No.2 Flashcards

1
Q

Work breakdown structure WBS

A

The main purpose is to define the hierarchy of work to be performed, which forms the basis for:

Budgeting man power and resources
Scheduling
Reporting relationships and reporting project status and expenditures
Ensuring everyone in the project hierarchy, including functional managers have considered all components of the work that have to be performed carefully

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Factors shaping the WBS

A
FActors shaping the WBS include:
Environment
Business need
What deliverables or products will be produced 
New or existing technology
Levels of output expected 
First time or been done previously
Amount of risk involved
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Characteristics of the WBS

A

Characteristics of the WBS:
Describe all work that needs to be performed (verbs at activity level)
Define manageable work packages and activities that could be performed independently by responsible people unambiguously
Defines the responsibility of individuals and teams

Developing a wbs is not a mechanistic process - it involves decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Developing the WBS

A
THe WBS structure can be started in a number of ways:
Using phases (level 1) followed by the products and deliverables (level 2)

Using major deliverables (level 1) followed by the work packages that deliver each deliverable (level 2)

Using sub projects or contracts (level 1) followed by the sellers contractors own wbs as part of the contracted work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Importance of proper work definiton

A

It forms the basis for project plans and schedules

Projects are organised by organising work packages. It involves TV w assembling of resources and defeating responsibilities

The project effort is controlled by the effectiveness of people working on individual activities and tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Resourcing

A

Resource planning has to do with determining what resources will be required to complete with the project. Resources include: people equipment material information

For project level resource types are allocated
For the project phase level, specific resources are allocated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Resource allocation

A

Resource allocations is concerned with determining the best trade offs between avalajbke resources, including time, throughout the duration of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Responsibilities assignment

A
R= responsible 
A = approve 
C = consult 
I = inform
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimation of effeort

A

When will the project be completed and what will it cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimation tools and techniques

A

Expert judgment - asking experts
Analogous estimation - use previous similar activities
Three point estimation - estimating probability distribution and determine aggressive and safe estimates.
Bottom up estimation - roll up lower level activities costs estimates to determine task costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Bottom up estimation

A

Activities to work packages to phase to project

Activities start at bottom and works up to final one project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimation under uncertainty

A

Define what is being estimated, each participant states estimate, several rounds to work toward consensus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Three point estimation (pert approximation)

A

Ave weighted = opt +less + 4 ml all /6

Opt = most optimistic cost estimate 
Peas = moss pessimistic cost estimate 
Ml = most likely cost estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly