PMI - Managing the Project Schedule Flashcards

scheduling tools and techniques for creating project calendars and controlling the project schedule. You'll explore concepts like earned value management (EVM) and schedule performance index (SPI) that will aid you in resource smoothing and leveling and managing schedules more efficiently and effectively.

1
Q

Tools and techniques used to control the schedule
List

A
  • Re-estimate an activity duration
  • Data analysis
    – earned value analysis
    – iteration burn down charts
    – performance reviews
    – trend analysis, variance analysis
    – and what if scenario analysis
  • Critical path method
  • Project management information system, or PMIS
    – eporting
    – measuring variances
    – forecasting the effects of control efforts
    – modeling technique
  • Resource optimization
  • Leads and lags
  • Schedule compression
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value (EV) - schedule performance
Formula

A

Actual Cost X Amount done (%) = Earned Value

You calculate the earned value for each activity by multiplying its approved budget by the percentage of work actually completed on the activity up to the current date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Variance
Formula

A

Schedule Variance = Earned Value - Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Variance
Definition

A

Variance is the difference between the project’s earned value and planned value at any point in the project.

Schedule Variance = Earned Value - Planned Value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Resource Leveling
Definition

A

Resource leveling is a way to balance resource availability with the demands of various activities. The resources could be people, equipment, or materials.

Move resources from one activity that has float (time) to another where needed to keep project timeline moving (Critical path).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Resource Smoothing
Definition

A

Resource smoothing uses the available float (time) to delay an activity to start at a later point in time. The activity doesn’t change in duration, and the resource assignments don’t change either. The activity still costs the same as well.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Crashing the Schedule
Definition

A

Designate additional resources for an activity in order to compress the schedule. Crashing is expensive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Fast Tracking
Definition

A

Performing activities simultaneously that were previously intended to be performed in sequence is a schedule compression technique called fast tracking. And although there are definite risks and pitfalls to using fast tracking, there could also be great advantages to your schedule if you need to get things done faster.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule performance index (SPI)

A

To calculate SPI, you divide the earned value by the planned value. The formula for this is SPI = EV/PV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Schedule variance (SV)

A

To calculate schedule variance, you subtract the planned value from the earned value. So the formula for this is SV = EV - PV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Earned value (EV)

A

To calculate earned value, you

  • multiply each activity’s planned budget, or approved cost estimate, by the percentage of work actually completed on the activity up to the given date
  • add the earned values of each activity together to get the total earned value

For example, if the first activity is 100% complete, the second activity is 90% complete, and the third activity is 25% complete, you add the full cost estimate for the first activity, 90% of the cost estimate for the second activity, and 25% of the cost estimate for the third activity to calculate the earned value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Planned value (PV)

A

To calculate planned value, you

  • multiply each activity’s planned budget, or approved cost estimate, by the percentage of work planned to be completed for that activity by the measurement date
  • add the planned values of each activity together to get the total planned value

For example, if the first two activities are meant to be 100% complete and the third activity is meant to be 40% complete at the day of the calculation, you add 100% of the cost estimates for the first two activities and 40% of the cost estimate for the third activity to calculate the planned value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly