Your system is experiencing heavy loading and low voltage. What is the first response for a System Operator?
a) Take lines out of service
b) Put capacitors in service
c) Put reactors in service
d) Lower loads
b) Put capacitors in service
Which of the following action is appropriate for mitigating heavy power transfer on a transmission line?
a) Put parallel line in service
b) Put a capacitor in service
c) Put a reactor in service
d) Increase generation
a) Put parallel line in service
Line A is a 100 mile 500 kV transmission line. Line B is a 10 mile 500 kV transmission line. Both
lines are lightly loaded. Line B is contributing 3.2 MVAR to the bus. How much MVAR will line A
contribute to the bus?
a) 10 times 3.2 MVAR
b) Less than 3.2 MVAR
c) Equal to 3.2 MVAR
d) More than 3.2 MVAR
d) More than 3.2 MVAR
What are the effects of transmission line loading above its surge impedance loading?
a) The line acts like a capacitor
b) The line acts like a reactor
c) The line ceases to function
d) The line’s losses decrease
b) The line acts like a reactor
After a forced outage, a contingency analysis study shows that one more outage will cause an
IROL violation. There is a parallel line out for maintenance that can be returned within a 4 hours
window if requested. What must be done first to mitigate this condition?
a) Put the parallel line in service with protection
b) Put the parallel line in service without protection
c) Take the protective tripping off the line
d) Call the RC and formulate an Operating Plan
d) Call the RC and formulate an Operating Plan
A transformer rated at 100 MVA has 80 MW flowing through it. How many MVARS could flow
through it without exceeding its rating?
a) 80 MVAR
b) 60 MVAR
c) 50 MVAR
d) 20 MVAR
b) 60 MVAR
A system operator notices that frequency has dropped to 59.95 Hz and his Balancing Area’s ACE
is near zero. The Balancing Authority has plenty of generation to help restore the Interconnection Frequency. Which statement best describes the appropriate action?
a) Increase generation to improve his CPS score.
b) Notify the deficient BA to sell them power.
c) Take units off of AGC.
d) Ensure that generators are providing governor response.
d) Ensure that generators are providing governor response.
A transmission path is rated at 550 MVA and has 500 MW and 55 MVAR of power flowing on the
line. What action is required of the system operator?
a) The line has exceeded its rating is beyond its rating and power flow must be reduce.
b) The line will trip if not removed from service.
c) No action beyond continued monitoring is required
d) Reconfiguration is needed to lower the reactive power flow
c) No action beyond continued monitoring is required
If two heavily loaded transmission lines into a Balancing Authority area trip resulting in that area
being islanded, what is the likely impact to Interconnection frequency?
a) Interconnection frequency will remain the same
b) Interconnection frequency will likely increase
c) Interconnection frequency will likely decrease
d) The island will have its own frequency
b) Interconnection frequency will likely increase
Which transmission line type will likely produce more reactive power?
a) Underground cable
b) Lightly loaded short overhead line
c) Loaded tie-line
d) Radial Lines with capacitor banks in service
a) Underground cable
Power is flowing from source BA 1 to sink BA 2 and loading the tie-lines. Which action would
reduce the power flow on the tie-lines?
a) Reliability Coordinator declaring an EEA
b) Increasing generation in the sink BA
c) Increasing generation in the source BA
d) Buy more power from source BA
b) Increasing generation in the sink BA
An Emergency outage request would result in exceeding an SOL? Which actions need to be
considered prior to taking the outage?
a) Will it exceed SOL study
b) Redispatch generation or reconfigure transmission
c) Shed Load to allow outage
d) Open the line that will exceed SOL
b) Redispatch generation or reconfigure transmission
A local transmission line trips after making contact with a tree. At one terminal SCADA shows
every breaker on the bus standing open. What likely caused this result?
a) Differential relay
b) Ground relay
c) SPS/RAS
d) Breaker Failure relay
d) Breaker Failure relay
A line has 200 ohms of capacitive reactance and 600 ohms of inductive reactance, what is the
total reactance of the line?
a) 200 ohms
b) 400 ohms
c) 600 ohms
d) 800 ohms
b) 400 ohms
When you need to increase MVARS due to inductive reactive power demands, which equipment
would you primarily use?
a) Generators kV setpoint
b) Capacitor Banks
c) Shunt Reactor
d) Transformer Tap Changer
b) Capacitor Banks