Outputs Flashcards

1
Q

DEVELOP PROJECT CHARTER

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

DEVELOP PROJECT MANAGEMENT PLAN

A

Project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

DIRECT AND MANAGE PROJECT WORK

A
Deliverables
Work performance data
Change requests
Project management plan updates
Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

MONITOR AND CONTROL PROJECT WORK

A

Change requests
Work performance reports
Project management plan updates
Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

PERFORM INTEGRATED CHANGE CONTROL

A

Approved change requests
Change log
Project management plan updates
Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CLOSE PROJECT OR PHASE

A

Final product, service or result transition

Organizational process assets updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IDENTIFY STAKEHOLDERS

A

Stakeholder register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PLAN STAKEHOLDER MANAGEMENT

A

Stakeholder management plan

Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

MANAGE STAKEHOLDER ENGAGEMENT

A
Issue log
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CONTROL STAKEHOLDER ENGAGEMENT

A
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

PLAN SCOPE MANAGEMENT

A

Scope management plan

Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

COLLECT REQUIREMENTS

A

Requirements documentation

Requirements traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

DEFINE SCOPE

A

Project scope statement

Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CREATE WBS

A

Scope baseline

Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

VALIDATE SCOPE

A

Accepted deliverables
Change requests
Work performance information
Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

CONTROL SCOPE

A
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

PLAN SCHEDULE MANAGEMENT

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

DEFINE ACTIVITIES

A

Activity list
Activity attributes
Milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

SEQUENCE ACTIVITIES

A

Project schedule network diagrams

Project documents updates

20
Q

ESTIMATE ACTIVITY RESOURCES

A

Activity resource requirements
Resource breakdown structure
Project documents updates

21
Q

ESTIMATE ACTIVITY DURATIONS

A

Activity duration estimates

Project documents updates

22
Q

DEVELOP SCHEDULE

A
Schedule baseline
Project schedule
Schedule data
Project calendars
Project management plan updates
Project documents updates
23
Q

CONTROL SCHEDULE

A
Work performance information
Schedule forecasts
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
24
Q

PLAN COST MANAGEMENT

A

Cost management plan

25
Q

ESTIMATE COST

A

Activity cost estimates
Basis of estimates
Project documents updates

26
Q

DETERMINE BUDGET

A

Cost baseline
Project funding requirements
Project documents updates

27
Q

CONTROL COSTS

A
Work performance information
Cost forecasts
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
28
Q

PLAN QUALITY MANAGEMENT

A
Quality management plan
Process improvement plan
Quality metrics
Quality checklists
Project documents updates
29
Q

PERFORM QUALITY ASSURANCE

A

Change requests
Project management plan updates
Project documents updates
Organizational process assets updates

30
Q

CONTROL QUALITY

A
Quality control measurements
Validated changes
Validated deliverables
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
31
Q

PLAN HUMAN RESOURCE MANAGEMENT

A

Human resource management plan

32
Q

ACQUIRE PROJECT TEAM

A

Project staff assignments
Resource calendars
Project management plan updates

33
Q

DEVELOP PROJECT TEAM

A

Team performance assessments

Enterprise environmental factors updates

34
Q

MANAGE PROJECT TEAM

A
Change requests
Project management plan updates
Project documents updates
Enterprise environmental factors updates
Organizational process assets updates
35
Q

PLAN COMMUNICATIONS MANAGEMENT

A

Communications management plan

Project documents updates

36
Q

MANAGE COMMUNICATIONS

A

Project communications
Project management plan updates
Project documents updates
Organizational process assets updates

37
Q

CONTROL COMMUNICATIONS

A
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
38
Q

PLAN RISK MANAGEMENT

A

Risk management plan

39
Q

IDENTIFY RISKS

A

Risk register

40
Q

PERFORM QUALITATIVE RISK ANALYSIS

A

Project documents updates

41
Q

PERFORM QUANTITATIVE RISK ANALYSIS

A

Project documents updates

42
Q

PLAN RISK RESPONSES

A

Project management plan updates

Project documents updates

43
Q

CONTROL RISKS

A
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
44
Q

PLAN PROCUREMENT MANAGEMENT

A
Procurement management plan
Procurement statement of work
Procurement documents
Source selection criteria
Make-or-buy decisions
Change requests
Project documents updates
45
Q

CONDUCT PROCUREMENTS

A
Selected sellers
Agreements
Resource calendars
Change requests
Project management plan updates
Project documents updates
46
Q

CONTROL PROCUREMENTS

A
Work performance information
Change requests
Project management plan updates
Project documents updates
Organizational process assets updates
47
Q

CLOSE PROCUREMENTS

A

Closed procurements

Organizational process assets updates