Chapter 5 Flashcards

1
Q

What is a critical path?

A

The longest path from start to finish for the project. Activities with zero float are considered critical path tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is duration compressing?

A

The use of techniques such as fast-tracking or crashing to shorten the planned duration of a project or to resolve schedule slippage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a mandatory dependecy?

A

A type of dependency where the relationship between two tasks is created by the type of work the project requires.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly