No.2 Flashcards
Work breakdown structure WBS
The main purpose is to define the hierarchy of work to be performed, which forms the basis for:
Budgeting man power and resources
Scheduling
Reporting relationships and reporting project status and expenditures
Ensuring everyone in the project hierarchy, including functional managers have considered all components of the work that have to be performed carefully
Factors shaping the WBS
FActors shaping the WBS include: Environment Business need What deliverables or products will be produced New or existing technology Levels of output expected First time or been done previously Amount of risk involved
Characteristics of the WBS
Characteristics of the WBS:
Describe all work that needs to be performed (verbs at activity level)
Define manageable work packages and activities that could be performed independently by responsible people unambiguously
Defines the responsibility of individuals and teams
Developing a wbs is not a mechanistic process - it involves decisions
Developing the WBS
THe WBS structure can be started in a number of ways: Using phases (level 1) followed by the products and deliverables (level 2)
Using major deliverables (level 1) followed by the work packages that deliver each deliverable (level 2)
Using sub projects or contracts (level 1) followed by the sellers contractors own wbs as part of the contracted work
Importance of proper work definiton
It forms the basis for project plans and schedules
Projects are organised by organising work packages. It involves TV w assembling of resources and defeating responsibilities
The project effort is controlled by the effectiveness of people working on individual activities and tasks
Resourcing
Resource planning has to do with determining what resources will be required to complete with the project. Resources include: people equipment material information
For project level resource types are allocated
For the project phase level, specific resources are allocated
Resource allocation
Resource allocations is concerned with determining the best trade offs between avalajbke resources, including time, throughout the duration of the project
Responsibilities assignment
R= responsible A = approve C = consult I = inform
Estimation of effeort
When will the project be completed and what will it cost
Estimation tools and techniques
Expert judgment - asking experts
Analogous estimation - use previous similar activities
Three point estimation - estimating probability distribution and determine aggressive and safe estimates.
Bottom up estimation - roll up lower level activities costs estimates to determine task costs
Bottom up estimation
Activities to work packages to phase to project
Activities start at bottom and works up to final one project
Estimation under uncertainty
Define what is being estimated, each participant states estimate, several rounds to work toward consensus
Three point estimation (pert approximation)
Ave weighted = opt +less + 4 ml all /6
Opt = most optimistic cost estimate Peas = moss pessimistic cost estimate Ml = most likely cost estimate