Construction Management Flashcards

1
Q

Main project stages are (6)

A
Appraisal
Definition
Design
Construction
Commission
Operation and maintenance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The contractor is responsible for

A

Carrying out the works as described in information provided at tender stage. Only constraints are set out in tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The task of project management is

A

To ensure the contractor uses his freedom responsibly and works in a competent and efficient manner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

5 Stages of contractor selection by…

A

Preparation and issue of tender documents by The Engineer.
Preparation and submission of tender by the contractor.
Evaluation of tender and recommendation by The Engineer.
Contract award by the client.
Start of construction by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Preparing the tender the contractor must consider (6)

A
Sequence construction
Best method
Resources needed
Makes models and number of plant items
Cost of resources
Profit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is front loading

A

When a contractor puts profit in early to get money early

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why wouldn’t the cheapest contractor be chosen (3)

A

Unrealistically low price (do they understand the risks)
Inadequate resources or experience
Late knowledge the contractor is in financial difficulty (eg from media)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why may a contractor want to change his price/methods after contract award(4)

A

Wanted to win at a competitive but safe price
Decisions made under time pressure
After award agent has more time and former review of resources available
Exist to make profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When can price be changed after contract award(4)

A
Major design changes
Inflation (must be allowed for in tender) 
Risks occur (unpredictable) 
Disruption from delays leading to claims (eg late drawings)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The contractor should review ( 4) at regular intervals

A

Methods of construction
Programme expenditure
Forecast cost to completion
Profit forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

For control of resources the contract will (5)

A
Buy materials and plants items
Appoint sub contractors
Hire/buy equipment
Hire/fire labourers
Establish site facilities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly