1
Q

DEVELOP PROJECT CHARTER

A
I	Project statement of work
I	Business case
I	Agreements
I	Enterprise environmental factors
I	Organizational process assets
TT	Expert judgement
TT	Facilitation techniques
O	Project charter
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

DEVELOP PROJECT MANAGEMENT PLAN

A
I	Project charter
I	Outputs from other processes
I	Enterprise environmental factors
I	Organizational process assets
TT	Expert judgement
TT	Facilitation techniques
O	Project management plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

DIRECT AND MANAGE PROJECT WORK

A
I	Project management plan
I	Approved change requests
I	Enterprise environmental factors
I	Organizational process assets
TT	Expert judgement
TT	Project management information system
TT	Meetings
O	Deliverables
O	Work performance data
O	Change requests
O	Project management plan updates
O	Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

MONITOR AND CONTROL PROJECT WORK

A
I	Project management plan
I	Schedule forecasts
I	Cost forecasts
I	Validated changes
I	Work performance information
I	Enterprise environmental factors
I	Organizational process assets
TT	Expert judgement
TT	Analytical techniques
TT	Project management information system
TT	Meetings
O	Change requests
O	Work performance reports
O	Project management plan updates
O	Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PERFORM INTEGRATED CHANGE CONTROL

A
I	Project management plan
I	Work performance reports
I	Change requests
I	Enterprise environmental factors
I	Organizational process assets
TT	Expert judgement
TT	Meetings
TT	Change control tools
O	Approved change requests
O	Change log
O	Project management plan updates
O	Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CLOSE PROJECT OR PHASE

A
I	Project management plan
I	Accepted deliverables
I	Organizational process assets
TT	Expert judgement
TT	Analytical techniques
TT	Meetings
O	Final product, service or result transition
O	Organizational process assets updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IDENTIFY STAKEHOLDERS

A
I	Project charter
I	Procurement documents
I	Enterprise environmental factors
I	Organizational process assets
TT	Stakeholder analysis
TT	Expert judgement
TT	Meetings
O	Stakeholder register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PLAN STAKEHOLDER MANAGEMENT

A
I	Project management plan
I	Stakeholder register
I	Enterprise environmental factors
I	Organizational process assets
TT	Expert judgement
TT	Meetings
TT	Analytical techniques
O	Stakeholder management plan
O	Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

MANAGE STAKEHOLDER ENGAGEMENT

A
I	Stakeholder management plan
I	Communications management plan
I	Change log
I	Organizational process assets
TT	Communication methods
TT	Interpersonal skills
TT	Management skills
O	Issue log
O	Change requests
O	Project management plan updates
O	Project documents updates
O	Organizational process assets updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CONTROL STAKEHOLDER ENGAGEMENT

A
I	Project management plan
I	Issue log
I	Work performance data
I	Project documents
TT	Information management systems
TT	Expert judgement
TT	Meetings
O	Work performance information
O	Change requests
O	Project management plan updates
O	Project documents updates
O	Organizational process assets updates
How well did you know this?