Overall Project+ Material Flashcards
What is a chart of accounts?
IDs that represent each level in WBS outline form
Purpose of Functional Requirement?
- Characteristics needed for project to perform
- Behavioral, performance-oriented; descriptive
What is a business case?
Document to show benefit/reward of potential project
Executing:
Deliverables produced/verified
What is PV?
Planned Value:
- PART OF EARNED VALUE MANAGEMENT
- Cost of authorized work that’s budgeted for a specific schedule activity or WBS component during a given time period or phase.
What is RACI?
Chart to show
Responsible/Accountable/Consulted/Informed
What are the key project charter elements?
- Purpose of project
- Goals/objectives
- Deliverables
- Requirements
- Milestones
- Budget
- Assumptions
- Constraints/risks
- PM
- Sponsor
- Project approval criteria
What is SS?
Start-to-Start
Predecessor must start before successor.
What does a PERT do?
Program Evaluation Review Technique
- (optimistic + pessimistic + (4 × most likely)) / 6
- Calculates expected value (weighted average) of critical path tasks IOT determine project duration by using three estimates:
- Most likely
- Pessimistic
- Optimistic
Purpose of Non-Functional Requirement?
Describe the characteristics of the functional requirements. They are not performance or behavioral based.
Who is in Agile team?
- Scrum Master
- Product Owner
- Stakeholders
- Team Members
What is a predecessor activity?
An activity that comes before another activity.
Purpose of Business Requirement?
To satisfy business goals/strategic perspectives
What is a CPM used for?
Critical Path Method
- Determines task float time
- Calculating the overall time from start to finish to complete the project and identifying tasks on the critical path
What does CPM stand for?
Critical Path Method
What is ETC and it’s purpose?
- Estimate to Complete
- Can be used for burn rate determination
What is the purpose of a Run chart?
Displays data observed or collected over time as plots on a line
What type of clarity does Scope Management Plan provide?
- Defines preperation process for scope statement/WBS.
- Documents process that manages/changes project scope
What are quality gates and when are they used?
Used for quality checks @ certain milestones
What are the different Task Duration Estimating Techniques?
- Analogous Estimating
- Expert Judgement
- Parametric Estimating
- Program Evaluation and Review Technique (PERT)
What is CV and it’s formula?
Cost Variance:
- CV = EV - AC
- Tells you whether costs are higher than budgeted or lower than budgeted
- Measures the actual performance to date against what’s been spent.
- Positive = lower than budgeted
- Nagative = higher than budget
What are the key scope management elements?
- Scope change request process
- Deliverables acceptance/validating definition
- WBS creation/maintaining/approving process
What are the functions of a PMO?
- PM project quality guidance
- Maintain project standards, processes, and templates
What does IPECAC stand for?
Initiating Planning Executing Controlling And Closing
