Formulas Flashcards
1
Q
Parametric estimating formula:
A
[Quantity of work] x [Productivity rate]
2
Q
What is the formula for three-point estimating?
A
(a) + (b) + (c) / 3
3
Q
What is CV and it’s formula?
A
Cost Variance:
- The difference between a task’s value at the measurement date and its actual cost.
- CV = EV - AC
4
Q
What is SV and it’s formula?
A
Schedule Variance
- Compares activity’s actual progress to date vs. estimated progress
- Represented in terms of cost
- Tells you whether the schedule is ahead of or behind what was planned for this period
- SV = EV - PV
5
Q
What is the formula for CPI?
A
Cost Performance Index:
- Measures the value of the work completed at the measurement date against actual cost.
- Most critical of all EVM measurements
- If less than 1, you are spending more than anticipated for completed work
- CPI = EV / AC
6
Q
What is the formula for SPI?
A
Schedule Performance Index
- SPI = EV / PV
- If SPI is less than 1, you’re behind schedule at the measurement date.
7
Q
What is the formula for Lines of Communication?
A
n(n-1) / 2