Carrying our the Works (Section 2) Flashcards

1
Q

What section is “Carrying out the Works” found in in the JCT SBC?

A

Section 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the general obligations of the contractor when carrying out the works in accordance with the JCT SBC?

A

In a proper and workmanlike manner and in compliance with the Contract Documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the normal duty of care that both professional services and building contracts require of the service provider?

A

Reasonable skill and care.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does the term fit for purpose mean and how does that serve to change the normal duty of care?

A

A fitness [or fit] for purpose obligation imposes a higher duty [than that imposed by “reasonable skill and care”], as it is an absolute obligation to achieve a specified result. A breach of which does not require proof of negligence. PI (professional indemnity) may not cover fit for purpose due to the nature of it not allowing any errors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a performance bond [or performance security]?

A

A bond which is provided by a bank / insurer which will be paid out if the contractor fails to fulfill their obligations in providing what is stated in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is an on demand performance bond and how does it differ from the sort of performance bonds commonly used today?

A

On Demand - can be called upon whether there has been a default or not.

Conditional or default - requires that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an advanced payment bond?

A

A bond which is provided by a security provider to cover the loss or damage to materials already paid for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of a bond covering the payment of materials off site?

A

It covers the loss or damage to materials already paid for off site, in case the supplier goes into administration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where are bonds appropriate?

A

A new contractor, to protect a one off developer, due to risks in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In your experience, what level of cover is generally taken out in a performance bond?

A

10% of Contract sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Does the price included by a contractor for a performance bond in its tender tell you anything about the contractor?

A

Yes - the cost of the bond gives client a guide as to the credit worthiness and reputation of the contractor in the bond market.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where you have used a PCG on a project and how did you determine the financial stability of the parent company?

A

The financial stability of the parent company would be assessed by analyzing the financial accounts for the previous 3 years. - profit & loss, balance sheet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a Parent Company Guarantee (PCG)?

A

Parent Company Guarantee (PCG) - form of security that may be required by clients to protect them in the event of default on a contract by a contractor that is controlled by a parent company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the period of deferment of possession as stated in the JCT SBC?

A

Maximum of 6 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If there is an error in the ER’s, what is the process?

A

Alter and modify accordingly and treat as a variation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If there is an error in the CP’s, what is the process?

A

Alter and modify but no addition to contract sum or EoT.

17
Q

What must be in place for materials off site to be used in a contract?

A

The materials must be included in the Contract Particulars as Listed Items.

18
Q

When adjusting the completion date, what must be proven by the Contractor?

A

That there has been a Relevant Event.

19
Q

What are the relevant events in the JCT?

A

Clause 2.26

  • Variations
  • Instructions (incl. opening up for inspection, where the Works were in accordance with the contract)
  • Deferment of possession
  • Antiquities (e.g. fossils, antiques and other objects of interest on site)
  • Contractor’s right of suspension (following non-payment)
  • The carrying out by a Statutory Undertaker of work in pursuance with its statutory obligations in relation to the works
  • Exceptionally adverse weather conditions
  • Specified Perils
  • Force majure (terrorism, pandemic, earthquake)
  • Strikes (of workmen)
  • Delay in receipt of any necessary permissions or approval of any statutory body
20
Q

What is the contractor expected to do if there is an EoT? - in terms of work.

A

Provide best endeavors to prevent delay in progress of works, and do all reasonably required to proceed with works.

21
Q

What certificates are to be issued if the works are completed on time/not completed on time?

A

On time = Practical Completion Certificate

Late = Non-completion Certificate

22
Q

What does practical completion trigger?

A
  1. ) release of 1/2 retention
  2. ) LAD relief
  3. ) Rectification period begins
  4. ) Insurances back with the client, they’re responsible for site security etc.
23
Q

What must the employer send to the contractor if damages are to be levied?

A

Pay Less notice

24
Q

Where are damages stated?

A

Contract Particulars

25
Q

What are damages and how are they calculated?

A

They are a genuine pre estimate of loss to the employer if the contractor does not obtain PC on the specified completion date. For example, by delaying a property from being rented, the client would be losing out on rent if PC is delayed.

26
Q

If the employer asked you to calculate their damages for a project, what would you say?

A

I would state that I cannot calculate LADs but I could give advice to the employer on how he can calculate. E.g.

  1. ) Damages should be set as a genuine pre-estimate of loss
  2. ) What is the intended use of the development?
  3. ) What is the average property price or rental price for that area?
  4. ) Are there any potential out of sequence promotional costs?
27
Q

What is the difference between sectional completion and partial possession?

A

Sectional:
Sectional completion is agreed up front and provided for in the contract. The contractor has an obligation to achieve the sectional completion date. LD’s are agreed up front, should the section be delivered late.

Partial Possession:
Requires an agreement during the progress of the works which requires an instruction. Usually more expensive than sectional completion.

28
Q

What happens to damages and retention when a section is handed over?

A

Pro-rate in relation to the size / value of the completed area.

29
Q

Can you tell me the process for during and after the rectification period if defects are found?

A

During = patent defects.
The defects are to be put into a schedule of defects. These are to be given to the contractor no later than 14 days after the end of the rectification period and the contractor must correct these in reasonable times at no cost to the employer. The contractor must be given the chance to correct the defects, if he fails to then the employer can amend the defect at the cost of the contractor (retention money)

After = latent defects.
After the end of the defects liability period the building owner does not have a contractual right to insist that the contractor rectifies defects not notified during that period. The building owner must instead seek action for damages, breach of contract or for negligence.

30
Q

What certificate is issued following the rectification period?

A

Certificate of making good

31
Q

What effect does the issuance of the certificate of making good have?

A
  1. ) Releasing the remainder of any retention.

2. ) Results in the Final Certificate being issued.