PMBOK Chapter 6 - Project Time Management Flashcards
What is Project Time Management? (knowledge area)
includes the processes required to manage the timely completion of the project
Plan Schedule Management (process)
the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing and controlling the project schedule
Define Activities (process)
the process of identifying and documenting the specific actions to be performed to produce the project deliverables
Sequence Activities (process)
the process of identifying and documenting relationships among the project activities
Estimate Activity Resources (process)
the process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity
Estimate Activity Durations (process)
the process of estimating the number of work periods needed to complete individual activities with estimated resources
Develop Schedule (process)
the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model
Control Schedule (process)
the process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan
What is a schedule model?
a representation of the plan for executing the project’s activities including durations, dependencies, and other planning information
What is the schedule management plan?
a component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule.
What are work packages decomposed to?
activities that represent the work effort required to complete the work package
What is rolling wave planning?
an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level
What is an activity list?
a comprehensive list that includes all schedule activities required on the project, also includes the activity identifier and a scope of work description for each activity
What are activity attributes?
Multiple attributes associated with each schedule activity that can be included within the activity list.
Activity attributes include activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
What is a milestone list?
a list identifying all project milestones and indicates whether the milestone is mandatory
What is the precedence diagramming method?
a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed
What is a predecessor activity?
an activity that logically comes before a dependent activity in a schedule
What is a successor activity?
a dependent activity that logically comes after another activity in a schedule
Four types of logical relationships:
1) Finish-to-start (FS) - a successor activity cannot start until a predecessor activity has finished
2) Finish-to-finish (FF) - a successor activity cannot finish until a predecessor activity has finished
3) Start-to-start (SS) - a successor activity cannot start until a predecessor activity has started
4) Start-to-finish (SF) - a successor activity cannot finish until a predecessor activity has started