Earned Value Management Flashcards

1
Q

PV Term

PV Definition

A

Planned Value

Budgeted value of work planned to be done at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV Term

EV Definition

A

Earned Value

Budgeted value of work completed at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC Term

AC Definition

A
Actual Cost (total)
Actual cost of work completed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC Term

BAC Definition

A

Budget At Completion

The original cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV Term
CV Formula
CV Explanation

A

Cost Variance
EV - AC
Negative is bad; Positive is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV Term
SV Formula
SV Explanation

A

Schedule Variance
EV - PV
Negative is bad; Positive is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI Term
CPI Formula
CPI Explanation

A

Cost Performance Index
EV / AC
Under 1 is bad; Over 1 is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI Term
SPI Formula
SPI Explanation

A

Scheduled Performance Index
EV / PV
Under 1 is bad; Over 1 is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
EAC Term
EAC Formula (most accurate)
EAC Formula (variances typical)
EAC Formula (variances atypical)
EAC Formula (poor cost/need completion date hit)
EAC Explanation
A
Estimated At Completion
AC + Bottom-up ETC
BAC / CPI
AC + (BAC-EV)
AC + [ (BAC-EV)/(CPI*SPI)]
Expected total project cost (forecasted based on performance to date)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC Term
ETC Formula
ETC Explanation

A

Estimate To Completion
EAC - AC
Expected cost of work remaining (now until project completes)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC Term
VAC Formula
VAC Explanation

A

Variance At Completion
BAC - EAC
Expected variance over/under budget
Negative is bad; positive is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI Term
TCPI Formula (within budget)
TCPI Formula (budget not achieved)
TCPI Explanation

A

To Complete Performance Index
(BAC-EV)/(BAC-AC)
(EAC-EV)/(EAC-AC)
within budget - Cost performance rate needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly