Planning Flashcards
The purpose of planning is (3)
Persuade people to perform tasks timely so as not to delay others
Make best use of resources
Provide a framework for decision making for change
4 steps to planning
Analysis- break down into activities
Sequence and interdependence
Time or cost values
Determine critical path
Critical path=
The longest sequence of activities from start to finish
Bar/gantt charts include
Tasks and durations
Also resources required
AdvNtages of Gantt chart (3)
Simple
Easy to prepare/understand
Good for showing progress/delays
Disadvantages of Gantt charts (3)
Fails to highlight interdependencies
Not good for complicated jobs
Operations easily omitted by mistake
Productivity=
Quantity per amount of time
Time required found by
Quantity / productivity
Network methods show
A project as a series of activities