behind schedule.
Schedule Performance Index (SPI)
Formula
Earned Value (EV) / Planned Value (PV) = Schedule Performance Index (SPI)
EV / PV = SPI
Cost Performance Index (CPI)
Definition
The ratio between earned value and actual costs, which represents cost performance.
- A CPI value greater than 1 indicates better performance than expected
- A value less than 1 indicates poor performance.
Cost Performance Index (CPI)
Formula
Earned Value (EV) / Actual Cost (AC) = Cost Performance Index (CPI)
EV / AC = CPI
Earned Value Management (EVM)
Definition
Earned value management, or EVM, involves measuring and monitoring several key performance dimensions using a variety of formulas.
Forecasting
Definition
Forecasting helps you calculate accurate estimates of costs for future activities that have not yet been completed, based on current work performance and cost information.
Estimate At Completion (EAC)
Definition
A formula used to calculate and forecasting the total cost of a project that’s faced with uncertainty
Estimate At Completion (EAC) > Bottom-up
Definition
When you want to forecast EAC based on the project manager’s bottom-up ETC. Used when the original budget n longer valid, was incorrect, wrong data or changes have happened.
Estimate At Completion (EAC) > Bottom-up
Formula
Actual Cost (AC) + Bottom-up Estimate To Complete (ETC) = Estimate At Completion (EAC)
AC + ETC = EAC