Contract Selection Flashcards

1
Q

What are the main criteria for selecting a form of contract?

A
  1. ) Procurement type,
  2. ) How risk averse the client is,
  3. ) Size of project
  4. ) Client (public or private)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How might the type of client affect the choice of contract?

A

Private (quality) vs Public (cost and programme),
Risk averse or non risk averse
Experienced or not

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What different types are there of SBC?

A
  1. ) JCT SBC,
  2. ) D&B,
  3. ) Minor Works,
  4. ) Intermediate,
  5. ) Major Works,
  6. ) Constructing Excellence
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What different types are there of SBC?

A

With quants, without quants, approximate quants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When would you use JCT minor works?

A

Small, simple, short duration, roughly up to £200,000, lump sum form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When would you use JCT SBC with quants?

A

Full design, There is BoQ, Lump sum, contractors risk of price only, employer takes risk on quant errors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When would you use JCT SBC without quants?

A

Work designed but there are no quants in BoQ, lump sum form, contractors risk on price and quants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When would you use JCT SBC approx quants?

A

Remeasurable contract, no contract sum, design is not complete, approx BoQ prepared, construction commencing prior to complete design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When would you use JCT major works?

A

Significant size.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When would you use JCT prime cost contract?

A

Contractor paid cost of carrying out the works plus a percentage fee for OH&P, may be used if contractor is selected following insolvency [of the previous contractor on the job], total cost unknown until completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What management contract is produced by the JCT?

A

Constructing Excellence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Please name the NEC options?

A
A = Priced Activity Schedule, 
B = Priced BoQ, 
C = Target cost Activity Schedule, 
D= Target Cost BoQ, 
E = Cost Reimbursable, 
F = Management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does the NEC incorporate D&B?

A

NEC4 Design, Build and Operate Contract (DBO), released in 2017.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Are you aware of any of the core clauses in the NEC suite?

A

Payment, Compensation Events, Liabilities and Insurance, Termination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Are you aware of any of the secondary option clauses in the NEC suite?

A
X1 = inflation, 
X4 = PCG, 
X5 = Sectional Completion, 
X7 = Delay damages, 
X12 = Partnering, 
X13 = Performance bond, 
X16 = Retention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Parties in JCT SBC contract?

A

Employer, Contractor, CA, QS, Principle Designer

17
Q

Parties in JCT D&B contract?

A

Employer, Contractor, EA

18
Q

Parties in NEC contract?

A

Employer, Contractor, PM, Supervisor

19
Q

What are key differences between NEC and JCT?

A
  1. ) NEC uses 6 main options and sub-options where as the JCT uses separate contracts.
  2. ) NEC is written in laymen terms where as JCT is a more complicated read.
  3. ) The parties are different; there’s no QS mentioned in the NEC and the EA or CA is referred to as the PM.
  4. ) NEC fosters collaboration where as the JCT is said to be adversarial.
  5. ) The programme and risk register are contractual documents under NEC.
  6. ) Variations, EoTs and Loss and Expense claims are handled by Compensation Events under the NEC.
  7. ) NEC has “periods of reply” to encourage parties to respond to each other.
  8. ) The NEC has an early warning notice system where to contractor should highlight risks.
20
Q

Explain to me as an uninformed Client the comparative dangers of using a bespoke form of contract and advantages of using a standard form of contract?

A

Standard form = written by experts, rights and obligations clearly stated, risks allocated fairly, well understood within industry, time and expense of preparing bespoke is avoided, case law available.

21
Q

Why use a bespoke contract?

A

Apportionment of risk can be questioned and altered, you will have to be familiar with what’s in a bespoke contract as it is drafted by yourself, using an inappropriate standard form cancels out advantages.

22
Q

What is the legal principle of “contra proferentum”?

A

Would apply to a bespoke contract and not a standard form. “Interpretation against the draftsman”, is a doctrine of contractual interpretation where a term is ambiguous, the preferred meaning should be the one that works against the interests of the party who provided the wording.

23
Q

What are the common contract documents?

A

ER’s
Pricing document i.e. CSA in D&B contracts.
CP’s
Preliminary pricing document.

24
Q

What is a named sub-contractor?

A

Employer supplies list of names in prelims to the contractor.

25
Q

How do you include client amendments into your forms of contract?

A

Append amendments to contract.