October Study Session Flashcards

1
Q

How much load needs to be shed per 1.0 Hz?

A

6%-10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Uncontrolled loss of firm load for greater than 15 minutes from a single incident is how many MW?

A

Greater than 300 MW for entities with previous year’s peak demand greater than 300 MW

OR

Greater than 200 MW for all other entities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

ACE Equation

A

ACE = (Actual Net Interchange - Scheduled Net Interchange) - 10B(Actual Frequency- Scheduled Frequency) - Interchange Meter Error

B = Frequency Bias Setting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Exporting Power

A

Positive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Importing power

A

Negative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Zone 1 covers how much percent of the line?

A

75-80%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Zone 2 covers how much of the line?

A

100-120%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly