Cost Estimating Flashcards

1
Q

Many projects show … caused by

A

Massive cost and time overruns caused by under estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The aim of cost estimating is

A

To predict the most likely cost of the project at each stage in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Requirements of cost estimating are (5)

A
Predict most probably cost of works
Predict gusts of programs for works
Identify and quantify problems/risks 
State all assumptions and note exclusions
Forecast of expenditure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost estimates are carried out at

A

Every stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cash flow concerns

A

The flow of money in and out of an account per time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A project t that brings in money before it is finished (example)

A

Housing estates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost=

A

Cost= cost directly attributable to an element of work, including direct overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Price=

A

Cost of an element of work plus allowance for general overheads, insurances, taxes, finance and profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Things included in the price (5)

A
Permanent works costs
General overhead costs
Taxes
Interest charges on money borrowed 
Allowances or contingencies for risks and uncertainties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Average profit margin of a contractor and why

A
3-5%
Very competitive (4-6 bidding on job)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Amount of profit decided by contractor depends on (4)

A

Type of work
Size of project/contract
Extent of competition
Requirements of organisation to secure work in future

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BOQ is created by… but

A

Created by client but partially completed by contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Included in BOQ

A
Client-item number
Description
Quantity
Contractor-rate
Price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

5 cost estimating techniques

A
Man-hour
Global
Factorial
Unit rates
Operational
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Man hour technique suitable for and used when

A

Suitable for labour intensive implementation, construction and operations
Used at construction stage only

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Total man hours = ..+…+…

A

Current labour rate+ cost of materials+ cost of equipment

17
Q

To use man hours technique u need….

Uncertainty is caused by…

A

Need a detailed program

Uncertainty from over/underestimating total hours

18
Q

Global method relies on …. is used when

A

Historical data

Is used to give initial estimates only

19
Q

Sources of error in global method (5)

A
Different definitions on cost included 
Different definitions on the measurement of units of capacity(eg height including ceiling or not)
Not comparing like with like
Inflation and interest rates
Market factors
20
Q

Factorial technique provides and is used for

A

A comprehensive list of potential costs

Is used for process plants etc where major item costs can be obtained from suppliers

21
Q

Advantages and disadvantage of factorial method

A

No detailed programme needed
Can identify implementation problems
Lead times for equipment delivered

Not reliable for site workers

22
Q

Unit rate technique involves

A

Using historical rates in the BOQ

23
Q

Operational method involves

A

Total cost found by considering constituent operations and activities using method statement and accumulated demand for resources

24
Q

Benefits of operational technique and requirements

A

Reliable
Uses current rates

Must use accurate data collection and risk identification
Must focus on high risk areas