Photovoltaic Installations 205.20B Flashcards
What is The expected voltage on a residential with PV?
Up to 600 volts DC
What is the expected Voltage for a commercial with PV system?
1000 volts DC
What is the expected voltage for utility installations?
1500 volts DC
Once converted through an inverter 1500 volts DC current becomes?
35,000 volts of AC current
What does BESS stand for?
Battery energy storage system
If it has been determined there is a residence with a PV system that has a BESS as part of the installation what steps should be taken?
- Notify command, upgrade to 3-1 hazardous materials response, isolate area
- operate electrical disconnect to isolate battery system, remember there is still stranded energy.
- crews in full PPE SCBA with mask
- charged hose line in place
- isolate a minimum of 40 feet
- don’t park in front of house
- make sure no damage to battery pack
- contact vendor and battery management system BMS
- consider extended monitoring period of 12 hours for thermal runaway passive cooling period
- direct water application infective to do construction
-temp reading every 10 minutes - water is preferred for lithium ion battery fires
- RP must arrange for disposal and clean up
- command must notify RP and warn of risk of a secondary event and make notification over radio that notifications have been made
PV panels or modules and be covered with what to stop generation of electricity?
Opaque tarps
What are some indicator that a PV installation are present?
• Visible array of PV panels
• Conduit coming from roof
• Invertors mounted on a wall or the ground next to building electrical panel
• Signage found around the electrical system
In order to fully secure utilities with PV a firefighter must?
• De-energize power coming into the building from utility company.
• De-energize electrical circuits leading from the PV system.
• Operate the rapid shut down switch to isolate the DC power for the PV system and confine
the power to the array.
How do you fight fire for a PV array?
- Fog pattern delivered at a min 10 degree pattern
- min of 20 feet away
- only employed on PV installation up to 1000 volts
Photovoltaic generating stations (utility stations)
- do not engage in any fire suppression
- isolate area
- remain outside fence line and protect exposures