Contract Selection Flashcards
What are the main criteria for selecting a form of contract?
- ) Procurement type,
- ) How risk averse the client is,
- ) Size of project
- ) Client (public or private)
How might the type of client affect the choice of contract?
Private (quality) vs Public (cost and programme),
Risk averse or non risk averse
Experienced or not
What different types are there of SBC?
- ) JCT SBC,
- ) D&B,
- ) Minor Works,
- ) Intermediate,
- ) Major Works,
- ) Constructing Excellence
What different types are there of SBC?
With quants, without quants, approximate quants.
When would you use JCT minor works?
Small, simple, short duration, roughly up to £200,000, lump sum form.
When would you use JCT SBC with quants?
Full design, There is BoQ, Lump sum, contractors risk of price only, employer takes risk on quant errors.
When would you use JCT SBC without quants?
Work designed but there are no quants in BoQ, lump sum form, contractors risk on price and quants.
When would you use JCT SBC approx quants?
Remeasurable contract, no contract sum, design is not complete, approx BoQ prepared, construction commencing prior to complete design.
When would you use JCT major works?
Significant size.
When would you use JCT prime cost contract?
Contractor paid cost of carrying out the works plus a percentage fee for OH&P, may be used if contractor is selected following insolvency [of the previous contractor on the job], total cost unknown until completion.
What management contract is produced by the JCT?
Constructing Excellence
Please name the NEC options?
A = Priced Activity Schedule, B = Priced BoQ, C = Target cost Activity Schedule, D= Target Cost BoQ, E = Cost Reimbursable, F = Management
How does the NEC incorporate D&B?
NEC4 Design, Build and Operate Contract (DBO), released in 2017.
Are you aware of any of the core clauses in the NEC suite?
Payment, Compensation Events, Liabilities and Insurance, Termination
Are you aware of any of the secondary option clauses in the NEC suite?
X1 = inflation, X4 = PCG, X5 = Sectional Completion, X7 = Delay damages, X12 = Partnering, X13 = Performance bond, X16 = Retention