OP-2 Flashcards
WHO IS AUTHORIZED TO ISSUE OK’S TO WORK, HOT WORK CLEARANCES
OPERATIONS SUPERVISOR
COLOR OF OPERATIONS INTERAGENCY LOCKS?
ORANGE
CAN YOU USE PLASTIC TAPE TO BARRICADE?
NO
WHAT TAG IS USED FOR TEMPORARY USE FOR EQUIPMENT?
PROVISIONAL ACCEPTANCE TAG
UNDER TEMPORARY RELEASE WHAT IS NEEDED TO WORK?
AN OK TO WORK
AFTER AN INTERAGENCY CLEARANCE IS PLACED WHICH WORKERS DO THE OPERATORS ISSUE THEIR CLEARANCES?
TO THEIR OWN COMPANY PERSONNEL
WHAT ARE WORKERS CARDS USED FOR?
CLEARANCES AND OK’S TO WORK
PROCESS FOR CLEARANCE TO WORK?
VISUALLY CHECK CLEARANCE LIMITS AND SIGN ON
WHAT SHALL A NON-ROUTINE GENERAL SWITCHING HAVE?
UNIQUE SYSTEM GENERATED NUMBER
DOES A WORKER SIGN THE WORKER’S CARD?
NO
WHO IS RESPONSIBLE FOR CONTRACTOR FOLLOWING LOTO
CONTRATOR REPRESENTATIVE
COMPLICATIONS WITH OP-2
CONTACT THE CHIEF WATER AND POWER DISPATCHER
EXCEPT FOR INTER-COMPANY CLEARANCES WHO SIGNS ON FIRST?
ELECTRICIANS SO THEY CAN HANG GROUNDS
CAN YOU USE INDICATOR LIGHTS FOR BREAKER STATUS DURING A CLEARANCE?
NO
RECORD ON ANYTHING BUT THE SWITCHING ORDER FORM?
NO
WHOSE REQUIRED TO CHECK THE CLEARANCE BEFORE SIGNING ON
THE CLEARANCE HOLDER
A PERSON AUTHORIZED TO WORK UNDER A CLEARANCE HOLDER?
A WORKER
WHO CAN STOP UNSAFE WORK
ANYONE
WHATS REQUIRED OF CONTRACTORS TO SIGN ON THE CLEARANCE?
WALK DOWN THE CLEARANCE
A PERSON WORKING UNDER A CLEARANCE
A WORKER
ANY REPOSITIONING OF ANY EQUIPMENT ON 600 VOLTS OR GREATER
TRUE
WHERE DO GROUND LOCATION GET LISTED
EROF
WHERE DO APPRENTICES LOCK ON
MULTI LOCK HASP
WHAT COLOR ARE THE LOCKS THAT OPERATORS USE FOR SWITCHING
RED
WHERE DO WORKERS SIGN ON UNDER A COWORKERS CLEARANCE
THE WORKERS LOCK BOX SIGN ON/SIGN OFF SHEET
WHO HAS CONTROL OVER INTERAGENCY CLEARANCES EQUIPMENT
EACH AGENCIES RESPONSIBLE FOR THEIR OWN EQUIPMENT
ARE SPECIAL CONDITIONS USED TO PROTECT PERSONNEL
NO THEY ARE USED FOR TEMPORARY OPERATIONAL LIMITATIONS
WHEN THE CLEARANCE HOLDER HAS WORKERS UNDER THEM IS 1 LOCK ENOUGH
NO 1 LOCK FOR RED BOX AND 1 FOR WORKERS BOX
WHERE SHOULD WE KEEP WORKERS CARDS AND CLEARANCE DOCUMENTATION
CENTRAL LOCATIONS OR SWITCHING CENTER
WHO UPDATES OP-2
POC OR CHIEF WATER AND POWER DISPATCHER
WHAT HAPPENS TO THE KEY FOR THE YELLOW BOX
THE WORKER AND CLEARANCE HOLDERS KEP THEIR KEYS
WHEN CAN ELECTRICIANS REMOVE GROUNDS UNDER AN OK TO WORK
TEMPORARY RELEASE
WHO CONDUCTS OP-2 ANNUAL AUDITS
CHIEF WATER AND POWER DISPATCHERS OFFICE
IF A SWITCH PERSON FINDS A DEVICE IN THE WRONG POSITION?
NOTIFY OPERATOR TO RE-CHECK THE PROCDURE
WHO APPROVES THE USE OF EXCEPTIONS
BRANCH AND FIELD DIVISION CHIEFS
WHERE DO CONTRACTORS LOCK ON
WORKERS MULTI LOCK HASP ON THE RED CLEARANCE BOX
HOW DO WORKERS LOCK OUT OK’S TO WORK
WITH A BLUE LOCK
HOW SHALL TAGS BE ATTACHED TO EQUIPMENT
WITH TIE WRAPS
WHAT IS USED IN CONJUNCTION WITH CLEARANCE BOUNDARIES?
SAFETY TAGS
WHATS NEEDED TO PERFORM WORK THAT USUALLY ONLY LAST 1 DAY AND DOES NOT AFFECT THE STATE WATER PROJECT AND ISSUED BY THE OPERATIONS SUPERVISOR
OK TO WORK
WHO VERIFIES THE EFFECTIVENESS OF SWITCHING OF A CLEARANCE
SWITCH PERSON