Other Formulas Flashcards
1
Q
Present Value
A
FV / ( 1 + i )n where n is superscript iteration
2
Q
Expected Activity Duration (Triangular)
A
(O + M + P) / 3
3
Q
Expected Activity Duration (Beta/PERT)
A
(O + 4M + P) / 6
4
Q
Standard Deviation of an Activity (SD)
A
(P-O) / 6
5
Q
Activity Variance
A
SD squared
6
Q
Range of Activity Duration
A
EAC +/- SD
7
Q
Communication Channels
A
N (N-1) / 2
8
Q
Expected Monetary Value (EMV)
A
Probability x Impact
9
Q
Point of Total Assumption
A
[(Ceiling Price - Target Price) / Buyers Share Ratio] + Target Cost