Critical Path Method Rules Flashcards
1
Q
Forward Pass EF
A
Early Finish
Duration + ES - 1
2
Q
Forward Pass ES
A
Early Start of Successor task
latest EF of predecessor + 1
3
Q
Backward Pass LS
A
Late Start
LF - duration + 1
4
Q
Backward Pass LF
A
Late Finish of Predecessor
earliest LS of Successor tasks - 1
5
Q
Float
A
Slack
LF - EF or LS - ES
How many days a task can be delayed before project impact
6
Q
Critical Path
A
Sum of longest duration path
Any delays will delay project