OBJ 4.5 Flashcards

Recommend a preliminary project budget and schedule

1
Q

Typical phase breakdown for architectural services:

A

Schematic design = 15% Design Development = 15% Construction documents = 35% Bid/negotiation = 5% Construction administration = 30% Programming is an extra service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Four factors that influence project schedules:

A
  1. Size of the project or scope of service 2. Complexity or budget 3. Estimated review time by stakeholders and city 4. Number of people working on the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Typical Project Schedule

A

Schematic design = 1–2 months Design documentation = 2–6 months Construction documents = 3–7 months Bid/negotiation = 3–6 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Fast-Track Schedule

A

Can reduce the average project time by 10–30%. Beneficial in places where land value is high or there is a time restraint on the project schedule. Construction documents are issued in phases, and construction begins before the design is finished. This schedule requires coordination among architect, contractor, and construction manager. Also requires staged bidding, which may result in multiple contractors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Critical Path

A

The total project time established by the path with the longest total required time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical Activities

A

Activities along the critical path that display both the starting time of any critical activity and any increase in duration that will delay the completion of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Float Path

A

All paths in the network of a critical path method schedule other than the critical path. This is the difference between the critical path and any other path. It is also a measure of the extra time available for an activity or group of activities, which allows extra time for delays to occur in one or more activities. If this time is not exceeded, there will be no delays in the project’s completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Construction Management

A

Activities over and above normal architectural and engineering services conducted during pre-design, design, and construction phases. These contribute to the control of time and cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Mezzanine Loan

A

Often used by developers for large projects, it is a loan with variable interest rates that increase substantially near the time that repayment is due.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Bridge Loan

A

Short-term loan used to quickly purchase property or to finance a project that must begin immediately while waiting for another lender to approve a long-term loan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are site development costs included in the cost of the building?

A

No, the costs to develop a site are in addition to the cost of the building, and each is a separate line item in a budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Inflation

A

Inflation is the general increase of costs of goods and services over time. Since construction projects can take a long time to complete, inflation must be accounted for in a project budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Financing Fees

A

These are not included in the construction budget and must be accounted for by the owner as a separate line item in the overall budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Database

A

There are several commercially available databases of construction cost information, which is gathered from construction projects across the country and published yearly. This information can be used to estimate the costs of future projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly