PMBOK Processes Flashcards

1
Q

Knowledge area processes

A
  1. Integration
  2. Scope
  3. Time
  4. Cost
  5. Quality
  6. Human Resources
  7. Communications
  8. Risk
  9. Procurement
  10. Stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Processes groups

A
  • Initiating
  • Planning
  • Executing
  • Monitoring and Controlling
  • Closing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Initiating processes

A
  1. 1 Develop Project Charter
  2. 1 Identify Stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Planning processes

A
  1. 2 Develop Project Management Plan
    * 5.1 Plan Scope Management*
    * 5.2 Collect Requirements*
    * 5.3 Define Scope*
    * 5.4 Create WBS*
  2. 1 Plan Schedule Management
  3. 2 Define Activities
  4. 3 Sequence Activities
  5. 4 Estimate Activity Resources
  6. 5 Estimate Activity Durations
  7. 6 Develop Schedule
    * 7.1 Plan Cost Management*
    * 7.2 Estimate Costs*
    * 7.3 Determine Budget*
  8. 1 Plan Quality Management
    * 9.1 Plan Human Resource Management*
  9. 1 Plan Communications Management
    * 11.1 Plan Risk Management*
    * 11.2 Identify Risks*
    * 11.3 Perform Qualitative Risk Analysis*
    * 11.4 Perform Quantitative Risk Analysis*
    * 11.5 Plan Risk Responses*
  10. 1 Plan Procurement Management
    * 13.2 Plan Stakeholder Management*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Executing Processes

A
  1. 3 Direct and Manage Project Work
  2. 2 Perform Quality Assurance
  3. 2 Acquire Project Team
  4. 3 Develop Project Team
  5. 4 Manage Project Team
  6. 2 Manage Communications
  7. 2 Conduct Procurements
  8. 3 Manage Stakeholder Engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Monitoring and Controlling Processes

A
  1. 4 Monitor and Control Project Work
  2. 5 Perform Integrated Change Control
  3. 5 Validate Scope
  4. 6 Control Scope
  5. 7 Control Schedule
  6. 4 Control Costs
  7. 3 Control Quality
  8. 3 Control Communications
  9. 6 Control Risks
  10. 3 Control Procurements
  11. 4 Control Stakeholder Engagement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Closing Processes

A
  1. 6 Close Project or Phase
  2. 4 Close Procurements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly