PMBOK Knowledge Areas Flashcards

1
Q

What are the 10 Knowledge Areas?

A
  1. Project Integration
  2. Scope
  3. Schedule
  4. Cost
  5. Quality
  6. Resource
  7. Communication
  8. Risk
  9. Procurement
  10. Stakeholder
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the processes for Project Integration Management?
(7 processes)

A
  1. Develop project charter
  2. Develop project management plan
  3. Direct and manage project work
  4. Manage project knowledge
  5. Monitor and control project work
  6. Perform integrated change control
  7. Close project or phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the ITTOs associated with Developing the Project Charter?

4 Inputs
3 Tools & Techniques
2 Outputs

4 Inputs

Knowledge Area: Project Integration Management

A

Inputs
1. Business documents
2. Agreements
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Interpersonal and team skills

Outputs
1. Project charter
2. Assumption log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the ITTOs associated with Developing the Project Management Plan?

4 Inputs
4 Tools & Techniques
1 Output

Knowledge Area: Project Integration Management

A

Inputs
1. Project charter
2. Outputs from other processes
3. Enterprise environmental factors
4. Organization proces assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Interpersonal and team management

Output
1. Project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the ITTOs associated with Directing and Managing Project Work?

5 Inputs
3 Tools & Techniques
7 Outputs

Knowledge Area: Project Integration Management

A

Inputs
1. Project management plan
2. Project documents
3. Approved change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Project management information system
3. Meetings

Output
1. Deliverables
2. Work performance data
3. Issue log
4. Change requests
5. Project management plan updates
6. Project documents updates
7. Organizational process assets updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the ITTOs associated with Managing Project Knowledge?

5 Inputs
4 Tools & Techniques
3 Outputs

Knowledge Area: Project Integration Management

A

Inputs
1. Project management plan
2. Project documents
3. Deliverables
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Knowledge management
3. Information management
4. Interpersonal and team skills

Output
1. Lessons learned register
2. Project management plan updates
3. Organizational process assets updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the ITTOs associated with Monitoring and Controlling Project Work?

6 Inputs
4 Tools & Techniques
6 Outputs

Knowledge Area: Project Integration Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance information
4. Agreements
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
2. Decision making
3. Meetings

Output
1. Work performance reports
2. Change requests
3. Project management plan updates
4. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the ITTOs associated with Performing Integrated Change Control?

6 Inputs
5 Tools & Techniques
3 Outputs

Knowledge Area: Project Integration Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance reports
4. Change requests
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Change control tools
3. Data analysis
4. Decision making
5. Meetings

Output
1. Approved change requests
2. Project management plan updates
3. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the ITTOs associated with Closing the Project or Phase?

8 Inputs
3 Tools & Techniques
4 Outputs

Knowledge Area: Project Integration Management

A

Inputs
1. Project charter
2. Project management plan
2. Project documents
3. Accepted deliverables
5. Business documents
6. Agreements
7. Procurement documentation
8. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. Meetings

Output
1. Project documents updates
2. Final product, service, or result transition
3. Final report
4. Organizational process assets updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the processes for Project Scope Management?
(6 processes)

A
  1. Plan scope management
  2. Collect requirements
  3. Define scope
  4. Create WBS
  5. Validate Scope
  6. Control Scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the ITTOs associated with Planning Scope Management?

4 Inputs
3 Tools & Techniques
2 Outputs

Knowledge Area: Project Scope Management

A

Inputs
1. Project charter
2. Project management plan
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. Meetings

Output
1. Scope management plan
2. Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the ITTOs associated with Collecting Requirements?

7 Inputs
8 Tools & Techniques
2 Outputs

Knowledge Area: Project Scope Management

A

Inputs
1. Project charter
2. Project management plan
3. Project documents
4. Business documents
5. Agreements
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Data analysis
4. Decision making
5. Data representation
6. Interpersonal and team skills
7. Context diagram
8. Prototypes

Output
1. Requirements documentation
2. Requirements traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the ITTOs associated with Defining Scope?

5 Inputs
5 Tools & Techniques
2 Outputs

Knowledge Area: Project Scope Management

A

Inputs
1. Project charter
2. Project management plan
3. Project documents
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. Decision making
4. Interpersonal and team skills
5. Product Analysis

Output
1. Project scope statement
2. Project document updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the ITTOs associated with Creating WBS?

4 Inputs
2 Tools & Techniques
2 Outputs

Knowledge Area: Project Scope Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Decomposition

Output
1. Scope baseline
2. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the ITTOs associated with Validating Scope?

4 Inputs
2 Tools & Techniques
4 Outputs

Knowledge Area: Project Scope Management

A

Inputs
1. Project management plan
2. Project documents
3. Verified deliverables
4. Work performance data

Tools & Techniques
1. Inspection
2. Decision making

Output
1. Accepted deliverables
2. Work performance information
3. Change requests
4. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the ITTOs associated with Controlling Scope?

4 Inputs
1 Tools & Techniques
4 Outputs

Knowledge Area: Project Scope Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance data
4. Organizational process assets

Tools & Techniques
1. Data analysis

Output
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the processes for Project Schedule Management?
(6 processes)

A
  1. Plan schedule management
  2. Define activities
  3. Sequence Activitities
  4. Estimate activity durations
  5. Develop schedule
  6. Control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the ITTOs associated with Planning Schedule Management?

4 Inputs
3 Tools & Techniques
1 Output

Knowledge Area: Project Schedule Management

A

Inputs
1. Project charter
2. Project management plan
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. Meetings

Output
1. Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the ITTOs associated with Defining Activities?

3 Inputs
4 Tools & Techniques
5 Outputs

Knowledge Area: Project Schedule Management

A

Inputs
1. Project management plan
2. Enterprise environmental factors
3. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Decomposition
3. Rolling wave planning
3. Meetings

Output
1. Activity list
2. Activity attributes
3. Milestone list
4. Change requests
5. Project management plan updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the ITTOs associated with Sequencing Activities?

4 Inputs
4 Tools & Techniques
2 Outputs

Knowledge Area: Project Schedule Management

A

Inputs
1. Project management plan
2. Project documents
2. Enterprise environmental factors
3. Organizational process assets

Tools & Techniques
1. Precedence diagramming method
2. Dependency determination and integration
3. Leads and flags
4. Project management information system

Output
1. Project schedule network diagrams
2. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the ITTOs associated with Estimating Activity Durations?

4 Inputs
8 Tools & Techniques
3 Outputs

Knowledge Area: Project Schedule Management

A

Inputs
1. Project management plan
2. Project documents
2. Enterprise environmental factors
3. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimating
5. Bottom-up estimating
6. Data analysis
7. Decision making
8. Meetings

Output
1. Duration estimates
2. Basis of estimates
3. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the ITTOs associated with Developing Schedule?

5 Inputs
8 Tools & Techniques
7 Outputs

Knowledge Area: Project Schedule Management

A

Inputs
1. Project management plan
2. Project documents
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Schedule network analysis
2. Critical path method
3. Resource optimization
4. Data analysis
5. Leads and lags
6. Schedule compression
7. Project management information system
8. Agile release planning

Output
1. Schedule baseline
2. Project schedule
3. Schedule data
4. Project calendars
5. Change requests
6. Project management plan updates
7. Project douments updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the ITTOs associated with Controlling Schedule?

4 Inputs
6 Tools & Techniques
5 Outputs

Knowledge Area: Project Schedule Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance data
4. Organizational process assets

Tools & Techniques
1. Data analysis
2. Critical path method
3. Project management information system
4. Resource optimization
5. Leads and lags
6. Schedule compression

Output
1. Work performance information
2. Schedule forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates

24
Q

What are the processes for Project Schedule Management?
(6 processes)

A
  1. Plan schedule management
  2. Define activities
  3. Sequence Activitities
  4. Estimate activity durations
  5. Develop schedule
  6. Control schedule
25
Q

What are the ITTOs associated with Planning Cost Management?

4 Inputs
3 Tools & Techniques
1 Outputs

Knowledge Area: Project Cost Management

A

Inputs
1. Project charter
2. Project management plan
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. Meetings

Output
1. Cost management plan

26
Q

What are the ITTOs associated with Estimating Costs?

4 Inputs
8 Tools & Techniques
3 Outputs

Knowledge Area: Project Cost Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimating
6. Data analysis
7. Project management information system
8. Decision making

Output
1. Cost estimates
2. Basis of estimates
3. Project documents updates

27
Q

What are the ITTOs associated with Determining Budget?

6 Inputs
6 Tools & Techniques
3 Outputs

Knowledge Area: Project Cost Management

A

Inputs
1. Project management plan
2. Project documents
3. Business documents
4. Agrements
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Cost aggregation
3. Data analysis
4. Historical information review
5. Funding limit reconciliation
6. Financing

Output
1. Cost baseline
2. Project funding requirements
3. Project documents updates

28
Q

What are the ITTOs associated with Controlling Costs?

5 Inputs
4 Tools & Techniques
5 Outputs

Knowledge Area: Project Cost Management

A

Inputs
1. Project management plan
2. Project documents
3. Project funding requirements
4. Work performance data
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. To-complete performance index
4. Project management information system

Output
1. Work performance information
2. Cost forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates

29
Q

What are the processes for Project Quality Management?
(3 processes)

A
  1. Plan Quality Management
  2. Manage Quality
  3. Control Quality
30
Q

What are the ITTOs associated with Planning Quality Management?

5 Inputs
7 Tools & Techniques
4 Outputs

Knowledge Area: Project Quality Management

A

Inputs
1. Project charter
2. Project mangement plan
3. Project documents
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Data analysis
4. Decision making
5. Data representation
6. Test and inspection planning
7. Meetings

Output
1. Quality management plan
2. Quality metrics
3. Project management plan updates
4. Project documents updates

31
Q

What are the ITTOs associated with Managing Quality?

3 Inputs
8 Tools & Techniques
5 Outputs

Knowledge Area: Project Quality Management

A

Inputs
1. Project mangement plan
2. Project documents
3. Organizational process assets

Tools & Techniques
1. Data gathering
2. Data analysis
3. Decision making
4. Data representation
5. Audits
6. Design for X
7. Problem solving
8. Quality improvement methods

Output
1. Quality reports
2. Test and evalustion documents
3. Change requests
4. Project management plan updates
5. Project documents updates

32
Q

What are the ITTOs associated with Controlling Quality?

7 Inputs
6 Tools & Techniques
6 Outputs

Knowledge Area: Project Quality Management

A

Inputs
1. Project mangement plan
2. Project documents
3. Approved change requests
4. Deliverables
5. Work performance data
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Data gathering
2. Data analysis
3. Inspection
4. Testing/product evaluations
5. Data representation
6. Meetings

Output
1. Quality control measurements
2. Verified deliverables
3. Work performance information
4. Change requests
5. Project management plan updates
6. Project documents updates

33
Q

What are the processes for Project Resource Management?
(6 processes)

A
  1. Plan Resource Management
  2. Estimate Activity Resources
  3. Acquire Resources
  4. Develop Team
  5. Manage Team
  6. Control Resources
34
Q

What are the ITTOs associated with Planning Resource Management?

5 Inputs
4 Tools & Techniques
3 Outputs

Knowledge Area: Project Resource Management

A

Inputs
1. Project charter
2. Project management plan
3. Project documents
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data representation
3. Organizational theory
4. Meetings

Output
1. Resource management plan
2. Team charter
3. Project documents updates

35
Q

What are the ITTOs associated with Estimating Activity Resources?

4 Inputs
7 Tools & Techniques
4 Outputs

Knowledge Area: Project Resource Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Bottom-up estimating
3. Analogous estimating
4. Parametric estimating
5. Data analysis
6. Project management information system
7. Meetings

Output
1. Resource requirements
2. Basis of estimates
3. Resource breakdown structure
4. Project documents updates

36
Q

What are the ITTOs associated with Acquiring Resources?

4 Inputs
4 Tools & Techniques
8 Outputs

Knowledge Area: Project Resource Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Decision making
2. Interpersonal and team skills
3. Pre-assignment
4. Virtual teams

Output
1. Physical resource assignments
2. Project team assignments
3. Resource calendars
4. Change requests
5. Project management plan updates
6. Project documents updates
7. Enterprise environmental factors updates
8. Organizational process assets updates

37
Q

What are the ITTOs associated with Developing Team?

4 Inputs
8 Tools & Techniques
6 Outputs

Knowledge Area: Project Resource Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Colocation
2. Virtual teams
3. Communication technology
4. Interpersonal and team skills
5. Recognition and rewards
6. Training
7. Individual and team assesments
8. Meetings

Output
1. Team performance assessments
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Enterprise environmental factors updates
6. Organizational process assets updates

38
Q

What are the ITTOs associated with Managing Team?

6 Inputs
2 Tools & Techniques
4 Outputs

Knowledge Area: Project Resource Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance reports
4. Team performance assessments
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Interpersonal and team skills
2. Project management information system

Output
1. Change requests
2. Project management plan updates
3. Project documents updates
4. Enterprise environmental factors updates

39
Q

What are the ITTOs associated with Controlling Resources?

5 Inputs
4 Tools & Techniques
4 Outputs

Knowledge Area: Project Resource Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance data
4. Agreements
5. Organizational process assets

Tools & Techniques
1. Data analysis
2. Problem solving
3. Interpersonal and team skills
4. Project management information system

Output
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates

40
Q

What are the processes for Project Communications Management?
(3 processes)

A
  1. Plan Communications Management
  2. Manage Communications
  3. Monitors Communications
41
Q

What are the ITTOs associated with Planning Communications Management?

5 Inputs
8 Tools & Techniques
3 Outputs

Knowledge Area: Project Communications Management

A

Inputs
1. Project charter
2. Project management plan
3. Project documents
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Communication requirements analysis
3. Communication technology
4. Communication models
5. Communication methods
6. Interpersonal and team skills
7. Data representation
8. Meetings

Output
1. Communications management plan
2. Project management plan updates
3. Project documents updates

42
Q

What are the ITTOs associated with Managing Communications?

5 Inputs
7 Tools & Techniques
4 Outputs

Knowledge Area: Project Communications Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance reports
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Communication technology
2. Communication methods
3. Communication skills
4. Project management information system
5. Project reporting
6. Interpersonal and team skills
7. Meetings

Output
1. Project communications
2. Project management plan updates
3. Project documents updates
4. Organizational process assess updates

43
Q

What are the ITTOs associated with Monitoring Communications?

5 Inputs
5 Tools & Techniques
4 Outputs

Knowledge Area: Project Communications Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance data
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Project management information system
3. Data representation
4. Interpersonal and team skills
5. Meetings

Output
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates

44
Q

What are the processes for Project Risk Management?
(7 processes)

A
  1. Plan Risk Management
  2. Identify Risks
  3. Perform Qualitative. Risk Analysis
  4. Perform Quantitative Risk Analysis
  5. Plan Risk Responses
  6. Implement Risk Responses
  7. Monitor Risks
45
Q

What are the ITTOs associated with Planning Risk Management?

5 Inputs
3 Tools & Techniques
1 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project charter
2. Project management plan
3. Project documents
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data analysis
3. Meetings

Output
1. Risk management plan

46
Q

What are the ITTOs associated with Identifying Risks?

6 Inputs
6 Tools & Techniques
3 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project management plan
2. Project documents
3. Agreements
4. Procurement documentation
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Data analysis
4. Interpersonal and team skills
5. Prompt lists
6. Meetings

Output
1. Risk register
2. Risk report
3. Project documents updates

47
Q

What are the ITTOs associated with Performing Qualitative Risk Analysis?

4 Inputs
7 Tools & Techniques
1 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Data analysis
4. Interpersonal and team skills
5. Risk categorization
6. Data representation
7. Meetings

Output
1. Project documents updates

48
Q

What are the ITTOs associated with Performing Quantitative Risk Analysis?

4 Inputs
5 Tools & Techniques
1 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Interpersonal and team skills
4. Representations of uncertainty
5. Data analysis

Output
1. Project documents updates

49
Q

What are the ITTOs associated with Planning Risk Responses?

4 Inputs
9 Tools & Techniques
3 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project management plan
2. Project documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Interpersonal and team skills
4. Strategies for threats
5. Strategies for opportunities
6. Contingent response strategies
7. Strategies for overall project risk
8. Data analysis
9. Decision making

Output
1. Change requests
2. Project management plan updates
3. Project documents updates

50
Q

What are the ITTOs associated with Implementing Risk Responses?

3 Inputs
3 Tools & Techniques
2 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project management plan
2. Project documents
3. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Interpersonal and team skills
3. Project management information system

Output
1. Change requests
2. Project documents updates

51
Q

What are the ITTOs associated with Monitoring Risk?

4 Inputs
3 Tools & Techniques
5 Outputs

Knowledge Area: Project Risk Management

A

Inputs
1. Project management plan
2. Project documents
3. Work performance data
4. Work performance reports

Tools & Techniques
1. Data analysis
2. Audits
3. Meetings

Output
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates

52
Q

What are the processes for Project Procurement Management?
(3 processes)

A
  1. Plan Procurement Management
  2. Conduct Procurements
  3. Control Procurements
53
Q

What are the ITTOs associated with Planning Procurement Management?

6 Inputs
5 Tools & Techniques
10 Outputs

Knowledge Area: Project Procurement Management

A

Inputs
1. Project charter
2. Business documents
3. Project management plan
4. Project documents
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Data gathering
3. Data analysis
4. Source selection analysis
5. Meetings

Output
1. Procurement management plan
2. Procurement strategy
3. Bid documents
4. Procurement statement of work
5. Source selection criteria
6. Make-or-buy decisions
7. Independent cost estimates
8. Change requests
9. Project documents updates
10. Organizational process assets updates

54
Q

What are the ITTOs associated with Conducting Procurements?

6 Inputs
5 Tools & Techniques
6 Outputs

Knowledge Area: Project Procurement Management

A

Inputs
1. Project mangement plan
2. Project documents
3. Procurement documentation
4. Seller proposals
5. Enterprise environmental factors
6. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Advertising
3. Bidder conferences
4. Data analysis
5. Interpersonal and team skills

Output
1. Selected sellers
2. Agreements
3. Change requests
4. Project management plan updates
5. Project documents updates
6. Organizational process assets updates

55
Q

What are the ITTOs associated with Controlling Procurements?

8 Inputs
5 Tools & Techniques
7 Outputs

Knowledge Area: Project Procurement Management

A

Inputs
1. Project mangement plan
2. Project documents
3. Agreements
4. Procurement documentation
5. Approved change requests
6. Work performance data
7. Enterprise environmental factors
8. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Claims administration
3. Data analysis
4. Inspection
5. Audits

Output
1. Closed procurements
2. Work performance information
3. Procurement documentation updates
4. Change requests
5. Project management plan updates
6. Project documents updates
7. Organizational process assets updates