Payment (Section 4) Flashcards
What is a contract sum?
A sum which is agreed between the Contractor and the Employer for the Contractor to carry out the works.
What items are able to adjust a contract sum?
Variations, provisional sum adjustments, approximate quantity adjustments, acceleration, fluctuations, loss and expense (relevant matters).
How are adjustments to the contract sum taken into account?
An adjustment to the contract sum should be taken into account at the next Interim Certificate. E.g. paying the value of a variation that had been instructed during the period.
What are the timeframes associated with the Final adjustment (final account)?
No later than 6 months from issue of the PC certificate shall the contractor provide the CA / QS with all documents necessary to adjust the CS. Then, the CA / QS has 3 months from receipt of the documents to prepare a statement of all adjustments and send a copy to the contractor.
What are the 2 alternatives for payment in the D&B contract?
Alternative A = Stage payments (work stages identified and when completed an application is submitted)
Alternative B = Periodic payments i.e. monthly
Which is the default if an alternative is not selected?
Alternative B - Periodic payments
Can you tell me about the payment terms on a project you have worked on?
Contractor issues their Interim Valuation Application 7 days prior to the due date. CA has 5 working days from the due date to issue the Payment Notice/Certificate. The final date for payment is 14 days after the due date. The client must issue a Pay Less Notice no later than 5 days before the Final Date for Payment if they are to amend the amount stated in the Payment Certificate (or Interim Valuation Application if no payment notice was issued).
What is the difference between the JCT vs NEC payment timeline?
Pay Less notice is 7 days before final date for payment, not 5 as in JCT.
What is the JCT Scheme for Construction Contracts payment timeline?
The Scheme for Construction Contracts applies when construction contracts don’t comply with HGCRA 1996. Where the contract fails to provide an adequate mechanism for determining what payments become due under the contract or when they become due for payment, the below provisions shall apply:
- ) the latter of; the expiry of 7 days following the relevant period or the making of a claim by the payee (contractor)
- ) The final payment is payable when; 30 days following completion of the work or the making of a claim by the payee (contractor) - whichever occurs later.
- ) The final date for payment shall be 17 days from the date that payment becomes due.
Which payment dates are fixed by statute and which dates are fixed by the contract?
Contract = IVD to D.D (7 days), Due date to final date for payment (14 days), Pay less to final date for payment (5 days).
Statute = Due date to interim certificate (5 days)
If no adequate provisions for payment terms are provided for the contract, what are the payment terms to be based on?
Those stated in the Scheme for Construction Contracts will be used.
Where is the due date specified?
Pre-agreed date between the contractor and employer, as per the Contract Particular’s.
The first Interim Valuation Date is usually specified in the Contract Particular’s and a timeframe for subsequent IVD’s is specified. If the first Interim Valuation Date isn’t specified, then the date is taken as 1 month after the date of possession. As the due date is 7 days after the IVD, they are also known.
Using the JCT SBC if a contractor does not submit an interim application by the due date what is the process for payment?
The QS will undertake a valuation and produce an interim valuation which will be the basis for the interim certificate.
Using the JCT D&B if a contractor does not submit an interim application by the due date what is the process for payment?
The D&B contract does not name the QS and if there is no application made then the onus is on the contractor to produce an application and the payment dates shift forward.
Using the JCT SBC if the contractor submits an application but the CA does not submit his interim certificate what happens?
The contractors interim application will become an interim payment notice.
If, under a JCT SBC neither the contractor submits his interim application and the CA does not produce an interim certificate what is the process?
The contractor can issue an interim payment notice which will shift the payment dates forward.