NERC PRACTICE SET 4 Flashcards

1
Q

In the ACE equation, (NIA - NIS) reflects the _______ portion.

a. frequency
b. interchange
c. load
d. generation

A

b. interchange

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Multiple contingencies occurring within ______ of each other shall be treated as a single contingency.

a. One minute or less
b. 15 minutes
c. 5 minutes
d. 2 minutes

A

a. One minute or less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

On a radial transmission system a generator has a capacity of 600 MWs. The Droop
characteristic is at 5% and the generator is currently loaded at 300 MWs. If frequency
suddenly drops to 59.3 Hz, what would be the total generator output?

a. 350
b. 400
c. 440
d. 600

A

c. 440

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Interconnection frequency is 60.20 Hz. Your ACE is a large positive value, and your AGC is
pulsing your units down. What should you do?

a. Place AGC in constant frequency control
b. Place AGC in flat tie line control
c. Suspend AGC and investigate
d. Leave AGC in operation as your units respond

A

d. Leave AGC in operation as your units respond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Balancing Authority B has scheduled interchange of 100 MW from Balancing Authority A
and 100 MW to Balancing Authority C. Actual interchange is 115 MW from Balancing
Authority A and 95 MW to Balancing Authority C. What is the inadvertent interchange
for Balancing Authority B?

a. -20 MW
b. 20 MW
c. -40 MW
d. 40 MW

A

a. -20 MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Low Voltage is a result of:

a. VAR Losses associated with heavy power transfers
b. Insufficient generation
c. Insufficient transmission capacity
d. Insufficient shunt reactors in service

A

a. VAR Losses associated with heavy power transfers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

At 1105 frequency drops to 59.95 Hz due to a disturbance elsewhere in the Interconnection. The frequency returns to 60.00 Hz shortly afterwards and Balancing Authority A’s ACE is zero for the remainder of the hour. How would this affect the Balancing Authority’s Inadvertent Interchange for that hour?

a. Inadvertent would increase in the positive direction.
b. Inadvertent would increase in the negative direction.
c. Inadvertent would remain unchanged.
d. Inadvertent would go to zero.

A

a. Inadvertent would increase in the positive direction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A Balancing Authority’s ACE has been 0 for the entire hour. After the hour the Balancing Authority operator notices that last hour its Inadvertent was +20. What is the likely cause of this Inadvertent?

a. Average frequency was high during the last hour.
b. Average frequency was lower than 59.96 Hz during the last hour.
c. Frequency was exactly 60.00 Hz for the entire last hour.
d. The average frequency for the last hour was 60.02 Hz.

A

b. Average frequency was lower than 59.96 Hz during the last hour.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Two Balancing Authorities have arranged a schedule of 500 MW between them, well within their transfer capability. Before the ramp has begun, the Reliability Coordinator informs them that implementing the schedule will result in overloading a transmission line in a neighboring system. What action should the two Balancing Authorities take?

a. Reduce the schedule to a level that will not cause a problem in the neighboring system.
b. Promise to reduce the schedule in the next scheduling hour, since it is too late to make changes now.
c. Inform the Reliability Coordinator that they are well below their allowed schedule magnitude and will not make any changes.
d. Implement the schedule and rely on the Reliability Coordinator to initiate transmission loading relief procedures if a problem actually occurs.

A

a. Reduce the schedule to a level that will not cause a problem in the neighboring system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The load on a power transformer is 80 MW and 60 MVAR. What is the Transformer’s Power Factor?

a. 0.80 PF
b. 0.70 PF
c. 0.60 PF
d. 0.50 PF

A

a. 0.80 PF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A 50 MVA rated transformer has 40 MW of load. How many MVARs can flow through the transformer without exceeding the rating?

a. 50 MVAR
b. 40 MVAR
c. 30 MVAR
d. 0 MVAR

A

c. 30 MVAR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A transformer rated at 550 MVA has 500 MW and 55 MVAR passing through it. Which of the following is true?

a. No action is required because the transformer is within limits
b. No action is required because the transformer is less than 10% above its limit
c. The load on the transformer must be reduced because it is above its limit
d. The load on the transformer cannot be determined without knowing the power factor

A

a. No action is required because the transformer is within limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which statement describes a transmission line loaded at its Surge Impendence Loading (SIL)?

a. The line is inductive
b. The line is capacitive
c. The lines natural capacitance is equal to its inductance with no impact to voltage.
d. The line will exceed it SOL

A

c. The lines natural capacitance is equal to its inductance with no impact to voltage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

350 MW is flowing into a 230/100 kV transformer rated at 500 MVA transformer. What MW value is flowing on the low side of the transformer?

a. 100 MW
b. 230 MW
c. 350 MW
d. 500 MW

A

c. 350 MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If the frequency on both sides of an open breaker is exactly matched, which of the following statements is true?

a. The phase angle across the breaker is zero
b. The phase angle across the breaker is constant
c. The voltage magnitude across the breaker is matched
d. The phase angle across the breaker is 180 degrees

A

b. The phase angle across the breaker is constant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What direction do MVARs typically flow in a power system?

a. On a decreasing power angle
b. Higher voltage to lower voltage magnitude
c. Lower voltage to higher voltage magnitude
d. Higher to lower voltage angle

A

b. Higher voltage to lower voltage magnitude

17
Q

Protective relays have current flowing to them that is proportional to the current in the primary circuit. In most cases, what is used to transform the current from the primary circuit to a smaller proportional amount that flows to the protective relay?

a. Current transformers
b. Series capacitors
c. Voltage reduction relays
d. Potential transformers

A

a. Current transformers

18
Q

A voltage collapse is an uncontrollable reduction is system voltage caused by a deficiency of reactive power to serve the inductive load. This condition can be a result of which of the following?

  1. Heavy power transfers
  2. Forced transmission outages
  3. Forced reactive resource outages such as generators and shunt
    capacitors

a. 1 only
b. 2 and 3
c. 3 only
d. 1, 2, and 3

A

d. 1, 2, and 3

19
Q

Which entities are required to perform an Operational Planning Analysis (next day study) to assess whether planned operations will exceed any SOLs?

  1. Reliability Coordinators
  2. Transmission Operators
  3. Balancing Authorities
  4. Transmission Planners

a. 1 and 2
b. 2 and 3
c. 2 and 4
d. 3 and 4

A

a. 1 and 2

20
Q

A line is operating at 125% (25% above its SOL) following several parallel line outages caused by a severe storm. The flow on this line is from Bus A, which is north, to Bus B, which is south. As a System Operator, you decide to use generation redispatch to relieve the line loading problem. What should your course of action be?

a. Increase generation on the north side of Bus A and decrease generation on the south side of Bus B.
b. Decrease generation on the north side of Bus A and decrease generation on the south side of Bus B.
c. Increase generation on the north side of Bus A and increase generation on the south side of Bus B.
d. Decrease generation on the north side of Bus A and increase the generation on the south side of Bus B.

A

d. Decrease generation on the north side of Bus A and increase the generation on the south side of Bus B.

21
Q

A geomagnetic disturbance is predicted to occur tomorrow. Which parts of the system are most likely to experience problems?

a. HVDC transmission lines
b. Delta connected transformers
c. Wye connected transformers
d. Large generators

A

c. Wye connected transformers

22
Q

A severe lightning storm has hit your transmission system. Two 345 kV lines have been damaged and cannot be re-energized. Two large generators of 500 MW and 700 MW have tripped off-line. No additional generators are available to bring on line. The Parallel 230 kV and 138 kV lines are loaded at their emergency limits. As a System Operator, what should you do?

a. Wait until the generator operators report on how long it will be before the generators can be back on-line.
b. Shed load.
c. Place all the shunt reactors and shunt capacitors in service.
d. Remove the Zone 3 tipping from the over loaded transmission lines to prevent them from tripping.

A

b. Shed load.

23
Q

Reactive Power is needed to support what?

a. Interchange
b. ACE
c. Losses
d. Power flow

A

d. Power flow

24
Q

When a system is on the verge of a voltage collapse and all reactive resources are at maximum output. What else should a system operator consider to alleviate the problem.

a. Lower voltage to reduce local loads
b. Request the RC to shed load in their area
c. Reduce load in the area with the low voltage
d. Make sure all shunt reactors are in service

A

c. Reduce load in the area with the low voltage

25
Q

Which power system equipment would a System Operator use to reduce a high voltage
condition?
a. Series reactor
b. Shunt reactor
c. Shunt capacitor
d. Series capacitor

A

c. Shunt capacitor