A BA notices that Operating Reserves have steadily decline throughout the hour. What is most likely the cause?
An inaccurate load forecast
Balancing Authority A notices that the Interconnection frequency is 59.94 Hz and their ACE is 0. Which of the following could be the cause of this reading?
A net under-generation in the Interconnection
What is the penalty for a BA violating the Disturbance Control Standard?
Must carry additional Contingency Reserves
Your ACE is a large negative value and system frequency is 59.80 Hz. Your AGC system is pulsing your units down. What should you do?
Suspend AGC and investigate.
When two identical generating units are operated in parallel on governor control, and one machine has a 5% droop and the other has a 10% droop, the unit with the greater (10%) governor droop will:
Respond less to frequency deviations.
On a radial transmission system, a generator has a capacity of 600 MWs. The Droop characteristic is at 5% and the generator is currently loaded at 300 MWs. If frequency suddenly drops to 59.3 Hz, what would be the total generator output?
440 MW
What is the main purpose of the Frequency Bias Setting in the ACE equation?
Assist with arresting frequency deviations
A BA has a Frequency Bias setting of -200 MX/.1Hz. What is the BA’s Frequency Response for a frequency of 59.95 Hz?
100 MWs
Inadvertent energy accumulation occurs due to a difference in Net Actual Interchange and Net Interchange Schedule over time. This energy accumulation can be paid back unilaterally by adjusting delivery of power:
During periods corresponding to those in which the inadvertent energy was accumulated.
You are the Source Balancing Authority for an Arranged Interchange Transaction request. The request has a non-standard ramp rate specified. What action should you take?
Approve the request if able to accommodate.
Who must approve an Interchange Transaction before it becomes Confirmed Interchange?
BA
A BA is scheduled to receive 300 MWs from the north and 400 MW’s from the south for hour ending in 1300. The north schedule is curtailed starting at 1220 with a 10-minute ramp. What is the Net Interchange for the hour?
500 MWh
When current flow increases in the power system, losses in the system will increase based on which of the following relationships?
I2R
Which curve represents the results of a study on voltage response to power flow?
P-V Curve
Two adjacent lines exist in a BA that are the same length and have the same ratings. One line is overhead and the other is underground. How do these two lines respond as load picks up through the day?
The underground line will carry more of the load increase.