Carrying our the Works (Section 2) Flashcards
What section is “Carrying out the Works” found in in the JCT SBC?
Section 2
What are the general obligations of the contractor when carrying out the works in accordance with the JCT SBC?
In a proper and workmanlike manner and in compliance with the Contract Documents.
What is the normal duty of care that both professional services and building contracts require of the service provider?
Reasonable skill and care.
What does the term fit for purpose mean and how does that serve to change the normal duty of care?
A fitness [or fit] for purpose obligation imposes a higher duty [than that imposed by “reasonable skill and care”], as it is an absolute obligation to achieve a specified result. A breach of which does not require proof of negligence. PI (professional indemnity) may not cover fit for purpose due to the nature of it not allowing any errors.
What is a performance bond [or performance security]?
A bond which is provided by a bank / insurer which will be paid out if the contractor fails to fulfill their obligations in providing what is stated in the contract.
What is an on demand performance bond and how does it differ from the sort of performance bonds commonly used today?
On Demand - can be called upon whether there has been a default or not.
Conditional or default - requires that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.
What is an advanced payment bond?
A bond which is provided by a security provider to cover the loss or damage to materials already paid for.
What is the purpose of a bond covering the payment of materials off site?
It covers the loss or damage to materials already paid for off site, in case the supplier goes into administration.
Where are bonds appropriate?
A new contractor, to protect a one off developer, due to risks in the project.
In your experience, what level of cover is generally taken out in a performance bond?
10% of Contract sum
Does the price included by a contractor for a performance bond in its tender tell you anything about the contractor?
Yes - the cost of the bond gives client a guide as to the credit worthiness and reputation of the contractor in the bond market.
Where you have used a PCG on a project and how did you determine the financial stability of the parent company?
The financial stability of the parent company would be assessed by analyzing the financial accounts for the previous 3 years. - profit & loss, balance sheet.
What is a Parent Company Guarantee (PCG)?
Parent Company Guarantee (PCG) - form of security that may be required by clients to protect them in the event of default on a contract by a contractor that is controlled by a parent company.
What is the period of deferment of possession as stated in the JCT SBC?
Maximum of 6 weeks
If there is an error in the ER’s, what is the process?
Alter and modify accordingly and treat as a variation.
If there is an error in the CP’s, what is the process?
Alter and modify but no addition to contract sum or EoT.
What must be in place for materials off site to be used in a contract?
The materials must be included in the Contract Particulars as Listed Items.
When adjusting the completion date, what must be proven by the Contractor?
That there has been a Relevant Event.
What are the relevant events in the JCT?
Clause 2.26
- Variations
- Instructions (incl. opening up for inspection, where the Works were in accordance with the contract)
- Deferment of possession
- Antiquities (e.g. fossils, antiques and other objects of interest on site)
- Contractor’s right of suspension (following non-payment)
- The carrying out by a Statutory Undertaker of work in pursuance with its statutory obligations in relation to the works
- Exceptionally adverse weather conditions
- Specified Perils
- Force majure (terrorism, pandemic, earthquake)
- Strikes (of workmen)
- Delay in receipt of any necessary permissions or approval of any statutory body
What is the contractor expected to do if there is an EoT? - in terms of work.
Provide best endeavors to prevent delay in progress of works, and do all reasonably required to proceed with works.
What certificates are to be issued if the works are completed on time/not completed on time?
On time = Practical Completion Certificate
Late = Non-completion Certificate
What does practical completion trigger?
- ) release of 1/2 retention
- ) LAD relief
- ) Rectification period begins
- ) Insurances back with the client, they’re responsible for site security etc.
What must the employer send to the contractor if damages are to be levied?
Pay Less notice
Where are damages stated?
Contract Particulars