Overall Project+ Material Flashcards
What is a chart of accounts?
IDs that represent each level in WBS outline form
Purpose of Functional Requirement?
- Characteristics needed for project to perform
- Behavioral, performance-oriented; descriptive
What is a business case?
Document to show benefit/reward of potential project
Executing:
Deliverables produced/verified
What is PV?
Planned Value:
- PART OF EARNED VALUE MANAGEMENT
- Cost of authorized work that’s budgeted for a specific schedule activity or WBS component during a given time period or phase.
What is RACI?
Chart to show
Responsible/Accountable/Consulted/Informed
What are the key project charter elements?
- Purpose of project
- Goals/objectives
- Deliverables
- Requirements
- Milestones
- Budget
- Assumptions
- Constraints/risks
- PM
- Sponsor
- Project approval criteria
What is SS?
Start-to-Start
Predecessor must start before successor.
What does a PERT do?
Program Evaluation Review Technique
- (optimistic + pessimistic + (4 × most likely)) / 6
- Calculates expected value (weighted average) of critical path tasks IOT determine project duration by using three estimates:
- Most likely
- Pessimistic
- Optimistic
Purpose of Non-Functional Requirement?
Describe the characteristics of the functional requirements. They are not performance or behavioral based.
Who is in Agile team?
- Scrum Master
- Product Owner
- Stakeholders
- Team Members
What is a predecessor activity?
An activity that comes before another activity.
Purpose of Business Requirement?
To satisfy business goals/strategic perspectives
What is a CPM used for?
Critical Path Method
- Determines task float time
- Calculating the overall time from start to finish to complete the project and identifying tasks on the critical path
What does CPM stand for?
Critical Path Method
What is ETC and it’s purpose?
- Estimate to Complete
- Can be used for burn rate determination
What is the purpose of a Run chart?
Displays data observed or collected over time as plots on a line
What type of clarity does Scope Management Plan provide?
- Defines preperation process for scope statement/WBS.
- Documents process that manages/changes project scope
What are quality gates and when are they used?
Used for quality checks @ certain milestones
What are the different Task Duration Estimating Techniques?
- Analogous Estimating
- Expert Judgement
- Parametric Estimating
- Program Evaluation and Review Technique (PERT)
What is CV and it’s formula?
Cost Variance:
- CV = EV - AC
- Tells you whether costs are higher than budgeted or lower than budgeted
- Measures the actual performance to date against what’s been spent.
- Positive = lower than budgeted
- Nagative = higher than budget
What are the key scope management elements?
- Scope change request process
- Deliverables acceptance/validating definition
- WBS creation/maintaining/approving process
What are the functions of a PMO?
- PM project quality guidance
- Maintain project standards, processes, and templates
What does IPECAC stand for?
Initiating Planning Executing Controlling And Closing
What is AC?
Actual Cost
- PART OF EARNED VALUE MANAGEMENT
- Actual cost of completing work component in a given time period
What is a RAM?
Responsibility Assignment Matrix (RASI):
Maps WBS elements to required resources
Planning:
- Project schedule/WBS created
- Requirements identified
- Budget defined
- Communications, procurement, change management plan developed
What is a PDM?
Precedence Diagramming Method (Activity on node)
A network diagramming method that places activities on nodes, which connect to dependent activities using arrows.
- Boxes = project/node activities
- Arrows = Connect boxes & show dependencies
What does a business case include?
Business need/justification; shows high-level estimated budget/timelines
Monitoring and Controlling:
- Performance measures/reporting
- Quality control
- Request for change/corrective actions occur
What is established after lowest WBS level is established?
- Times/cost estimates
- Resource assignments
- Work package
What is EVM?
Earned Value Management:
Performance measurement technique that compares what your project has produced to what you’ve spent by monitoring the planned value, earned value, and actual costs expended to produce the work of the project.
- Cost Variance: EV – AC
- Cost Performance Index : EV/AC
- Schedule Variance: EV – PV
- Schedule Performance Index: EV/PV
What is FF?
Predecessor must finish before successor finishes.
Parametric estimating formula:
[Quantity of work] x [Productivity rate]
What is SV and it’s formula?
Schedule Variance
- Compares activity’s actual progress to date vs. estimated progress
- Represented in terms of cost
- Tells you whether the schedule is ahead of or behind what was planned for this period
- SV = EV - PV
What is CPI and it’s formula?
Cost Performance Index:
- Measures completed work’s value against actual cost
- EV / AC = CPI
- Shows cost efficiency
- CPI < 1 = Spending less than anticipated