No.3 Flashcards

1
Q

Network diagram one: activity on arrow

A

Activity on arrow is a network diagramming method in which activities are represented by arrows. The tail of the arrow represents the start and the head represents the finish of the activity (the length does not represent the expected duration of the activity). Activities are connected at points called nodes(drawn as circles) to illustrate the sequence in which the activities are to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Network diagrams: activity on node

A

Activity in node is a network diagramming method in which activities are represented in boxes or nodes. Activities are linked by arrows tos his the sequence in which activities are to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Network definitions

A
Es = Earliest starting time
Fs= earliest finishing time 
Ls = latest starting time 
LF = latest finishing time 
Ts= total slack (= ls-Es OR lf-ef 
Fs =free slack ( es-ef)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Total slack

A

Total slack is the amount of time an activity can be delayed without delaying the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Free slack

A

Free slack is the amount of time an activity can be delayed without delaying the early start of any successor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Network diagram

A

No. Activity Dur
ES. Name. EF
LS. TS. FS. LF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CriticAl path definition

A

Critical path is the longest combination of dependant events through the project
Includes those activities that have no slack and if delayed will delay the project as a whole

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Network diagram shortfalls

A

Network diagram shortfalls are

Difficult to visualise concurrent activities as no time axis is available

Resource usage is neglected (concurrent use of resources are ignored)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Time estimation

A

A time estimate is an estimation of the time under uncertainty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Three point estimation

A

Ave weighted = opt + peas + 4 ml all /6

Opt = most optimistic time estimate
Pess = most pessimistic time estimate
Ml =most likely time estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Time buffer calculation

A

A safe time estimate (prob of 90% that the actual time will fall within this estimate)

An aggressive time estimate (prob of 50% that the actual time will fall with this estimation)

For each activity calculate the difference between safe and aggressive time estimations

Sum the differences together for the activities on the critical path

Use a fraction of the summed difference as the time buffer for the project (aggregation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bar charts (gantt charts)

A

Simplest and most common way to present a project plan

Portrays work packages, tasks and activities as well as the status of the project visually against a time axis

Is developed from a WBS analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Progress estimation (50-50 rule)

A

Breakdown tasks in roughly the same sizes in terms of time

Apply the 50-50!47@3: 50% progress of activity is started and remaining 50% when completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Resource loading

A

Resource loading describes the number of individual resources the existing schedule requires

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Resource levelling

A

Resource levelling aims to minimise the period by period variations in resource loading using slack times, off loading and multi tasking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Work authorisation

A

Formalises agreement between people delegating work and those accepting responsibility to do the work (SLA)

17
Q

Control process

A

The control process is the setting of a standard (objective or plan)

It determines facts about the actual situation and anticipating future deviations from the plan

Comparing the actual facts with the standard
Taking actions to bring the actual situation in line with the standard

18
Q

Project control characteristics

A

Look ahead
Frequent monitoring
Balance quality cost and time
Contingencies

19
Q

Earned value concept

A

The earned value concept is integrating cost reporting with progress reporting
It represents an estimate of the percentage of work completed thus far

20
Q

Earned value definitions

A
Pv = planned value (budgeted cost of work scheduled)
Ev = earned value (budgeted cost of work performed or supposed cost)

Ac = actual cost

Sv = schedule variance (Sv = ev -pv)
Tv = time variance (sp - status date)
Sp is the date where pv = ev in time units)

Cv = cost variance (cv = ev- ac)

Positive variance implies good result s

21
Q

Schedule performance index SPI

A

SPI compares the earned value with the plan. Gives an indication of performance relative to the schedule. Spi = ev/pv
If SPI >1 it’s ahead of schedule

22
Q

Cost performance index

A

CPI compares the earned value with the actual cost
Measurement of performance relative to the budget
CPI = EV/AC

CPI >1 cost saving