Pak Man Dam Case Study Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Location

A

The Mun River, 5.5km upstream from its confluence with the Mekong, in the province of Ubon Ratchathani, in Northeast Thailand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Rivers

A

Mun

Mekong

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Timeline

A

Construction began - 1989
Opening date - 1994

Aims
Before construction of the plant it was estimated that:
- The cost of the project would be $144 million
- The dam would produce 136mw of electricity
- 248 households would be displaced
In reality:
- Cost was $260 million dollars, a cost overrun of 68%
- Dam average power generation is 21mw
- 1700 households were displaced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Description

A

Height: 17 m
Length: 300 m
Width: 7.5 m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Power Capacity

A

Turbines: 4
Installed capacity: 136 MW
Annual generation: 290 GWh

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Social Impacts

A
  • The immediate impact of the dam was to flood 117 square kilometres of land and displace (move from home) around 3,000 families.
  • In all around 25,000 villagers claim to have been affected by the dam.
  • Protests were staged at the dam site and outside
  • Government House in Bangkok. EGAT has paid out
  • US$44.24 million in relocation compensation, plus US$15.8 million for loss of fisheries.
  • The Mun River was once rich with all kinds of fish which supported the villagers’ way of life as freshwater fishermen.
  • Since the dam’s completion nearly 2/3 of the fish have disappeared from the river because fish migration from the Mekong has been virtually blocked.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Economic Impacts

A
  • The dam has not reliably produced the expected amount of electricity, making it economically unprofitable.
  • Its target capacity of power generation was 136 megawatts (MW), which is enough to supply power for 5 large department stores.
  • Due to insufficient water (the river suffers from droughts) the actual output of the dam has been less than half of its expected capacity.
  • EGAT responded that such consistent electricity production was unnecessary, and that the dam was a useful source of electricity.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Environmental Impacts

A
  • The dam blocked up the river and sediment, run off of pesticides, chemical fertilisers and industrial waste collected behind the dam creating a stagnant and toxic pool.
  • In these conditions of the reservoir, few species of fish are able to survive, due to their high tolerance for pollution.
  • The closing of the dam gates also raises water levels, flooding riverbank vegetation and preventing many plant species from growing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Political Impacts

A
  • There were various organised protests after the construction of the dam
  • In 1995, some of the protestors created the Assembly for the Poor, a non-governmental organization created with the goal of opening the Pak Mun dam. This organization became vital in organising protests around the dam and in Bangkok.
  • In 2000, the Assembly for the Poor concerted a large series of protests that brought the issue of the dam to the world’s attention.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Outcomes of Protests of Pak Mun Dam

A
  • Protests ultimately led to a decision by the government in 2001 to open the gates of the dam for 4 months of each year, with the goal of rebuilding the ecosystem of the river during that time and letting the villagers fish
  • FAILURE!!! Damage to ecosystem
  • It has been suggested that the failure of the Pak Mun dam and the ensuing protests are the main reason for new dams not being constructed in Thailand.
  • Although this was not a goal of the protests, it can also be seen as a partial victory
  • Overall, the government has paid out almost 500 million baht in compensation for the loss of fisheries livelihood
  • If the question is on renewable energy - you can talk about how it influenced Thailand’s energy mix
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Views of Different Groups on the construction of Pak Mun Dam

A

Local residents
- Overwhelmingly negative, creating decades of resentment and a complete disruption of lives

EGAT and the World Bank
- Capable of fulfilling additional energy demand in the region at peak times, therefore the scheme is justified

World Commision on Dams
- If all benefits and costs were assessed, it is unlikely that the project would have been built in the current context

Government
- Negative - overseas bad perception of Thailand, because of all the protests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Evaluation of the successes and failures of the dam.

A

Positives
- It brought a renewable supply of energy to Thailand.

Negatives

  • There were delays in the construction of the dam and the price overran by a couple billion baht this cost the government more money which could be better spent in other sectors.
  • No participation of locals in decision making process
  • A poor Environmental Impact Assessment which did not forsee the impact on fisheries
  • Careless decision-making from The World Bank
  • Destruction of the livelihood of local residents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly