Earned Value Management Flashcards
PV Term
PV Definition
Planned Value
Budgeted value of work planned to be done at a given time
EV Term
EV Definition
Earned Value
Budgeted value of work completed at a given time
AC Term
AC Definition
Actual Cost (total) Actual cost of work completed
BAC Term
BAC Definition
Budget At Completion
The original cost baseline
CV Term
CV Formula
CV Explanation
Cost Variance
EV - AC
Negative is bad; Positive is good
SV Term
SV Formula
SV Explanation
Schedule Variance
EV - PV
Negative is bad; Positive is good
CPI Term
CPI Formula
CPI Explanation
Cost Performance Index
EV / AC
Under 1 is bad; Over 1 is good
SPI Term
SPI Formula
SPI Explanation
Scheduled Performance Index
EV / PV
Under 1 is bad; Over 1 is good
EAC Term EAC Formula (most accurate) EAC Formula (variances typical) EAC Formula (variances atypical) EAC Formula (poor cost/need completion date hit) EAC Explanation
Estimated At Completion AC + Bottom-up ETC BAC / CPI AC + (BAC-EV) AC + [ (BAC-EV)/(CPI*SPI)] Expected total project cost (forecasted based on performance to date)
ETC Term
ETC Formula
ETC Explanation
Estimate To Completion
EAC - AC
Expected cost of work remaining (now until project completes)
VAC Term
VAC Formula
VAC Explanation
Variance At Completion
BAC - EAC
Expected variance over/under budget
Negative is bad; positive is good
TCPI Term
TCPI Formula (within budget)
TCPI Formula (budget not achieved)
TCPI Explanation
To Complete Performance Index
(BAC-EV)/(BAC-AC)
(EAC-EV)/(EAC-AC)
within budget - Cost performance rate needed