Critical Path Method Rules Flashcards

1
Q

Forward Pass EF

A

Early Finish

Duration + ES - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Forward Pass ES

A

Early Start of Successor task

latest EF of predecessor + 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Backward Pass LS

A

Late Start

LF - duration + 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Backward Pass LF

A

Late Finish of Predecessor

earliest LS of Successor tasks - 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Float

A

Slack
LF - EF or LS - ES
How many days a task can be delayed before project impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical Path

A

Sum of longest duration path

Any delays will delay project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly