HSI Quiz Bank Flashcards

1
Q

Which of the following terms is defined as the scan rate values of a Balancing Authority’s ACE measured in MW, which includes the difference between the Balancing Authority’s Net Interchange Actual and its Net Interchange Scheduled, plus its Frequency Bias obligation, plus any known meter error?

Automatic Time Error
Reporting ACE
Reserve Sharing Group Reporting
ACE Control Error

A

Reporting ACE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The Control Performance Standards limit the width of the regulation boundaries for which of the following?

AGC
ACE
Frequency
Voltage

A

ACE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Each Balancing Authority must fulfill its commitment to the Interconnection and not __________the other Balancing Authorities in the Interconnection.

Communicate with
Own Joint units
Burden
Trade with

A

Burden

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which of the following terms applies to the Western Interconnection only, and the addition of a component to the ACE equation that modifies the control point for the purpose of continuously paying back Primary Inadvertent Interchange to correct accumulated time error?

Reserve Sharing Group Reporting ACE
Automatic Time Error Correction
Reporting ACE
Regulation Reserve Sharing Group

A

Automatic Time Error Correction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

In the ACE equation (NIA - NIS) reflects which portion?

Load
Interchange
Generation
Frequency

A

Interchange

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You are a Balancing Authority Operator. A neighboring Balancing Authority in the Interconnection suddenly has a 500 MW generator trip due to a generator ground. What part of the ACE equation, ACE = (NIA-NIS) - 10B (FA-FS) - IME, allows you and other Balancing Authorities in the Interconnection to help stabilize the Interconnection frequency error?

IME
(FA- FS) - IME
NIA - NIS
10B (FA-FS)

A

10B (FA-FS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Balancing Authority A is scheduled to import a net 200 MW and is actually importing a net 150 MW. The Bias Setting is -100 MW/.1 HZ and Actual Frequency is 59.95 Hz. What is Balancing Authority A’s ACE reading?

-100 MW
-55 MW
+100 MW
0 MW

A

0 MW

Feedback: The key to this question is recognizing the word import. That means the schedule and actual interchange are negative values.

ACE = [(-150) – (-200)] – [10(-100)(59.95 – 60.00)]

ACE = [+50] – [+50]

ACE = 0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following elements is NOT included in the ACE equations frequency component?

Actual Frequency (FA)
Scheduled Frequency (FS)
Meter Error (IME)
Frequency Bias Setting (B)

A

Meter Error (IME)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A Balancing Authority has a tie-line meter that has been verified reading 5 MWs high. The flow on the tie-line is out of the BA’s Area. What effect will this have on the ACE reading?

ACE will read 5 MW above its actual value
ACE will not be affected by the inaccurate reading
It depends on whether frequency is high or low
ACE will read 5 MW below its actual value

A

ACE will read 5 MW above its actual value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happens when a Balancing Authority is being evaluated for its CPS1 Control Performance, and a sustained interruption in the recording of ACE or Frequency Deviation due to loss of telemetering or computer unavailability results in a one-minute interval not containing at least 50% of samples of both ACE and Frequency Deviation?

The one-minute interval is excluded from the CPS1 calculation.
The information that was salvaged is saved and added to another partial interrupted minute, then included in the calculation when the total information gathered equals one-minute.
The information is used because at least 10% of the data was accumulated.
The information from the partial minute is sent to the NERC Operating Committee for evaluation.

A

The one-minute interval is excluded from the CPS1 calculation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A Balancing Authority has an ACE of -50 MW when Interconnection frequency is 60.04 Hz. Is the BA in danger of exceeding the Balancing Authority ACE Limit (BAAL)?

Yes, if the BA’s Frequency Bias is less than or equal to -100MW/.1 Hz
No, there is no low BAAL when frequency is high
Yes, if the BA’s Frequency Bias is greater than -100MW/.1 Hz

A

No, there is no low BAAL when frequency is high

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

To conform to CPS requirements, a Balancing Authority must have which of the following?

CPS1 greater than or equal to 90% or BAAL greater than or equal to 100%.
CPS1 greater than or equal to 100% and ACE does not exceed BAAL more than 15 consecutive minutes.
CPS1 greater than or equal to 90% and ACE does not exceed BAAL more than 30 consecutive minutes.
CPS1 greater than or equal to 100% and ACE does not exceed BAAL more than 30 consecutive minutes.

A

CPS1 greater than or equal to 100% and ACE does not exceed BAAL more than 30 consecutive minutes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The purpose of Reliability Standard BAL-001, which defines CPS1 and BAAL compliance requirements is:

To ensure Balancing Authorities within an Interchange with multiple Balancing Authorities maintain regulation reserves equal to or greater than their MSSC.
To control Interconnection frequency deviations to less than or equal to two standard deviations.
To ensure equitable market operations between Balancing Authorities within the identified BES Interchange.
To control Interconnection frequency within defined limits.

A

To control Interconnection frequency within defined limits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If a Balancing Authority does not comply with the Control Performance Standard, it is not permitted to provide which of the following for any other Balancing Authority entities?

Regulation of other services related to control performance
Scheduled transactions
System support
Frequency control

A

Regulation of other services related to control performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which statement best describes the CPS1 requirement?

The Responsible Entity must operate so its CPS1 is greater than or equal to 100% for the preceding 12-month period.
The average ACE for a defined 10-minute period must be within a limit called L10.
ACE must follow changes in load and schedule within a bandwidth called L10.
ACE must start to return to zero one minute after crossing zero.

A

The Responsible Entity must operate so its CPS1 is greater than or equal to 100% for the preceding 12-month period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A Balancing Authority’s CPS1 calculation is computed using its clock-minute average of two values. What are those two values?

Actual and Scheduled Net Interchange NIA and NIS.
Reporting ACE and Frequency Error
L10 and Reporting ACE
Actual and Scheduled Frequency (FA and FS)

A

Reporting ACE and Frequency Error

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A Balancing Authority is slightly undergenerating its Actual System Frequency (FA) is 60.03 Hz. What is the result of the Balancing Authority’s action?

The Balancing Authority is hurting the Interconnection Frequency.
The Balancing Authority is helping the Interconnection Frequency.
The Balancing Authority is in CPS1 violation.
The Balancing Authority is in BAAL violation

A

The Balancing Authority is helping the Interconnection Frequency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should a Balancing Authority set Scheduled Frequency to for a slow Time Error Correction?

59.80 Hz
59.98 Hz
60.20 Hz
60.02 Hz

A

60.02 Hz

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What happens to frequency on the Interconnection (measured by FA in the ACE equation) when its generation does not match its load?

The Interconnection’s Scheduled Frequency will no longer be included in the ACE equation calculation.
The Interconnection’s Actual Frequency will match its Scheduled Frequency.
The Interconnection’s Frequency will increase by 0.05 Hz.
The Interconnection’s Actual Frequency will either increase or decrease in proportion to the generation/load mismatch

A

The Interconnection’s Actual Frequency will either increase or decrease in proportion to the generation/load mismatch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What should a Balancing Authority set Scheduled Frequency to for a fast Time Error Correction?

60.20 Hz
59.98 Hz
60.02 Hz
59.80 Hz

A

59.98 Hz

Feedback: If there is a fast time error, that means frequency has averaged above 60.00 Hz for a period of time. To correct that time error. All BAs in the Interconnection set their Scheduled Frequency to 59.98 Hz to bring the average frequency back down to 60.00 Hz.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Balancing Authority B has a Net Interchange Schedule of 300 MW and a Frequency Bias of -80 MW/.1 Hz. A 400 MW generator in the BA’s area trips resulting in a New Interchange Actual reading of -80 MW and frequency of 59.96 Hz. What is BA B’s ACE?

-384 MW
+412 MW
-412 MW
-700 MW

A

-412 MW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

When does the Contingency Reserve Restoration Period begin?

At the top of the hour after the Reportable Disturbance
At the end of the Disturbance Recovery Period
When all Contingency Reserve has been exhausted
At the start of the Reportable Disturbance

A

At the end of the Disturbance Recovery Period

Feedback: The Contingency Reserve Restoration Period begins at the end of the Disturbance Recovery Period.

NERC Standard BAL 002

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How often must each Reserve Sharing Group and Balancing Authority review their probable contingencies to determine their prospective most sever single contingency?

Monthly
Annually
Quarterly
Semi-annually

A

Annually

Feedback: At a minimum, the Balancing Authority or Reserve Sharing Group shall carry at least enough contingency reserve to cover the most severe single contingency. All Balancing Authorities and Reserve Sharing Groups shall review, no less frequently than annually, their probable contingencies to determine their prospective most severe single contingencies.

Balancing Authorities change. New generators and lines are added as system demands grow. Failing to recognize the need for increased contingency reserve could cause a Balancing Authority or its Reserve Sharing Group to fail to meet the DCS.

NERC Standard BAL-002

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The Contingency Reserve Restoration period is ________.

One minute
90 minutes
15 minutes
45 minutes

A

90 minutes

Feedback: The Contingency Reserve Restoration Period begins at the end of the Disturbance Recovery Period.

The default Contingency Reserve Restoration period is 90 minutes. This period may be adjusted to better suit the reliability targets of the Interconnection based on analysis approved by the NERC Operating Committee.

The Contingency Reserve Restoration period is 90 minutes beyond the 15-minute Disturbance Recovery Period. Meaning the Balancing Authority or Reserve Sharing Group must obtain enough reserves to respond to the next most severe single contingency not longer than 90 minutes later. Shedding load would be an option to acquire enough contingency reserves to meet the next reportable disturbance if the reserves cannot be obtained by more normal means.

NERC Standard BAL-002

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Which of the following is a potential source of Contingency Reserve? 1. Offline generation that takes 10 minutes to start and ramp to full output 2. Online generation at full load 3. Controllable load resources 4. Voltage reductions 2 and 3 1 and 2 1 and 3 3 and 4
1 and 3 Feedback: Each Balancing Authority shall have access to and/or operate Contingency Reserve to respond to Disturbances. Contingency Reserve may be supplied from generation, controllable load resources, or coordinated adjustments to Interchange Schedules. NERC Standard BAL 002
24
A Balancing Authority experiences a Reportable Balancing Contingency Event which results in ACE dropping to -540 MW. The BA's ACE was 0 prior to the event. Ten minutes into the recovery, a 150 MW generator trips, resulting in ACE dropping again. What must the BA return its ACE to by the end of the recovery period to be compliant? -150 MW 150 MW 0 MW -390 MW
-150 MW
25
Multiple contingencies occurring within _________ of each other shall be treated as a single contingency. 5 minutes One minute or less 2 minutes 15 minutes
One minute or less Feedback: Simultaneous contingencies - multiple contingencies occurring within one minute or less of each other shall be treated as a single contingency. If the combined magnitude of the multiple contingencies exceeds the most severe single contingency, the loss shall be reported, but excluded from compliance evaluation. NERC Standard BAL-002
26
If a Reserve Sharing Group member has experienced a Reportable Disturbance condition but does not call for reserve activation from other members, the entire group is considered to be in a disturbance condition. True False
False Feedback: Each Reserve Sharing Group shall comply with the DCS. A Reserve Sharing Group shall be considered in a Reportable Disturbance condition whenever a group member has experienced a Reportable Disturbance and calls for the activation of Contingency Reserves from one or more other group members. (If a group member has experienced a Reportable Disturbance but does not call for reserve activation from other members of the Reserve Sharing Group, then that member shall report as a single Balancing Authority.) NERC Standard BAL 002
27
A Balancing Authority has a normal load of around 8500 MW. Its most severe single contingency is a 700 MW coal-fired steam unit. At 0810, the ACE value was at -55 MW when a 600 MW generator in the Balancing Authority's northern area tripped off line due to a generator differential. This event resulted in a large negative ACE for the Balancing Authority. What value must ACE return to and in what time frame to avoid a DCS violation? -55 MW ACE in 15 minutes Zero ACE in 15 minutes -55 MW ACE in 10 minutes Zero ACE in 10 minutes
-55 MW ACE in 15 minutes Feedback: A Balancing Authority shall return its ACE to zero if its ACE just prior to the Reportable Disturbance was positive or equal to zero. For negative initial ACE values just prior to the Disturbance, the Balancing Authority shall return ACE to its pre-Disturbance value within 15 minutes. NERC Standard BAL 002
28
A Balancing Authority's largest single contingency is a unit rated at 1,000 MW. Which of the following disturbances would constitute a reportable disturbance for DCS evaluation based on the NERC DCS criteria? The loss of a 750 MW generating unit at 100% output The loss of a 950 MW generating unit at 100% output The loss of two 400 MW generators only five minutes apart The loss of 715 MW of firm load
The loss of a 950 MW generating unit at 100% output Feedback: BAL-002 states "A Balancing Authority or Reserve Sharing Group shall calculate and report compliance with the Disturbance Control Standard for all Disturbances greater than or equal to 80% of the magnitude of the Balancing Authority's or of the Reserve Sharing Group's most severe single contingency loss." The 950 MW unit is 95% of the most severe single contingency and meets the criterion of "greater than or equal to 80%..." NERC Standard BAL 002
29
A Balancing Authority has 600 MW generator which is determined to be its MSSC. How much contingency reserve is the BA required to have available? 480 MW 500 MW 660 MW 600 MW
600 MW Feedback: A Balancing Authority is required to maintain enough contingency reserve to cover its Most Severe Single Contingency (MSSC). In this example 600 MW.
30
The minimum compliance for NERC Disturbance Control Standard (DCS) is ________? 90% of all reportable disturbances 90% of all disturbances 100% for all reportable disturbances 100% for all generator tips
100% for all reportable disturbances Feedback: A Balancing Authority or Reserve Sharing Group shall meet the Disturbance Recovery Criterion within the Disturbance Recovery Period for 100% of reportable disturbances. NERC Standard BAL 002
31
The change in a balancing area's supply and demand following a sudden loss of load or generation within the Balancing Authority's boundaries, results in a sudden change in that Balancing Authority's _________. ACE Frequency Bias Setting CPSI score Contingency reserves
ACE Feedback: The change in demand-supply balance following a sudden loss of load or generation failure, results in a sudden change in the Balancing Authority's ACE, which means the Balancing Authority or Reserve Sharing Group is off schedule and dragging or pushing the tie lines. If the Balancing Authority lost load, then they would have too much generation causing the Interchange Actual to exceed the Interchange Schedule of the ACE equation. Power flow off the Balancing Authority's tie line in excess of the Interchange Schedule. Losing generation would cause the Balancing Authority to have more load then generation, causing the Interchange Actual to have power flowing into the Balancing Authority of the Interchange Schedule. Performance Standards Reference Document Section 2 NERC Reliability Standard BAL-001 NERC Reliability Standard BAL-002
32
The Disturbance Control Standard measures a Balancing Authority's ability to utilize ____________. Regulating reserve Operating reserve Contingency reserve Curtailable load
Contingency reserve Feedback: DCS, or the Disturbance Control Standard, measures a Balancing Authority's ability to respond to system disturbances and measure whether the Balancing Authority's contingency reserve is adequate. If the calculated percent recovery from disturbances is less than 100%, the Balancing Authority or Reserve Sharing group must increase its contingency reserve requirement by the contingency reserve adjustment factor. NERC Standard BAL 002
33
A generator large enough to cause frequency to drop to 59.950 Hz tripped in your Interconnection. Your Balancing Authority's Frequency Bias is 120 MW/0.1 Hz. How many MWs would your system initially contribute to frequency support? 12 MWs 60 MWs 600 MWs 30 MWs
60 MWs Feedback: Since the frequency dropped .05 Hz, and the Frequency Bias Setting of the Balancing Authority is 120 MW/.1 Hz, assuming the Frequency Response Characteristic of the Balancing Authority is very close to the Bias Setting (B), you would expect the Balancing Authority to respond with half of its Bias setting (.05 Hz is half of .1 Hz so half of the 120 MWs).
34
In your Interconnection, a generator tripped that was large enough to reduce the frequency from 60.000 Hz to 59.940 Hz. Your Balancing Authority's Frequency Bias is 200 MW/0.1 Hz. How many MW would your system initially contribute to frequency support? 200 MW 120 MW 100 MW 80 MW
120 MW Feedback: Frequency Bias (which is always a negative number) is measured in MW per tenth Hz (MW/0.1 Hz). This means that if scheduled and actual frequency are at 60.000 Hz and the frequency drops to 59.900 Hz, a Balancing Authority with a 200 MW/0.1 Hz Frequency Bias would contribute 200 MW to help arrest the frequency decline. The frequency bias obligation portion of the ACE equation is -10 * B * (FA - FS) Plugging in actual numbers gives us -10 * 200 MW/0.1 Hz * (59.94 Hz - 60 Hz) = -2000 Mw/Hz * -0.060 Hz - 120 MW Your Balancing Authority would over generate by 120 MW. This should happen naturally with the response of your generator governors and loads to the declining frequency. A shortcut to this calculation is figuring that 0.06 Hz is 60% of 0.1 Hz and 60% of 200 MW is 120 MW.
35
A 700 MW generator in a Balancing Authority area trips due to operator error. Which control system on the remaining generators would respond to the drop in system frequency resulting from the loss of generation? Differential relay systems Governor control systems Special protection systems Automatic voltage regulators
Governor control systems Feedback: NERC Standard BAL 003 states, "Each Balancing Authority shall establish and maintain a Frequency Bias Setting that is as close as practical to, or greater than, the Balancing Authority's Frequency Response." Further, the Glossary of Terms used in the Reliability Standards defines frequency response as "The sum of the change in demand, plus the change in generation, divided by the change in frequency, expressed in MW per 0.1 Hertz (MW/0.1 Hz). The loss of generation on an Interconnection results in a corresponding decrease in frequency. The first control systems to respond to a frequency disturbance are the generator governor control systems. Declining frequency causes the governor controls to open valves to increase input to the prime mover, increasing the torque angle and MW output of the generator. NERC Standard BAL-003
36
A Balancing Authority is performing Overlap Regulation Service for another Balancing Authority. Which of the following statements applies to the Balancing Authority providing this service? The Balancing Authority shall not adjust its Frequency Bias Setting, but instead import the other Balancing Authorities ACE reading. The Balancing Authority shall use the larger of the two Frequency Bias Settings in its ACE equation. The Balancing Authority's Frequency Bias Setting shall be modified to reflect the combined Frequency Bias Setting of both Balancing Areas. The Balancing Authority shall use the average of the two Frequency Bias Settings in its ACE equation.
The Balancing Authority's Frequency Bias Setting shall be modified to reflect the combined Frequency Bias Setting of both Balancing Areas. Feedback: BAL-003 requires each Balancing Authority performing Overlap Regulation Service to modify its Frequency Bias Setting to represent the Frequency Bias Setting for the combined Balancing Authority Area. This combined setting should be equivalent to either the sum of the Balancing Area's Frequency Bias Settings, or the single Frequency Bias Setting for the combined area as determined through the yearly NERC process for assigning and implementing Frequency Bias Settings
37
To achieve sufficient Frequency Response, the Frequency Response Measure (FRM) of a Balancing Authority or Frequency Response Sharing group must be: Equal to or more negative than the Frequency Response Obligation (FRO) Tested annually Reported annually Approved by NERC
Equal to or more negative than the Frequency Response Obligation (FRO) Feedback: BAL-003 requires the annual FRM for a Balancing Authority or FRSG be equal to or more negative than its FRO.
38
What happens to ACE after a sudden loss of generation in an external balancing area if the Frequency Bias Setting is less negative than the Frequency Response of the Balancing Authority? This will not affect ACE. ACE will be a negative value and AGC will increase generation. ACE will be zero and AGC will not act. ACE will be a positive value and AGC will lower generation.
ACE will be a positive value and AGC will lower generation. Feedback: If a Balancing Authority establishes a frequency bias setting less than its frequency response characteristic, the Balancing Authority ACE value will become positive if frequency falls below 60 Hz due to events outside the balancing area. In response to the positive ACE value, the AGC will reduce the output of generators under its control. This is not the appropriate response to a reduction in Interconnection frequency caused by a loss of generation in an external balancing area, since pulsing the units of the Balancing Authority LOWER in response to a LOSS of generation and only aggravate the frequency decline. This example highlights the importance of setting the Frequency Bias Setting equal to, or greater than, the Balancing Authority's Frequency Response.
39
If the frequency bias setting is a more negative value than the frequency response of a Balancing Authority and a frequency decline is caused by a sudden loss of generation in an external balancing area, what is the result? ACE will be a positive value and AGC will lower generation. ACE will be zero and will take no AGC action. ACE will be a negative value and AGC will increase generation. This will not affect ACE.
ACE will be a negative value and AGC will increase generation. Feedback: If a Balancing Authority establishes a frequency bias setting less than its frequency response, when the frequency drops its ACE becomes positive. In response to the positive AGC value, the AGC reduces the output of generators under its control. This response is not appropriate to a reduction in frequency caused by a loss of generation in an external balancing area. Therefore, it will take longer to restore frequency back to schedule on the Interconnection. In this example, the Balancing Authority's Frequency Bias Setting is set higher than its Frequency response characteristic (which is allowable) and results in ACE being negative after the external disturbance and the Balancing Authority's generation on AGC picks up and provides more support to the Interconnection than just its natural frequency response. the result, it will take longer to restore frequency back to schedule on the Interconnection.
40
What service is a method of providing regulation in which the providing Balancing Authority incorporates all other Balancing Authorities tie lines, frequency response, and schedules into its own AGC/ACE equation? Supplemental regulation service Interconnection regulation service Overlap regulation service Unilateral regulation service
Overlap regulation service
41
Which of the following is used to calculate a Balancing Authority's yearly Frequency Response Obligation (FRO)? The Balancing Authority's percentage of the Interconnection's generation and load. The change in the Balancing Authority's Net Interchange Actual for a frequency deviation. The Balancing Authority's average Frequency Bias Setting for the year. The Balancing Authority's average ACE and its L10 value.
The Balancing Authority's percentage of the Interconnection's generation and load. Feedback: BAL 003 requires that a Balancing Authority meets its obligation to respond to frequency deviations caused by disturbances in the Interconnection. This obligation is called Frequency Response Obligation (FRO) and is calculated each year based on a Balancing Authority's percentage of the annual generation and load in the Interconnection to which it belongs.
42
How is the Frequency Response Obligation (FRO) of a Frequency Response Sharing Group determined? Taking the median Frequency Response Measure of the previous year. Averaging the members' FRO Adding individual FRO of each member Adding the member's Frequency Response Measures from the previous year.
Adding individual FRO of each member Feedback: NERC allows Balancing Authorities to form Frequency Response Sharing Groups (FRSGs) with other Balancing Authorities to jointly meet their FROs. These FRGs determine their joint FRO by adding up the member's individual FROs
43
What is the purpose of generator droop settings? It allows generators to respond to frequency excursions in parallel It allows generators to respond to frequency events in proportion to their size It prevents generators from competing with each other when a frequency excursion occurs All answers are correct
All answers are correct Feedback: EPRI Power System Tutorial
44
Balancing Authority A is currently reading a system frequency of 59.95 Hz. Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's frequency bias setting is 100 MW/0.1 Hz, its AGC is pulsing its generators to do what? Stay at the current MW output level Increase MW output Decrease MW output Increase excitation on the field windings
Increase MW output Feedback: Each Balancing Authority shall establish and maintain a Frequency Bias Setting that is close as practical to, or greater than, the Balancing Authority's Frequency Response. Each Balancing Authority shall operate its Automatic Generation Control (AGC) on Tie Line Frequency Bias, unless such operation is adverse to system or Interconnection reliability. It can be determined that because Net Interchange deviation is negative, and because frequency is less than 60 Hz, Balancing Authority A's AGC will be pulsing its generators to increase generator output. This could be in response to circumstances such as a disturbance within the Balancing Area of poor control and the resulting negative ACE value. Any time Interchange Actual is less that Interchange Schedule the remainder is a negative number, and the Interconnection frequency is below scheduled frequency which means that the frequency bias portion of the ACE equation contributes to an even more negative ACE. When ACE is negative Automatic Generation Control (AGC) will be pulsing the Generator governors to increase megawatt output. NERC Standard BAL-003
45
Two generators, A and B, have the same droop setting of 5 %. Generator A is twice the capacity of Generator B. If Generator A responds to a frequency drop with 20 MW, what will Generator B's response be to the same frequency Drop? 10 MW 40 MW 30 MW 20 MW
10 MW
46
What is the primary purpose of governor dead band? It prevents governors from operating when slight variations occur in the system's frequency. It helps arrest and stabilize the frequency decay. It helps increase generation when there is an actual Net Interchange flowing out of their system. It prevents governors from operating during emergency conditions.
It prevents governors from operating when slight variations occur in the system's frequency. Feedback: The governor dead band prevents governors from operating when slight variations occur in the system's frequency which would result in unnecessary equipment wear, such as control valves and linkages.
47
A 500 MW generator in your Balancing Area has a droop setting of 5%. It is currently operating at 300 MWs. If frequency of the Interconnection dropped to 59.94, what is the resulting MW output of the generator? 310 MWs 400 MWs 325 MWs 290 MWs
310 MWs Feedback: A 5% droop means the generator will respond with its full capacity range for a 5% change in frequency (.05 x 60 Hz = 3 Hz). In this example, the frequency dropped by .06 Hz, so we use the following ratio: (500 MW/3 Hz) = (? MW/.06 Hz). If we cross multiply we get 3(?) = .06(500 MW) and solving for? we get 10 MW of change on the unit. Since we know frequency dropped, the unit responded by increasing generation by 10 MWs resulting in output of 310 MWs.
48
A generator with a droop setting of 4% means it will respond with its full capacity range for a frequency change of how much? 3 Hz 1.6 Hz 4 Hz 2.4 Hz
2.4 Hz Feedback: A 4% droop setting means that for a 4% change in frequency, the unit will respond with 100% of its capacity. 4% of 60 Hz is 2.4%.
49
Which definition best describes governor dead band? A mechanism that adjusts the mechanical power input of a steam generator by opening or closing the generator steam values. Generators respond to frequency deviation in proportion to their size. The amount of frequency change that occurs before the governor starts to respond. A generation change that is inverse to the frequency change due to turbine governor action.
The amount of frequency change that occurs before the governor starts to respond. Feedback: Generators respond to frequency deviation inversely or opposite of the frequency deviation. If frequency is low, a generator responds in proportion to their size by increasing output and vice versa. The governor dead band is in place to ensure generators are not continuously responding or chasing frequency.
50
A 500 MW generator trips in a Balancing Authority outside your Balancing Authority Area. Which of the following responses would you expect to see in your area? Reduced Net Actual Interchange Reduced net generation on your system. Frequency above 60 Hz. Net Actual Interchange greater than Scheduled Interchange.
Net Actual Interchange greater than Scheduled Interchange. Feedback: When a loss of generation occurs, Interconnection frequency decreases. Turbine governor respond to a frequency deviation and increase the output of their generators in proportion to their size and the amount of frequency deviation. The frequency bias portion of the ACE equation allows the generators in your Balancing Area to increase MW output without AGC trying to lower them at the same time. The result is a positive Net Actual Interchange deviation for your Balancing Authority. If ACE is zero while Interchange actual is greater than Interchange schedule during this disturbance your Balancing Authority's frequency bias is equal to your frequency response.
51
Turbine governors arrest Frequency deviations. Of the following, which control system compares and brings Net Actual Interchange back in line or as close to Net Scheduled Interchange as possible? Flat Frequency Control Automatic Generation Control Load Response Automatic Voltage Regulation
Automatic Generation Control Feedback: The Balancing Authority's AGC shall compare total Net Actual Interchange to total Net Scheduled Interchange plus Frequency Bias obligation to determine the Balancing Authority's ACE. Single Balancing Authorities operating asynchronously may employ alternative ACE calculations such as (but not limited to) flat Frequency Control. If a Balancing Authority is unable to calculate ACE for more than 30 minutes, it shall notify its Reliability Coordinator. Governor action is not intended to keep the system at 60 Hz. Governors arrest frequency deviations, but AGC maintains system frequency to a schedule by pulsing the generator governors to either increase or decrease MW production depending on the need. When AGC pulses the generator governor to increase megawatts on a fossil steam generator, it causes the steam regulating valves to open more, allowing more steam across the generator turbine blades. This action should increase the mechanical energy on the turbine which is then converted to electrical energy. NERC Standard BAL-005
52
Automatic Generation Control uses the ACE equation to ________. Minimize Inadvertent Interchange among Balancing Authority areas Provide frequency support for the Interconnection Both answers are correct Neither answer is correct
Both answers are correct Feedback: Automatic Generation Control uses the ACE equation to minimize the Inadvertent Interchange among Balancing Authority areas and provide frequency support for the Interconnection.
53
Interconnection frequency is 59.80 Hz. Your ACE is a large negative value and your AGC is pulsing your units down. What should you do? Place AGC in constant frequency control Leave AGC in operation but investigate Place AGC in Flat Tie Line Control Suspend AGC and investigate
Suspend AGC and investigate Feedback: "The Balancing Authority shall operate AGC continuously unless such operation adversely impacts the reliability of the Interconnection. If AGC has become inoperative, the Balancing Authority shall use manual control to adjust generation to maintain the Net Scheduled Interchange." In the scenario given, the AGC clearly is inoperative and since the frequency has dramatically declined to 59.80 Hz, is adversely impacting the reliability of the Interconnection. The negative ACE value is not unexpected; however, AGC should be pulsing units up instead of down. Therefore, suspending AGC and going to manual control to adjust generation is the recommended course of action.
54
Automatic Generation Control automatically and ________ adjusts a Balancing Authority's generation in response to changes in the Balancing Authority's ACE. Positively Precisely Economically Correctly
Economically Feedback: Automatic Generation Control automatically, with an economic component, adjusts a Balancing Authority's generation in response to change in its ACE.
55
Which part of the ACE equation reflects Dynamic Schedules? Dynamic Schedules are not included in the ACE equation. Actual Net Interchange Component, NIA Frequency component (FA-FS) Scheduled Net Interchange component, NIS
Scheduled Net Interchange component, NIS Feedback: Dynamic schedules are reflected in the NIS, or Scheduled Interchange component of the ACE equation.
56
Which part of the ACE equation reflects Pseudo-Ties values? Pseudo-Ties are not included in the ACE equation. Actual Net Interchange component, NIA Frequency component, FA - FS Scheduled Net Interchange component, NIS
Actual Net Interchange component, NIA Feedback: Pseudo-ties are reflected in NIA, or Actual Interchange component of the ACE equation.
57
Several AGC modes are available to most Balancing Authorities. A Balancing Authority operating asynchronously, or separated from the Interconnection, should switch its AGC mode to ______. Flat Frequency Control Manual Control Flat Tie Line Control Tie Line Bias Control
Flat Frequency Control Feedback: The Balancing Authority's AGC shall compare total Net Actual Interchange to total Net Scheduled Interchange plus Frequency Bias obligation to determine the Balancing Authority's ACE. Single Balancing Authorities operating asynchronously may employ alternate ACE calculations such as (but not limited to) flat frequency control. If a Balancing Authority is unable to calculate ACE for more than 30 minutes it shall notify its Reliability Coordinator. Normally, the Tie Line Bias control mode, which compares the Net Actual Interchange to the Net Scheduled Interchange plus the Balancing Authority's frequency bias obligation, should be used. However, if a Balancing Authority is operating asynchronously, or separated from the Interconnection, it should switch to Flat Frequency Control. Because its tie lines are no longer connected to the Interconnection and it is more important for the Balancing Authority to maintain 60 Hz. In the Flat Frequency control mode, ACE is looking only at the system frequency, not the Interchange portion of the ACE equation. Alternatively, the separated Balancing Authority could choose to continue operating in Tie Line Bias Control mode but with all Interchange schedules set to zero. This decision is equivalent to operating in Flat Frequency mode.
58
A Balancing Authority's frequency indication has become erratic and unreliable. Which AGC mode should the Balancing Authority operate in? Flat Frequency Control Tie Line Bias Control Flat Tie Line Control Manual Control
Flat Tie Line Control Feedback: If the Balancing Authority is unable to switch to a reliable frequency indication, Flat Tie Line control mode should be used for AGC. The Balancing Authority should immediately initiate maintenance activity to repair the frequency indication so AGC can be returned to Tie-Line Bias mode as soon as possible.
59
If AGC has become inoperative, what type of control shall be used to adjust generation to maintain scheduled Interchange? Base Control Interchange Control Schedule Control Manual Control
Manual Control Feedback: The NERC Standard states, "The Balancing Authority shall operate AGC continuously unless such operation adversely impacts the reliability of the Interconnection. If AGC has become inoperative, the Balancing Authority shall use manual control to adjust generation to maintain the Net Scheduled Interchange? NERC Standard BAL 005
60
What is the minimum accuracy of frequency metering equipment used for calculating Reporting ACE? 0.001 Hz 0.01 Hz 0.095 Hz 0.009 Hz
0.001 Hz Feedback: BAL-005, R3: Each Balancing Authority shall use frequency metering equipment for the calculation of Reporting ACE: 3.1 that is available a minimum of 99.95% for each calendar year; and 3.2 with a minimum accuracy of 0.001 Hz.
61
What is the availability requirement per calendar year for frequency metering used for calculating Reportable ACE? .995% 99.00% 99.95% 99.50%
99.95% Feedback: BAL-005, R3: Each Balancing Authority shall use frequency metering equipment for the calculation of Reporting ACE: 3.1 that is available a minimum of 99.95% for each calendar year; and 3.2 with a minimum accuracy of 0.001 Hz.
62
A Balancing Authority's EMS has failed and been unable to calculate ACE for 2 hours. This is he 5th time since the first of the year. NERC Standard BAL-005 requires the system for calculating Reporting ACE be available for what percentage of a calendar year? 99.95% 95% 100% 99.5%
99.5% Feedback: BAL-005, R5: Each Balancing Authority’s system used to calculate Reporting ACE shall be available a minimum of 99.5% of each calendar year.
63
A Balancing Authority has lost the ability to calculate Reporting ACE starting at 13:15. At 13:45, capability has not been restored. The Balancing Authority must notify the Reliability Coordinator before what time? No notification is required 14:00 14:45 14:15
14:00 Feedback: BAL-005, R2: A Balancing Authority that is unable to calculate Reporting ACE for more than 30 consecutive minutes shall notify its Reliability Coordinator within 45 minutes of the beginning of the inability to calculate Reporting ACE.
64
Which of the following is required to ensure Balancing Authority operators are aware of errors associated with data used for calculating Reporting ACE, and how to mitigate those errors? Monthly training on identifying and mitigating errors An Operating Process for identifying and mitigating errors A backup Reporting ACE calculation using data from an independent source A separate, independent alarm system for ACE data errors
An Operating Process for identifying and mitigating errors Feedback: BAL-005, R6: Each Balancing Authority that is within a multiple Balancing Authority Interconnection shall implement an Operating Process to identify and mitigate errors affecting the accuracy of scan rate data used in the calculation of Reporting ACE for each Balancing Authority Area.
65
A Balancing Authority has discovered one tie line meter reading is off by 30 MW, causing the ACE values to be incorrect. What should be done to temporarily adjust for the error until the meter can be calibrated or repaired? Use the IME portion of the equation to adjust for the meter error Change the Frequency Bias part of the ACE equation to reflect the error Take the numbers from the incorrect tie line and insert them into the NIS portion of the ACE equation Change the AGC mode to Flat Frequency Control
Use the IME portion of the equation to adjust for the meter error
66
In an Interconnection, which of the following is required to be in the metered boundaries of a Balancing Authority Area? All are required to be within the metered boundaries of a Balancing Authority. Load Generation Transmission
All are required to be within the metered boundaries of a Balancing Authority. Load Feedback: All generation, transmission, and load operating within an Interconnection must be included within the metered boundaries of a Balancing Authority Area. NERC Standard BAL-005
67
What service is a method of providing regulation in which the providing Balancing Authority incorporates all other Balancing Authorities tie lines, frequency response, and schedules into its own AGC/ACE equation? Supplemental regulation service Overlap regulation service Interconnection regulation service Unilateral regulation service
Overlap regulation service Feedback: Overlap regulation service is a method of providing regulation service in which the Balancing Authority providing the regulation service, incorporates all other Balancing Authority's tie lines, frequency response, and schedules into its own AGC/ACE equation.
68
A Balancing Authority has one of its tie-line meters out of service for maintenance. Which of the following actions would be appropriate for operating the area on Automatic Generation Control? Switch AGC to Flat Frequency mode Operate AGC in manual and adjust generation as necessary Use the Meter Error part of the ACE equation and remain in Tie-Line Bias mode Switch AGC to Flat Tie-Line mode
Use the Meter Error part of the ACE equation and remain in Tie-Line Bias mode Feedback: In this case meter error is not the issue, but with the meter out of service, the flow on that tie-line is not being included in the Actual Net Interchange portion of the ACE equation. The tie line flow can be determined by calling the adjacent BA periodically to get updates, or by using State Estimator and the value can be entered by the operator in the Meter Error term of ACE. It is better to operate in tie-line bias if at all possible and manually update the tie line information.
69
Which of the following terms of the ACE equation is not affected by frequency? NIA FA B All terms are affected
B Feedback: NIA is affected due to generators responding to frequency through governor response anytime frequency is outside the governor dead band.
70
The reporting ACE calculation requires data received from the field devices, such as frequency and Tie Line readings. What is the minimum scan rate for attaining this data? 6 seconds 3 seconds 10 seconds 1 second
6 seconds Feedback: BAL-005, R1: The Balancing Authority shall use a design scan rate of no more than six seconds in acquiring data necessary to calculate Reporting ACE.
71
Interchange Schedules are only between adjacent Balancing Authorities, with the exception of Dynamic Schedules. True or False? True False
True Feedback: While Interchange Transactions can be between any two Balancing Authorities, Interchange Schedules are only between adjacent Balancing Authorities. The exception to this is if two non-adjacent Balancing Authorities have a Dynamic Schedule representing jointly owned generation or load.
72
Which of the following must Balancing Authorities evaluate to determine if the Arranged Interchange should be confirmed? Select all that apply. Generator Ramping Capability Price Energy Magnitude System Operating Limits Load Forecast
Generator Ramping Capability Energy Magnitude
73
The timing requirement to assess Interchange will vary depending on which factor? Time of day Who has approved the Arranged Interchange When the E-tag is submitted When the ramp starts
When the ramp starts
74
What condition must be met prior to an Arranged Interchange transitioning to an Implemented status? Sink Balancing Authority must confirm the transaction status is Confirmed. Transaction that are denied have a reason. Energy delivered must be paid for The Reliability Coordinator provides its approval
Sink Balancing Authority must confirm the transaction status is Confirmed.
75
Which of the following best describes Available Transfer Capability (ATC)? The amount of transfer capability in the transmission network remaining for further commercial activity over and above already committed uses The difference between the scheduled and actual power flow on a path The difference between how much power flow a transmission path can handle and the actual flow on the path The amount of power flow capacity available on a path before it exceeds its SOL
The amount of transfer capability in the transmission network remaining for further commercial activity over and above already committed uses
76
An SOL has been exceeded due to excessive Interchange power flows. What must be done to return facility to within normal limits? The Transmission Operator must open the overloaded line The Reliability Coordinator will not get involved in Interchange even when SOL exceedances occur The Reliability Coordinator may need to modify or curtail Interchange Transactions impacting the overloaded facility Generation must be re-dispatched within the Balancing Authority
The Reliability Coordinator may need to modify or curtail Interchange Transactions impacting the overloaded facility Feedback: Since the overload is due to excessive interchange power flows, re-dispatching generation internally may not help the overloaded facility. The Interchange Transactions affecting the SOL must be reduced and will be initiated by the Reliability Coordinator.
77
Which of the following entities is responsible for approving or denying an Arranged Interchange? Purchasing-Selling Entity Reliability Coordinator Transmission Operator Balancing Authority
Balancing Authority Feedback: Balancing Authorities and Transmission Service Providers are responsible for evaluating and approving interchange transactions. Reliability Coordinators do not approve transactions, but are aware of all transactions affecting their reliability area. They will curtail transactions when necessary for reliability issues. Transmission Operators are not involved in the tagging process at all.
78
What is the purpose of conducting a reliability assessment for an Arranged Interchange? Determine the economic benefit Determine the capability of supporting the magnitude of the Interchange Ensure contingency reserves are met Ensure Tag is submitted
Determine the capability of supporting the magnitude of the Interchange
79
Which of the following are the two Balancing Authorities that commit to moving generation to support a transaction? Sending and receiving Balancing Authorities Source Balancing Authority and Sink Balancing Authority Intermediate and Inbetween Balancing Authority Wheeling and passthrough Balancing Authority
Source Balancing Authority and Sink Balancing Authority
80
If any entity involved in a transaction does not actively deny the Arranged Interchange within the required timeframe, the Interchange is transitioned to which status? Denied status Pending status Ramping status Confirmed status
Confirmed status
81
The communication and coordination of the Interchange process is carried out by the Interchange Authority. The Interchange Authority is best described as which of the following? Interconnection Distribution Calculator A computer software program of Electronic Tagging Energy Management System Generation Control of Actual Interchange
A computer software program of Electronic Tagging
82
What condition must be met prior to an Arranged Interchange transitioning to an Implemented status? Sink Balancing Authority must ensure the transaction status is Confirmed. Energy delivered must be paid for Transaction that are denied have a reason. The Reliability Coordinator provides its approval
Sink Balancing Authority must ensure the transaction status is Confirmed.
83
When an Interchange Transaction is approved, the full amount will travel on the reserved path per the E-tag. True False
False Feedback: Power flow follows paths of least impedance. Usually, the largest percentage of the total transaction will flow on the scheduled path. But most transactions will result in unscheduled flow on other paths, sometimes causing congestion. The amount of flow on a path resulting from a transaction is called the Power Transfer Distribution Factor, or PTDF.
84
When a transaction is approved and becomes Confirmed Interchange, which entities must be notified? All involved Balancing Authorities, Transmission Service Providers, Purchasing Selling Entities, and affected Reliability Coordinators Only the Source and Sink Balancing Authorities and the Reliability Coordinator All involved Balancing Authorities, Transmission Operators, and Purchasing Selling Entities All Balancing Authorities, Transmission Service Providers, Purchasing Selling Entities in the Interconnection
All involved Balancing Authorities, Transmission Service Providers, Purchasing Selling Entities, and affected Reliability Coordinators
85
What is the definition of Confirmed Interchange? The state where no party has denied, and all required parties have approved the Arranged Interchange The state where no party has denied, and the Transmission Operator approves the Arranged Interchange The state where no party has denied, and the Balancing Authority approves the Arranged interchange Interchange that has been approved by the Reliability Coordinator
The state where no party has denied, and all required parties have approved the Arranged Interchange Feedback: Confirmed Interchange - The state where no party has denied, and all required parties have approved the Arranged Interchange.
86
What is Composite Confirmed Interchange? The summation of Interchange waiting to be approved The energy profile (including non-default ramp) throughout a given time period, based on the aggregate of all Confirmed Interchange occurring in that time period Interchange which was not approved within the required time limits Arranged Interchange agreed to between the Source and Sink Balancing Authorities
The energy profile (including non-default ramp) throughout a given time period, based on the aggregate of all Confirmed Interchange occurring in that time period
87
Why is it important to have a coordinated Implementation of Interchange? To ensure Source and Sink Balancing Authorities have identical Composite Confirmed Interchange to Implement To provide implementation requirements for Transmission Operators with High-Voltage Direct Current ties To ensure Balancing Authorities implement the Interchange as agreed upon in the Interchange confirmation process. To provide the steps necessary to implement Confirmed Interchange
To ensure Balancing Authorities implement the Interchange as agreed upon in the Interchange confirmation process. Feedback: "Purpose: To ensure that Balancing Authorities implement the Interchange as agreed upon in the Interchange confirmation process."
88
Before implementing Confirmed Interchange, Adjacent Balancing Authorities shall agree on Composite Confirmed Interchange between them ensuring it is: Select all that apply. Identical in magnitude Within 10% magnitude of each other Opposite in sign Equal in sign
Identical in magnitude Opposite in sign
89
Four Balancing Authorities are involved in an Interchange Transaction. Balancing Authority D is the Sink and Balancing Authority A is the Source. BA-B and BA-C are Intermediate Balancing Authorities. BA-B must agree on the Composite Confirmed Interchange with whom? Sink BA-D only Source BA- A only All Balancing Authorities in the Transaction Adjacent Balancing Authorities BA-A and BA- C
Adjacent Balancing Authorities BA-A and BA- C
90
Attaining and Native Balancing Authorities must account for Pseudo-Ties using a dynamic value from an agreed upon common source. Where should they account for this value? In the Actual Frequency term In the Scheduled Net Interchange term of their respective ACE equations In the Frequency Bias Setting In the Actual Net Interchange term of their respective ACE equations
In the Actual Net Interchange term of their respective ACE equations
91
What is the role of the Reliability Coordinator in the scheduling or modification of Interchange for actual or anticipated reliability-related reasons? Submit the Request for Interchange or Reliability Adjustment Arranged Interchange as necessary. Direct the scheduling or modification of Confirmed or Implemented Interchange. Request an approval or denial for Request for Interchange. Approve the Composite Confirmed Interchange requests.
Direct the scheduling or modification of Confirmed or Implemented Interchange.
92
The Attaining Balancing Authority with a generator located in another Balancing Authority area implements a Dynamic Schedule to account for the generation produced. How is the generation produced in the other Balancing Authority area accounted for in real-time? E-tag is implemented that varies with the generation output Sink Balancing Authority only enters into ACE After the fact Energy Accounting Dynamic Schedule in NIs for each Balancing Authority
Dynamic Schedule in NIs for each Balancing Authority
93
What is the final step in the Interchange process after the appropriate assessment of the Interchange Transaction? Select all that apply. Notify the Reliability Coordinator Implement the transaction into the involved Balancing Authorities' ACE equation Coordinate with the Transmission Operator if an HVDC is involved in path Notify the Purchasing Selling Entity
Implement the transaction into the involved Balancing Authorities' ACE equation Coordinate with the Transmission Operator if an HVDC is involved in path
94
Transmission line relays and transformer differential relays have current flowing into them that is proportional to the current in the primary circuit. In most cases, what device is used to transform the current from the primary circuit to a smaller proportional amount that flows into the protective relay? Vacuum interrupters Positive sequence instruments Current transformers Series capacitors
Current transformers
95
When a high voltage transmission line circuit breaker trips open as a result of a fault, a synchronous check relay will monitor certain values on both the line side and the bus side of the open circuit breaker. Before the synchronous check relay re-closes the open circuit breaker, which of the following values has to be within a certain limit before the circuit breaker will close automatically? Frequency Voltage magnitudes Phase Angle between the voltages All of the above
All of the above Feedback: The synchronizing relay protects the open circuit breaker from closing when two areas of the power system have large differing values. For example, if the line was closed into a substation bus that had different phase angles or huge voltage differences, large amounts of current and reactive power would flow from one part of the system to another. This can cause high voltage swings, bumping or shaking and possibly knock generators off line and damage equipment.
96
As a result of high MW flows, a transmission line sags significantly and current flashes over to a tree growing directly below it. This causes the protective relays to take the transmission line out of service. How would you classify this type of fault? Positive sequence fault Ground fault Overvoltage fault Differential fault
Ground fault Feedback: The most common fault on the transmission system is the line to ground fault. This means that the current on the transmission line has found a path to ground, causing a short circuit on the system. That means that the current on the transmission line has found a path to ground, causing a short circuit on the system. There are many causes of ground faults; blown insulators, animals around the equipment, lightning, and vegetation such as trees and even smoke from a forest fire.
97
An isolating 138 kV disconnect switch is mistakenly opened when it still has load current flowing through it. The resulting arc that forms between the disconnect's arm and its receiver eventually jumps to the steel support structures, creating a ground fault. The circuit breaker and relays that should have detected and immediately isolated this fault fail. As a result, the fault stays on the system 15 cycles. How does this mis-operation affect system voltage? System voltage goes up because more megawatts are flowing from the system to neutral. System voltage will not be affected, only current. System voltage decreases due to the fault. System voltage stays the same; this type of fault will not affect system voltage.
System voltage decreases due to the fault. Feedback: The arc was initiated due to the current flow through the disconnect as the disconnect arm separated from the receiver. If the fault is not interrupted quickly, the high current flow will cause the system voltage to dip to dangerously low levels. These resulting low voltages will cause motors to draw more current, lights to dim, and if there are not enough reactive reserves available to stabilize voltage, a blackout could occur.
98
Protective relays used on transmission and distribution systems are designed to... protect power marketers from losing money by letting them know when a problem arises on the system. minimize damage and isolate problems on the system. Keep all generators on line no matter what the circumstances keep all lines in service no matter what happens on the system.
minimize damage and isolate problems on the system. Feedback: Protective Relays are designed to detect a fault and isolate the equipment by opening or tripping a device such as a circuit breaker. Basically, minimizing damage and isolating problems.
99
A car hits a power pole on a 13kV circuit, causing its A and B phases to wrap around each other. The relay at the substation fails to trip the 13 kV circuit breaker feeding the troubled line. Instead, a 51 relay senses the fault and trips the 138/13 kV transformer feeding the 13 kV system to protect it from damage. What type of relay is the 51 relay? Timed Overcurrent relay Differential relay Ground relay Phase Comparison relay
Timed Overcurrent relay Feedback: High voltage transformers are normally protected by differential relays for problems occurring to the transformer itself. However, a differential relay would not operate as the result of high current flow passing through the transformer feeding a fault on the distribution system. To protect the transformer from high fault current, overcurrent relays are installed to take the transformer off line should a lingering high current fault occur as the result of a distribution circuit breaker not opening when it should.
100
Transmission Operators frequently use distance relays to protect their transmission lines. These distance relay schemes quite often use _____ zones of protection. five three eight one
three Feedback: Distance relay schemes usually use three zones of protection. Zone 1 usually covers 80 to 90% of the line section and trips instantaneously at high speed. Zone 2 covers the entire length of the line, plus 20 to 50% into the other lines feeding off the same bus. Zone 2 will have a time delay of about 25 cycles and basically serves as a backup to zone 1. Zone 3 covers the entire length of the protected line, plus a 50% into the lines feeding off the same bus. Zone 3 has an even longer trip delay of anywhere from 60 cycles to 90 cycles depending on the company. protective relay strategy. It primarily serves as a backup to Zone 1 and Zone 2.
101
A bus is protected by a bus differential scheme. 500 amps enters the bus, and 400 amps leaves the bus. Is there a fault on this bus and will the bus differential scheme operate? There is a fault on the bus, and the bus differential scheme will operate There is no fault on the bus, so the bus differential scheme will not operate There is a fault on the bus, but the bus differential scheme will not operate There is not a fault on the bus, but this case the bus differential scheme will operate
There is a fault on the bus, and the bus differential scheme will operate Feedback: When the current leaving the bus differential scheme is not equivalent to the current entering it, a fault condition exists. This also means that the bus differential scheme will operate to open the circuit breaker. This means the answer that indicates 1.) there IS a fault on the bus and 2.) the buss differential scheme WILL operate, is the correct answer.
102
An entire bus at a substation was cleared instantaneously. A substation maintenance employee calls the control room to inform them the relayed target displays indicate operation of a relay 87 on its bus relay panel. What type of relay has operated? Lockout Relay Differential Relay Time Overcurrent Relay Distance Relay
Differential Relay Feedback: Relay 87 is a differential relay per IEEE Relay Standards naming convention. An entire bus cleared instantaneous is typically the result of a differential of current into and out of the bus.
103
A transformer differential zone has Circuit Breakers 624 and 634 protecting the transformer. Breaker 624 receives 1500 MVA and Breaker 634 sends 1200 MVA to the bus. Based on these conditions, determine which of the following statements is true. There is a fault in the transformer. The fault produces an extra secondary current, which flows to the operating coil of the differential relay. This fault conditions will cause all circuit breakers to open. All of the above
All of the above Feedback: Because there is more power leaving the transformer differential scheme than entering it, we can conclude there is a fault on the transformer. When a fault occurs, it produces a secondary current that operates the differential relay, which in turn opens the circuit breakers. This means the answer indicating "all of the above" is correct.
104
A relay controlling circuit breaker A detects a zone 2 fault outside its line section. Normally, under this condition, the relay is designed to trip circuit breaker A only it its zone 2 timer times out. However, in this case, circuit breaker A trips at high speed. The tripping of circuit breaker A would be classified as a ___________. normal trip safety trip control trip misoperation
misoperation Feedback: Relays are installed throughout the power grid in overlapping zones of protection to detect faults. When a fault occurs, isolation of the fault should affect the smallest amount of the power grid as possible. Therefore, each relay that detects a fault cannot and should not be the primary tripping source or huge portions of the power grid would be interrupted for a single fault. To prevent this from happening, delays are designed into relays (most of the time they are timers) allowing a relay outside the primary tripping zone to operate quickly but only if the primary relay misoperates. If the relays do not operate as designed, a misoperation has occurred.
105
Which of the following would be considered a protection system misoperation? A generator voltage regulator was left in manual rather than automatic. A relay is designed to operate a circuit breaker for a fault in 3 cycles, but did not respond at all, causing the backup overcurrent relay to operate in 25 cycles. An Interchange agreement between two Balancing Authorities was entered incorrectly causing the Interchange Schedule component of the ACE equation to be incorrect. A generator was left off AGC and did not increase MW production when AGC called for it.
A relay is designed to operate a circuit breaker for a fault in 3 cycles, but did not respond at all, causing the backup overcurrent relay to operate in 25 cycles. Feedback: A protection system misoperation is caused when protective relays do not respond to system conditions as designed. A relay misoperation causing a fault to stay on the system longer that it should, or de-energizing a line when it should not, are examples of protective system misoperations. Protection system misoperations must be evaluated to determine why they occurred and what can be done to ensure that they will not occur again.
106
What type of relays would you most likely find on each end of a 75 mile 230 kV transmission line? 49 Thermals 27 Voltage or 25 Synchronous check 87 Differentials 21 Distance or 67 Directional Overcurrent
21 Distance or 67 Directional Overcurrent Feedback: Transmission lines are usually protected by distance relays and ground overcurrent relays. Whether the relays are electromechanical, solid state, or computer type relays does not matter when it comes to the numbering for the distance relays. That number will usually be a 21 as defined by IEEE. Ground relay s, however, may be designed by different numbers. For example, if the ground relay is an older electromechanical directional ground relay, it will be a 64. If the relay is the newer computerized directional ground relay, it will be a 67. Whatever the case, transmission lines are usually protected by 21 distance and 64 or 67 directional ground or directional overcurrent relays.
107
What type of relay uses a combination of current transformer (CT) measurements and potential transformer (PT) measurements and operates when the ratio of the PT measurements to CT measurements is below a certain limit for a given period of time? Lockout relay (Device 86) Time overcurrent relay (Device 51) Distance Relay (Device 21) Differential relay (Device 87)
Distance Relay (Device 21) Feedback: A distance relay (Device 21) uses a combination of current transformer (CT) measurements and potential transformer (PT) measurements and operates when the ratio of the PT measurements to CT measurements is below a certain limit for a given period of time.
108
A storm blows the A phase and B phase conductors of a 138 kV transmission line together, creating a phase-to-phase fault. The magnitude of the current and voltage on the line immediately change, causing the distance relays at each end of the line to operate. How did the current and voltage on the line change causing the relay to indicate a fault? The voltage increased and current increased. The voltage decreased and current decreased. The voltage decreased and current increased. The voltage increased and current decreased.
The voltage decreased and current increased. Feedback: When a fault occurs on the power grid, the voltage decreases and the current increases resulting in a decrease in the impedance in the vicinity of the fault. the change in voltage and current is the input causing the distance relay to respond.
109
Communication signals are sometimes used to control how relays respond to system conditions. True False
True Feedback: Relays can detect faults that occur in other line sections. due to the overlapping zones of protection. To prevent relays from operating out of sequence or too rapidly, communication signals are transmitted from one relay to another controlling how the relays will respond.
110
A protective relay may send transfer trip signals to a remote location in order to trip a circuit via a communication channel. Transfer trip signals may either trip a circuit breaker directly or initiate operation of an auxiliary tripping relay. The use of transfer trip signals, however, is limited because they can only be sent via a power line carrier. True False
False Feedback: Transfer trip signals are a form of pilot relaying. Pilot relay signals can be sent over various types of communication channels. Examples of communication channels are pilot wires, power-line carrier, satellite, fiber optics, microwave, and even telephone lines.
111
A Generator Operator shall coordinate installation of all new protective systems and changes to existing protective system with its ______________. Transmission Operator and Host Balancing Authority Host Load Serving Entity Reliability Coordinator None of the above
Transmission Operator and Host Balancing Authority Feedback: Each Generator Operator shall coordinate all new protective systems and all protective system changes with its Transmission Operator and Host Balancing Authority.
112
A Transmission Operator has a Special Protection System in its area that has operated. Which entities must be notified? Affected Transmission Operators and Balancing Authorities Affected Balancing Authorities and Load Serving Entities Affected Load Serving Entities and Transmission Operators None of the above
Affected Transmission Operators and Balancing Authorities Feedback: Each Transmission Operator and Balancing Authority shall monitor the status of each Special Protection System in their area and shall notify affected Transmission Operators and Balancing Authorities of each change in status.
113
Which of the following situations would require an analysis and corrective action plan be submitted to the local Regional Reliability Organization (RRO)? A 161/69/13 kV transformer was de-energized due to a transformer differential relay operation at exactly the same time that a 161 kV line ground fault occurred on one of the 161 kV lines that feed from the station's 161 kV bus. A transformer differential that resulted from a lightning arrestor being destroyed by a lightning strike. A line fault that was interrupted using circuit breakers on each of the line within 3 cycles. A tree falls across a 13 kV distribution circuit causing the distribution 13 kV circuit breaker back at the substation to operate on a residual ground and overcurrent relay operation.
A 161/69/13 kV transformer was de-energized due to a transformer differential relay operation at exactly the same time that a 161 kV line ground fault occurred on one of the 161 kV lines that feed from the station's 161 kV bus. Feedback: A line fault should not affect the transformer differential relay. If a ground fault occurred on one of the 161KV lines that feed out of the station a couple of things could have happened to cause the transformer differential relay to operate at the same time. Saturated CT's or Zero sequence current could have gotten into the current transformers unbalancing the transformer differential relay. Either one of these would require a misoperation analysis and a corrective action plan to be submitted to the RRO.
114
A Generator Operator is planning to increase the capacity of an existing 500 MW generator to support the addition of new equipment. Which entity must be notified of the changes in generation capacity? Its Transmission Operator and others that may require changes in their protection system Transmission Planning Power marketers Balancing Authority
Its Transmission Operator and others that may require changes in their protection system Feedback: Each Generator Operator shall notify the affected Transmission Operators in advance of changes in generation or operating conditions that could require changes in the Transmission Operator's protection systems.
115
A 354 kV line carrying 1250 MWs of power trips off-line. This results in a SOL and IROL violation for a 230 kV parallel line and some substation buses to be 10% below their nominal voltage. What can the transmission operator do to return the system to its established voltage limits ready, for the next contingency? Send out an appeal for voluntary reductions. Request power marketers purchase power. Use Under Load Tap Changers to increase the distribution voltage. Re-dispatch generation, request MVAR support from each generator, place all available voltage support equipment on line, and curtail load if necessary.
Re-dispatch generation, request MVAR support from each generator, place all available voltage support equipment on line, and curtail load if necessary. Feedback: The increased flow on the 230kV line has pushed it above its Surge Impedance Loading causing the line to become a consumer of reactive power. Coupled with the loss of the voltage support from the 345kV line, this results in a System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) violation. NERC requires the Transmission Operator to resolve the operating limit violation as soon as possible but no longer than 30 minutes. The Transmission Operator's first choice might be re-dispatch generation and request all Generator Operators increase their voltage support. If this works, it should prepare for the next contingency. If the transmission system is still in violation, the next choice would be to curtail load in the area.
116
Which of the following actions should a Transmission Operator consider first when trying to correct a high voltage condition during a light load period like the middle of the night? Lower generator voltage setpoints until load picks up Place available shunt capacitors in service near the load Raise generator voltage setpoints until load picks up Remove from service one of several lightly loaded parallel lines
Remove from service one of several lightly loaded parallel lines Feedback: A transmission Operator should consider removing lightly loaded lines as long as there are parallel lines. This causes the other lines to increase in load and produce less MVAR, and voltage will drop. A quick study would be performed first to ensure no other reliability issues would arise. Generators are a dynamic resource and should be considered last for adjusting voltage conditions.
117
The voltage on the power system is increasing due to an unexpected drop in customer load. Which of the following devices would a Transmission Operator bring on-line to get the voltage level back into a normalrange? Capacitors Reactors Static VAR Compensators Generators
Reactors Feedback: Most generators have the capability to absorb reactive power by under-exciting the generator rotor. Static VAR compensators are also able to absorb excessive reactive power using its reactors as needed in just a few cycles. However, generators with their AVR in service and static VAR compensators are dynamic resources and should already be in service. If voltage is spiking due to an unexpected drop in customer load, reactors, which are typically located at high voltage stations, can be brought into service as needed.
118
Low voltage in an area of the power system is usually caused by which of the following? Excessive MVARs in the area. Light loading on underground cables. Heavy power flow in and across the area. An imbalance of generation and load in that area
Heavy power flow in and across the area. Feedback: Low voltages can almost always be attributed to heavy power flows. Heavy power flows cause lines to consume MVARS due to their inductive properties and without sufficient MVAR resources, voltages drop.
119
A Transmission Operator shall coordinate its voltage schedule with adjacent Transmission Operators and provide a copy of its schedule to its Reliability Coordinator to ______________. ensure each Generator Operator produces power to meet the fluctuating power demands of the Transmission Operators it supports. ensure they do not burden adjacent Transmission Operators with excessive reactive power flow across transmission tie lines and operate within System Operating Limits and Interconnection Reliability Operating Limits. support transmission lines as close to possible as their optimal loading level. support power angles of the transmission system at optimal levels.
ensure they do not burden adjacent Transmission Operators with excessive reactive power flow across transmission tie lines and operate within System Operating Limits and Interconnection Reliability Operating Limits. Feedback: Operating within System Operating Limits and Interconnection Reliability Operating Limits by Transmission Operators is critical to reliability. Implementing a system voltage schedule and providing a copy of the schedule to its Reliability Coordinator and adjacent Transmission Operators helps ensure excessive reactive power flow does not flow across transmission tie lines.
120
The point at which the MVARs required to support the MW load on a transmission line is equivalent to MVARs supplied from its natural capacitance is called its ___________. Instantaneous Peak System Operating Limit Surge Impedance Loading Integrated Peak
Surge Impedance Loading Feedback: Transmission Operators monitor the loading or current flow on a transmission line to determine whether the transmission lines are helping maintain system voltage. A transmission line at its Surge Impedance Loading (SIL) level is producing reactive power equal to the reactive power being consumed.
121
Examples of ________ reactive resources include generators and static VAR compensators. stationary slow to respond dynamic static
dynamic Feedback: Generators and lightly loaded transmission lines are examples of dynamic reactive resources. These reactive resources are considered dynamic due to their ability to provide or absorb varying amounts of VARs based on the needs of the system. Static VAR Compensators, or SVCs, are also a dynamic reactive resource. The word static in the name refers to the fact that they have no moving parts as compared to generators and synchronous condensers which are rotating machines.
122
It is the responsibility of the Transmission Operator to acquire sufficient ____________ within its area to protect the voltage levels under normal and contingency conditions. reactive resources field personnel operating reserves None of the choices provided are correct.
reactive resources Feedback: Based on its assessment of the system, each Transmission Operator shall have evidence of scheduling sufficient reactive resources within its area to protect the voltage levels under normal and contingency conditions. Transmission Operators can provide sufficient reactive resources through various means including, but not limited to, reactive generation scheduling, transmission line and reactive resource switching, and controllable load use.
123
Positioning capacitor banks close to the inductive load of a transmission system helps to ______________. increase the reactive power required by the inductive load keep real power at a consistent level as it travels from the generator to the load ensure reactive power flows opposite real power reduce reactive power flow and losses between the generator and the inductive load
reduce reactive power flow and losses between the generator and the inductive load Feedback: Since it is difficult to transmit reactive power over long distances, it is better to have reactive power reserves close to the load, where it is most needed.
124
Which of the following is an action a Transmission Operator would perform in Real-time when reactive resources are expected to be limited? Keep voltage schedules as low as the schedules will allow. Ensure that sufficient dynamic and static MVAR sources are available. Maintain system transfer limits to safe limits to prevent a loss synchronization type of voltage collapse. Consider increasing MW transfers to limit reactive power losses when conditions become critical.
Ensure that sufficient dynamic and static MVAR sources are available. Feedback: Based on its assessment of the system, each Transmission Operator shall have evidence of scheduling sufficient reactive resources within its area to protect the voltage levels under normal and contingency conditions. Transmission Operators can provide sufficient reactive resources through various means including, but not limited to, reactive generation scheduling, transmission line and reactive resource switching, and using controllable load.
125
The voltage on the power system is increasing due to an unexpected drop in customer load. Which of the following devices would a Transmission Operator bring on-line to get the voltage level back into a normal range? Capacitors Reactors Static VAR Compensators Generators
Reactors Feedback: Most generators have the capability to absorb reactive power by under-exciting the generator rotor. Static VAR compensators are also able to absorb excessive reactive power using its reactors as needed in just a few cycles. However, generators with their AVR in service and static VAR compensators are dynamic resources and should already be in service. If voltage is spiking due to an unexpected drop in customer load, reactors, which are typically located at high voltage stations, can be brought into service as needed.
126
A 354 kV line carrying 1250 MWs of power trips off-line. This results in a SOL and IROL violation for a 230 kV parallel line and some substation buses to be 10% below their nominal voltage. What can the transmission operator do to return the system to its established voltage limits ready, for the next contingency? Use Under Load Tap Changers to increase the distribution voltage. Send out an appeal for voluntary reductions. Re-dispatch generation, request MVAR support from each generator, place all available voltage support equipment on line, and curtail load if necessary. Request power marketers purchase power.
Re-dispatch generation, request MVAR support from each generator, place all available voltage support equipment on line, and curtail load if necessary. Feedback: The increased flow on the 230kV line has pushed it above its Surge Impedance Loading causing the line to become a consumer of reactive power. Coupled with the loss of the voltage support from the 345kV line, this results in a System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL) violation. NERC requires the Transmission Operator to resolve the operating limit violation as soon as possible but no longer than 30 minutes. The Transmission Operator's first choice might be re-dispatch generation and request all Generator Operators increase their voltage support. If this works, it should prepare for the next contingency. If the transmission system is still in violation, the next choice would be to curtail load in the area.
127
What are the two factors that determine the amount of voltage rise on a line? Flattening the curve with capacitors. Strength of the bus at the closed end. When MWs are increased from one electrical bus to another. Length of the line being energized.
Strength of the bus at the closed end. Length of the line being energized. Feedback: Two factors that determine the amount of voltage rise on the line are the length of the line being energized and the strength of the bus at the closed end.
128
MVAR production can be increased or decreased by which of the following: by placing a high voltage transmission line in service or taking one out of service. Placing a generator on Automatic Generation Control. the Ferranti Voltage Rise Effect. Placing an Under Load Tap Changer in automatic.
by placing a high voltage transmission line in service or taking one out of service. Feedback: Transmission lines can be a source of reactive power or a sink of reactive power. MVAR production can be increased or decreased by placing a high voltage transmission line in service or taking one out of service. This is an acceptable method of controlling voltage on the transmission system but should only be used when engineering studies indicate taking the line out of service will not have a negative impact on reliability.
129
What could cause low voltage on the Transmission and/or Distribution system? Misoperation of Static VAR Compensator A shortage of reactive resources Low power flows on the system An excessive amount of reactive power
A shortage of reactive resources Feedback: The root cause of low voltage is simply not having enough reactive power. If voltage needs to be raised, increase the reactive output of the generators, and place capacitor banks in service. When there is a shortage of reactive power, voltages drop as MW load increases. As current flow increases, making the transmission system more inductive, losses on the system increase.
130
What is the Ferranti Voltage Rise Effect? The voltage rise that occurs when the transmission system has an open-ended, energized transmission line. When MVAR product is increased. The sudden, dramatic increase in the line's surge impedance loading. The effect the P-V curve has on the receiving bus.
The voltage rise that occurs when the transmission system has an open-ended, energized transmission line. Feedback: A very important factor in voltage control is placing lines in service after they have been de-energized. In order to place a line in service, one end usually has to be closed while the other end of the line remains open for a period of time. The effect the open ended energized line has on the transmission system is known as the Ferranti Voltage Rise Effect.
131
Which of the following statements are true? Select all that apply When a line is loaded below its SIL, voltage increases, and capacitive reactive resources decrease the voltage. When a line is loaded above its SIL, voltage decreases, and inductive reactive resources will increase voltage. When a line is loaded below its SIL, voltage increases, and inductive reactive resources will reduce the voltage. When a line is loaded above its SIL, voltage decreases, and capacitive reactive resources will increase voltage.
When a line is loaded below its SIL, voltage increases, and inductive reactive resources will reduce the voltage. When a line is loaded above its SIL, voltage decreases, and capacitive reactive resources will increase voltage. Feedback: A transmission line loaded above its SIL (Surge Impedance Loading) decrease voltage, while a transmission line loaded below its SIL increases voltage. Capacitive reactive resources, such as capacitor banks, are designed to add MVARs to the system to increase voltage. Inductive reactive resources, such as reactors, are designed to absorb MVARs from the system to decrease voltage.
132
The voltage on the power system is starting to drop due to the normal load pick-up during the morning hours. As a Transmission Operator, where should you increase the reactive power on the transmission and distribution systems? Close to generation areas. The location of the reactive power has no effect on the voltage levels when inductive loads are causing the declining voltage. As close to the heaviest inductive load areas as possible. As far away from the heaviest inductive load areas as possible.
As close to the heaviest inductive load areas as possible. Feedback: The closer you can place reactive power sources to the inductive load, the less current you will have on the transmission system thus fewer MW and MVAR losses.
133
Is the Generator Operator required to give advance notification to the Transmission Operator for all of the following conditions? Generator testing Generator start-up Generator shut-down Yes No
Yes Feedback: Generators off-line for testing and during start-up or shutdown modes, cannot operate in AVR mode. Generators that cannot operate with the Automatic Voltage Regulator in service and controlling voltage may be unable to meet their generator voltage or reactive power schedule and the Transmission Operator must be notified.
134
Which of the following responses about the voltage or Reactive Power schedule are true? Choose all that apply. A target value communicated by the Transmission Operator to the Generator Operator establishes a tolerance band within which the target value is to be maintained during a specified period. Unless exempted by the Transmission Operator, each Generator shall maintain the generator voltage or Reactive Power schedule. When a generator's Automatic Voltage Regulator is out of service, the Generator Operator shall use an alternative method to control the generator reactive power output to meet the schedule provided by the Transmission Operator. A generator that cannot follow its Voltage Schedule is exempt.
A target value communicated by the Transmission Operator to the Generator Operator establishes a tolerance band within which the target value is to be maintained during a specified period. Unless exempted by the Transmission Operator, each Generator shall maintain the generator voltage or Reactive Power schedule. When a generator's Automatic Voltage Regulator is out of service, the Generator Operator shall use an alternative method to control the generator reactive power output to meet the schedule provided by the Transmission Operator. Feedback: Voltage control is a critical factor in the reliability of the Interconnection. Generators following a Voltage Schedule help keep system voltage at a satisfactory level. The voltage or Reactive Power schedule is a target value communicated by the Transmission Operator to the Generator Operator and is to be maintained for the specified period unless the Generator Operator is granted an exemption by the Transmission Operator, or the Transmission Operator has instructed the Generator Operator to modify voltage. When a generators Automatic voltage Regulator (AVR) is out of service, the Generator Operator shall use an alternative method to control the generator voltage and reactive output in order to meet the schedule.
135
Generator Owners are responsible for providing the Transmission Planner and Transmission Operator with requested information about generator step-up transformers and auxiliary transformers with primary voltages equal to or greater than the generator terminal voltage. Who must the Generator Owner consult regarding the necessary step-up transformer tap changes? Reliability Coordinator Transmission Operator Generator Operator Generator Owner
Transmission Operator Feedback: It is the responsibility of the Generator Owner to provide this information to the Transmission Operator and Transmission Planner, however, the Transmission Operator makes the request for step-up transformer tap changes as needed to support system voltages.
136
The Transmission Operator and Transmission Planner have requested the tap settings, available fixed tap ranges, and impedance data for several generator step-up transformers. How long does the Generator Owner(s) have to provide this information? 20 Calendar Days 30 Calendar Days 10 Calendar Days 60 Calendar Days 20 Calendar Days
30 Calendar Days Feedback: The Generator Owner has 30 calendar days to supply the Transmission Operator and Transmission Planner with requested information on its set-up transformers and auxiliary transformers. This information is used by the Transmission Operator and Transmission Planner to calculate the step-change percentage.
137
The Transmission Operator has determined the tap settings of a generators step-up transformer must change. Which entity is required to ensure the requested changes are implemented? Transmission Planner Generator Operator Transmission Owner Generator Owner
Generator Owner Feedback: Ater consulting with the Transmission Operator, the Generation Owner will ensure its step-up transformer taps are modified per the Transmission Operator's documentation, unless such action would violate safety, an equipment rating, a regulatory requirement, or a statutory requirement. If a Generator Owner cannot comply with the specification, it shall notify the Transmission Operator and provide the technical justification.
138
If your generator is offline for a scheduled maintenance and not in start-up mode, which of the following is also true? A Real-time communication or procedure has been provided to the Transmission Operator notifying it the generator is offline and will be in manual voltage control until it's ramped up to its minimum continuously sustainable load. A Real-time communication or procedure has been provided to the Transmission Operator notifying it the generator is offline, and the Automatic Voltage Control Mode is in place during start-up.
A Real-time communication or procedure has been provided to the Transmission Operator notifying it the generator is offline and will be in manual voltage control until it's ramped up to its minimum continuously sustainable load. Feedback: The Generator Operator operates each generator interconnected to the BES in the Automatic Voltage Control mode unless the Transmission Operator has specified a different control mode or the Generator Operator has notified the Transmission Operator through a real-time communication or procedure, the generator is being operated in start-up, shutdown or testing mode. When a generator is in start-up mode it gradually increases its MW output and voltage control must be manually adjusted to keep pace until the generator reaches its minimum continuously sustainable load and can be synchronized to the interconnection.
139
Why must the Generator Operator use an alternative method to control the generator voltage and reactive output when the Automatic Voltage Regulator is out of service? To comply with training requirements. To meet the voltage or Reactive Power Schedule. To get ahead of the voltage.
To meet the voltage or Reactive Power Schedule. Feedback: Generator Voltage Schedule is how all generators work together to maintain power system voltages and schedules. Unless exempted by the Transmission Operator, each Generator Operator is required to maintain the generator voltage or Reactive Power schedule within each generating facility's capabilities.
140
When power flow is expected to reach or exceed System Operating Limits, the System Operator must:' Continue to provide electric service to customers. None of the answers are correct. Disconnect the equipment. Redistribute power flow to relieve the overloaded transmission line.
Redistribute power flow to relieve the overloaded transmission line. Feedback: When power flow has reached or is exceeding its respective System Operating Limits, System Operators must try to redistribute the power flow to relieve the congested line. If the overload is severe, they may need to disconnect service to customers or load shed. Disconnecting equipment is discouraged in the power system.
141
Which procedure utilizes Power Transfer Distribution Factors to curtail transactions and reduce power flows? Control Performance Standard. Transmission Loading Relief. Outage Transfer Distribution Factor. Interchange distribution Calculator.
Transmission Loading Relief. Feedback: Transmission Load Relief procedures use Power Transfer Distribution Factors to curtail transactions and reduce power flows. The Control Performance Standards calculation do not use Distribution Factors. The Interchange Distribution Calculator contains a matrix of line and transformer impedance's, it is a tool, and not a procedure. Outage Transfer Distribution Factors are used to determine the effects of transmission outages.
142
Outage Transfer Distribution Factors help System Operators __________. (select best answer) estimate the effect of an outaged transmission elements determine which Interchange Transactions may be affecting a constrained path. estimate the System Operating Limit of a transmission line. determine the number of unexpected outaged elements.
estimate the effect of an outaged transmission elements Feedback: Outage Transfer Distribution Factors help System Operators estimate the effect of outaged transmission elements. Power Transfer Distribution Factors estimates the effect of an Interchange Transaction on a specific flowgate. The answers 'determine the number of unexpected outaged elements...' and estimate the system operating limit...' are false and serve as distracters in this question.
143
Generation Shift Factors help System Operators determine which ___________. (select best answer) generators are operating at maximum capacity. generators could be adjusted to relieve the loading on the transmission lines. interchange transactions may be impacting overloaded conditions. generators produce power most efficiently
generators could be adjusted to relieve the loading on the transmission lines. Feedback: Generation Shift Factors help System Operators determine which generators may be adjusted to relieve loading on transmission lines. Generator Shift Factors determine the amount of flow contribution that changes in output will have on identified transmission facilities.
144
How does a negative Generation Shift Factor affect line loading? When a generator with a negative shift factor increases is output, it contributes to loading on the transmission line. A generator with a negative shift factor inefficient. When a generator with a negative shift factor increases its output, it relieves line loading. A generator with a negative shift factor is in the Source Balancing Area.
When a generator with a negative shift factor increases its output, it relieves line loading. Feedback: When a generator with a negative shift factor increases its output, the power flow relieves line loading, typically because the generation increase is close to load.
145
A transmission line is overloaded by 100 MWs. The Harbor and Greenwood generators affect the overloaded line; the Harbor generator has a GSF of 0.25 and the Greenwood generator has a GSF of -0.5. Which of the following dispatch scenarios will provide adequate relief for the line? Decrease the Harbor generator 200 MWs. Decrease the Greenwood generator 200 MWs. Increase the Greenwood generator 200 MWs. Increase Harbor generator 135 MWs and decrease Greenwood generator 135 MWs.
Increase the Greenwood generator 200 MWs. Feedback: Positive Generator Shift Factors will increase loading on the specified line and negative Generator Shift factors will decrease loading. However, these directional signs must be considered when analyzing the direction of flow, shift factor direction and the relief needed.
146
Power Transfer Distribution Factors help System Operators _____________. (Select the best answer) determine which Interchange Transactions may be affecting a constrained path. determine a generator's impact on a flowgate. determine power needs of the Balancing Authorities that purchased it. estimate the effort of outaged transmission element(s)
determine which Interchange Transactions may be affecting a constrained path. Feedback: Power Transfer Distribution Factors help system operators determine if an Interchange Transaction may be affecting a constrained path. It is also used to determine if any of these transactions should be curtailed to relieve congestion. Outage Transfer Distribution Factors determine the effect of outage transmission elements. Generation shift Factors determine a generator's impact on a flowgate. Distribution or shift factors help System Operators determine power needs.
147
Which type of tools use Line Outage Distribution Factors to predict the loading on transmission elements in the event of a transmission line outage? Marketing analysis tools. Contingency analysis tools. Load ability Calculator. Congestion management tools.
Contingency analysis tools. Feedback: Contingency Analysis tools use Line Outage Distribution Factors to predict how transmission line outages may affect loading on other lines. The other terms load ability calculator, market analysis and congestion management are tools that have other applications.
148
System load is continuing to increase when a transmission line becomes overloaded by 100 MWs. Both St. Clair and Grand River generators affect the overloaded line; the St. Clair generator has a GSF of +0.6 and the Grand River generator has a GSF of -0.4. Which of the following options is best for the System Operator to perform? Increase the Grand River generator by 250 MWs. Decrease the Grand River generator by 125 MWs and increase the St. Clair generator by 125 MWs. Decrease the St. Clair generator by 100 MWs.
Increase the Grand River generator by 250 MWs. Feedback: There are many combinations that will provide the needed relief, including increasing the output of the generator that has a negative impact or shift factor and decreasing the generator that has the added impact or positive shift factor. Decreasing the St. Clair generators output by 100 MWs will provide 60 MWs of relief, not enough to relieve the overload. Decreasing the Grand River generator output will increase loading because of its negative shift factor and increasing output of the St. Clair generator will also increase load. The best of these options is to increase the output of the Grand river generator by 250 MWs to obtain the 100 MWs of relief. 100/0.4=250 MWs.
149
How does a positive Generation Shift Factor affect line loading? A generator with a positive shift factor economical. When a generator with a positive shift factor increases its output, it contributes to loading on the transmission line. When a generator with a positive shift factor increases its output, it relieves the loading. When a generator with a positive shift factor is in the Load or Sink area.
When a generator with a positive shift factor increases its output, it contributes to loading on the transmission line. Feedback: When a generator with a positive shift factor increases its output, the increased power flow will contribute to line loading.
150
System Operators must act when congestion or overloading on transmission lines causes which of the following conditions? Inability to transfer power sold to adjacent Balancing Authorities. System Load exceeding generator capability. A violation of Control Performance Standards (CPS). Transmission lines exceeding their System Operating Limits.
Transmission lines exceeding their System Operating Limits. Feedback: System Operators must act when congested or overloaded transmission lines in their area have either reached or exceeded their System Operating Limits.
151
Transmission line transfer capability is determined by which characteristics? Transfer distribution factors MW, MVAR, MVA limits System loading, voltage, impedance Local loading, voltage, resistance
System loading, voltage, impedance Feedback: Reference: Transmission line limits are affected by system loading, voltage, and physical properties
152
The power system serves mostly inductive loads which consume reactive power. What equipment is used most often to counteract inductive loads? Shunt capacitors Shunt reactors Series capacitors Transformers
Shunt capacitors Feedback: Reference: Shunt capacitors produce reactive power to support inductive loads while maintaining voltage. Capacitor output is best when voltage is 100%
153
Station configurations vary, balancing the economics of building a station with additional breakers and lines. The most expensive and reliable station bus scheme is which of the following? Ring bus Single bus, single breaker Breaker and half Double bus, double breaker
Double bus, double breaker Feedback: Reference: The double bus, double breaker, configuration utilizes two buses and two breakers per circuit. Both buses are normally energized, and any circuit can be removed without an outage on the corresponding circuit. Failure of one bus will not interrupt a circuit because all circuits can be fed from the remaining bus. This configuration is expensive, requiring twice the equipment as a single bus scheme, but is highly reliable.
154
What physical law allows transformation of voltage and current using a transformer? Voltage Electricity Magnetism Electromagnetic induction
Electromagnetic induction Feedback: Reference: When a changing magnetic field is placed next to a coil of wire, voltage is produced. When alternating voltage is applied to a coil wire, a changing magnetic field is produced. Placing both coils of wire next to each other creates a transformer. Changing voltage on one side of the transformer creates voltage on the other side of the transformer.
155
Why do power companies choose to operate a three-phase power system? Distribution of power at a more constant rate, increased efficiency and more economical Less chance for outages Larger generators One conductor per phase
Distribution of power at a more constant rate, increased efficiency and more economical Feedback: Reference: A three-phase system is more efficient and economical that a single-phase system.
156
What is the effect on power losses if voltage is doubled and load magnitude stays the same? Losses are doubled Losses decrease by a factor of four Losses increase by a factor of four Losses are halved
Losses decrease by a factor of four Feedback: Reference: Power loss is current squared times resistance. Increasing voltage reduces current. Reducing current will reduce the power losses by a factor of four. Transformers in a power system are used to increase voltage and reduce current.
157
Substation equipment regulates voltage and provides critical information back to control centers for monitoring. When maintenance is required, the substation provides which of the following? Isolation points through breakers and switches Interconnection Scheme Redundancy
Isolation points through breakers and switches
158
What is the MVAR output of a 50 MVAR shunt capacitor energized when a 100 kV bus is at 90 kV (or 90% of its nominal voltage)? 40.5 55.6 61.7 45
40.5
159
System operators should keep voltage within what range for normal operations? 10% less than nominal and 5% greater than nominal 5% greater than nominal and 5% less than nominal 10% greater than nominal and 10% less than nominal 5% less than nominal and 10% greater than nominal
5% greater than nominal and 5% less than nominal Feedback: Reference: The Transmission Operators' task is to control voltage and keep it within a plus or minus (+/-) 5% bandwidth during normal operations.
160
A transmission line is rated at 1000 MVA. The power flow is currently 990 MW and 100 MVAR. Is this transmission line overloaded? No Yes Cannot be determined Power must be reduced
No Feedback: Reference: Total power is the square root of 9902 + 1002 which equals 995 MVA. This line is not overloaded.
161
Transmission lines, transformers, and other equipment have System Operating Limits or SOLs. What is a SOL? Angle stability limit A MW, MVAR, amp, voltage value that satisfies the most limiting of the prescribed operating criteria for a specified system configuration. Thermal limit When the MVAR from a transmission line's natural capacitance is equal to the MVAR the line needs to support its voltage
A MW, MVAR, amp, voltage value that satisfies the most limiting of the prescribed operating criteria for a specified system configuration. Feedback: Reference: According to the NERC Glossary of terms for System Operating Limits, system Operating Limits are based upon certain operating criteria to ensure operation within acceptable reliability criteria.
162
200 MW is scheduled to flow from Area X to Area Y. A transmission line on the scheduled path has an 80% distribution factor for this schedule. How much of the 200 MW schedule will flow on the transmission line? 160 MW 200 MW 100 MW 40 MW
160 MW Feedback: Reference: Power Transfer Distribution Factor, PTDF, is the percentage of electrical loading due to power flowing through the system. Power distribution is determined by transmission line property characteristics. In this problem, 80% PTDF for a 200 MW schedule means 160 MW will flow on Line X-Z.
163
How do we protect the power system from abnormal current or voltage surges? System studies Relay protection Situational awareness Operate the system with much lower than its System Operating Limits
Relay protection Feedback: Reference: Automated breaker operation protects the power system when certain conditions are met. Protective relays monitor system conditions, compare Real-time quantities against preset thresholds and react to abnormal conditions.
164
Impedance is the combination of which properties? Resistance and reactance Inductance and capacitance Loading and voltage Geomagnetic induced currents and resonance
Resistance and reactance Feedback: Reference: Impedance is the square root of resistance squared plus reactance squared. The sum of inductance and capacitance is called reactance.
165
What is the main purpose of the system of electrical conductors and substations we call the transmission system? Increase distance for power to travel Deliver power from generators to consumer loads Direct paths to customer Increase power losses
Deliver power from generators to consumer loads Feedback: Reference: Transmission lines are electricity's highways. The transmission system connects load to generation.
166
At what torque angle of operation does power typically begin to flow from the generator to the system? 30 degrees 10 degrees 60 degrees 90 degrees
10 degrees Feedback: When the torque angle of the generator reaches approximately 10 degrees, it begins to supply power to the system. Torque angles of 30 to 60 degrees indicate that the generator is in full operation. If the generator torque angle reaches 90 degrees or more, the generator may experience a loss of synchronization causing instability in the system.
167
Choose the answer that best describes the operation of a rotor. A type of superconductor. The stationary part of the transmission system. The excited (energized) field winding that rotates inside the stator to induce voltage into the stator winding and allows current to flow out of the stator when the generator is connected to the power grid. The stationary element of a generator that has its windings connected to the system.
The excited (energized) field winding that rotates inside the stator to induce voltage into the stator winding and allows current to flow out of the stator when the generator is connected to the power grid. Feedback: The energized field windings of the rotor rotate inside the stator to induce voltage into the stator windings allowing current to flow out of the stator when the generator is connected to the power grid.
168
In a system that is more capacitive than inductive, the current sine wave will ___________ the voltage sine wave which tends to ___________ voltage. lead; lower lag; lower lag; raise lead; raise
lead; raise Feedback: An inductive system tends to lower voltages and require more voltage support. Voltage leads current in an inductive system (ELI). A capacitive system tends to raise voltage, current leads voltage in a capacitive system (ICE).
169
Sustained operation with a power angle or torque angle above ________ can lead to system instability. 120 degrees 360 degrees 10 degrees 90 degrees
90 degrees Feedback: Power angles above 90 degrees will lead to system instability.
170
Which of the following conditions may cause transient instability in the power system? When the power angle increases to 90 degrees or more. When a disturbance causes momentary power angle excursions greater than 90 degrees. When heavy power transfers occur in the system, such as when there is a loss in generation. All of the above.
All of the above. Feedback: When the power angle between two points on the power system increases to an angle of 90 degrees, or more, transient instability occurs. This is often the result of heavy power transfers on the system combined with a loss of generation.
171
Which of the following is a method(s) Reliability Coordinators and Transmission Operators may use to manage transmission outages? Coordinate and adhere to voltage schedules to minimize reactive power flow. Optimize the use of Load Tap Changer transformer, capacitor, and reactors. Verify voltage control equipment are on automatic to supply the required support. All the above.
All the above. Feedback: Reliability Coordinators and Transmission Operators may use a number of techniques to manage the impact of transmission outages. These include coordinating and adhering to voltage schedules, optimizing the use of LTC transformers, and verifying voltage control equipment are operating in automatic mode.
172
A(n) ___________ is the value that satisfies the most limiting of the prescribed operating criteria for a specified system configuration to ensure operation within acceptable reliability criteria. System Operating Limit System Overloading Limit Interconnection Reliability Operating Limits Circuit Overload
System Operating Limit Feedback: The System Operating Limit is the most limiting of the operating criteria for a specified system configuration that ensures it remains within acceptable reliability criteria. The Interconnection Reliability Operating Limit is a subset of the System Operating Limits that, if exceeded, could expose a widespread area of the Bulk Electric System to instability, uncontrolled separation or cascading outages.
173
When a large generator in an Interconnection trips off line, the ___________ of the Interconnection ___________. frequency; decreases voltage; increases AVRs; decreases transformer temperature; decreases
frequency; decreases Feedback: When total generation in an Interconnection is less than the demand in the Interconnection, the Interconnection frequency decreases. Interconnection frequency reflects the balance of generation and load demand.
174
Which of the following is one of the criteria used to determine a System Operating Limit? Recognizing vegetation management limitations. Identifying equipment minimum loading capabilities. Setting appropriate voltage levels to withstand various contingencies. Identifying how transformers respond to severe fluctuations in frequency.
Setting appropriate voltage levels to withstand various contingencies. Feedback: System Operating Limits are determined by: setting appropriate voltage levels to withstand various contingencies. identifying equipment loading capabilities before excessive heat degrades their function and recognizing stability limitations.
175
Generator ratings specify the _________ and ___________ at which they can operate safely. temperature; voltage voltage; frequency Torque angle; voltage System Operating Limits; Interconnection Operating Limits
voltage; frequency Feedback: The generator's ratings specify the voltage and frequency at which it can continue to operate safely. Operating at a frequency or voltage level that is outside its ratings will cause damage to the generator.
176
Which of the following communications methodologies would be considered an alternative Interpersonal communications system for a telephone based Interpersonal communications system? Cell phone based system VOIP (Voice Over Internet Protocol) based system Satellite telephone based system All the above
All the above Feedback: COM-001-2 requires the Reliability Coordinator, Transmission Operator, and Balancing Authority to have an Alternative Interpersonal Communication system. This system must be redundant to the Interpersonal Communications System and not use the same infrastructure as the day-to-day Interpersonal Communication system.
177
A Transmission Operator uses a phone system for its primary Interpersonal communications system in the control room. If this system goes out of service, which of the following methods of communications would be a good choice for the Alternative Interpersonal Communications system? Different extension on the same telephone system Satellite phone and a cell phone Satellite phone Cell phone
Satellite phone and a cell phone Feedback: NERC glossary of terms, Alternative Interpersonal Communications definition. Any Interpersonal Communication that is able to serve as a substitute for and does not utilize the same infrastructure (medium) as, Interpersonal Communication used for day-to-day operation. A satellite phone and a cell phone would not utilize the same infrastructure as the normal day-to-day Interpersonal Communications system.
178
Each Reliability Coordinator, Transmission Operator, Generator Operator, and Balancing Authority shall have internal Interpersonal Communication capabilities for the exchange of information necessary for the Reliable Operation of the Bulk Electric System (BES). These include communication capabilities between Control Centers and field personnel, as well as which of the following? Control Centers within the same functional entity RCIS All Control Centers Internally
Control Centers within the same functional entity Feedback: The Reliability Coordinator, Transmission Operator, and Balancing Authority shall test their Alternative Interpersonal Communication capability at least once each calendar month. If the test is unsuccessful, the responsible entity shall initiate action to repair or designate a replacement Alternative Interpersonal Communication capability within 2 hours. Examples of Alternative Communications are Satellite phone, radio systems, or any other documented designated telecommunications capability.
179
Coordinating communications among Reliability Coordinators, Transmission Operators and Balancing Authorities must include the ability to do which of the following? Investigate and recommend solutions to internal and external telecommunications problems. Give management a consistent report in the event of a disturbance. Jointly contact the FBI or RCMP (as applicable) to report sabotage. Agree on what to tell news media representative in an emergency.
Investigate and recommend solutions to internal and external telecommunications problems. Feedback: Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall provide a means to coordinate telecommunications among their respective areas. This coordination shall include the ability to investigate and recommend solutions to telecommunications problems within the area and with other areas.
180
Which language has been established for all communications between and among operating personnel responsible for real-time generation control and operations of the Interconnected Bulk electric system? English English/French English/Spanish Spanish
English Feedback: Unless agreed to otherwise each Reliability Coordinator, Transmission Operator, and Balancing Authority shall use English as the language for all communications between and among operating personnel responsible for the real-time generation and operation of the Interconnected Bulk Electric System.
181
Where applicable, telecommunications facilities shall utilize different infrastructure. Which of the following is also required of these facilities? Redundancy Solid state Resplendency State of the art
Redundancy Feedback: Definition of the Alternative Interpersonal Communication. Any Interpersonal Communication that is able to serve as a substitute for and does not utilize the same infrastructure (medium) as, Interpersonal Communication used for day-to-day operation.
182
Vital telecommunications facilities shall be managed and alarmed in addition to what other action? Tested and/or actively monitored Inspected annually Utilized often Maintained under contract
Tested and/or actively monitored Feedback: Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall manage, alarm, test and/or actively monitor vital telecommunications facilities.
183
hat does NERC's concern with communications systems center mostly on? Cost Backup systems Training Reliability
Reliability Feedback: Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall provide adequate and reliable telecommunications facilities [for] the exchange of Interconnection and operating information.
184
Each Reliability Coordinator, Transmission Operator and Balancing Authority shall provide adequate and reliable telecommunications facilities internally and with which of the following? The Department of Energy Operations Center NERC Regions All PSEs operating within the Reliability Area boundaries Other Reliability Coordinators, Transmission Operators, and Balancing Authorities.
Other Reliability Coordinators, Transmission Operators, and Balancing Authorities. Feedback: Reliability Coordinators are required to have Interpersonal and Alternative Interpersonal Communication capability with Transmission Operators and Balancing Authorities in their RC area and with adjacent Reliability Coordinators.
185
Each control room should test its telecommunications facilities. Special attention should be given to emergency telecommunications facilities as well as what other equipment? Relay switches Broadband communication channels Equipment not used for routine communications Short-wave radios
Equipment not used for routine communications Feedback: Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall manage, alarm, test and/or actively monitor vital telecommunications facilities. Special attention shall be given to emergency telecommunications facilities and equipment not used for routine communications. Emergency and alternative facilities should receive special attention because it is easy to overlook equipment that is not normally used. Since they may be the facilities of last resort, it is important that they be available when needed.
186
If a Balancing Authority determines that its Interpersonal Communications system has been disabled for 30 minutes due to a power supply failure, how long does the Balancing Authority have to notify its Transmission Operator of the failure? Two (2) hours 30 minutes Immediately One (1) hour
One (1) hour Feedback: COM-002, Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall notify entities respectively within 60 minutes of the detection of a failure of its Interpersonal communication capability that lasts 30 minutes or longer.
187
If a Reliability Coordinator is testing the Alternative Interpersonal Communications system, and after the test determines the system is not functioning in accordance with requirements, what must the Reliability Coordinator do to address this issue? Continue testing the Alternative Interpersonal Communications system until it satisfies the requirements. Initiate action to repair or designate a replacement Alternative Interpersonal Communication system capability within 2 hours. Immediately submit a report to the RE stating the reasons for the system failure. Notify affected Balancing Authorities and Transmission Operators within 60 minutes.
Initiate action to repair or designate a replacement Alternative Interpersonal Communication system capability within 2 hours. Feedback: COM-001, Each Reliability Coordinator, Transmission Operator, and Balancing Authority shall test its Alternative Interpersonal Communication capability (TRE1) at least once each calendar month. If the test is unsuccessful, the responsible entity shall initiate action to repair or designate a replacement Alternative Interpersonal Communication capability within 2 hours.
188
A Transmission Operator receives an oral two-party, person-to-person Operating Instruction from the Reliability Coordinator but doesn't completely understand the Instruction. He/she can: Repeat verbatim the interpretation of the Operating Instruction. Notify all the Transmission Operators and Balancing Authorities via an Interconnection-wide telecommunications system. Accept the Operating Instruction by just acknowledging receipt of the order. Request that the Reliability Coordinator reissue the Operating Instruction.
Request that the Reliability Coordinator reissue the Operating Instruction. Feedback: NERC Standard COM-002-4 R6 R6 requires each Balancing Authority, Distribution Provider, Generator Operator, and Transmission Operator who during an emergency, receives an oral two-party, person-to-person Operating Instruction, excluding written or oral single-party to multiple party burst Operating Instructions, request that the issuer reissue the Operating Instruction.
189
Each Transmission Operator, Balancing Authority, and Reliability Coordinator shall develop a documented communication protocol for its operating personnel who issue and receive ________. Operating Instructions Operating Migration Directions Directives Operation Planning Instructions
Operating Instructions Feedback: R1 requires each Transmission Operators, Balancing Authority, and Reliability Coordinator to develop documented communications protocols for its operating personnel who issue and receive Operating Instructions.
190
A Transmission Operator receives an Operating Instruction from its Reliability Coordinator. The Transmission Operator must repeat the Operating Instruction back to the Reliability Coordinator: Verbatim every time the Transmission Operator receives an Operating Instruction during an emergency. Only during an emergency or alert. Verbatim every time the Transmission Operator receives an Operating Instruction. Not necessarily verbatim as long as the major components of the Operating Instruction are repeated correctly.
Not necessarily verbatim as long as the major components of the Operating Instruction are repeated correctly. Feedback: R6 requires each Balancing Authority, Distribution Provider, Generator Operator, and Transmission Operator who during an emergency, receives an oral two-party, person-to-person Operating Instruction, excluding written or oral single-party to multiple party burst Operating Instructions to either: Repeat, not necessarily verbatim, the Operating Instruction, and receive confirmation from the issuer that the response was correct, or Request that the issuer reissue the Operating Instruction.
191
A Transmission Operator who issues an oral single-party to multiple-party burst All Call Operating Instruction during an emergency is ____________. Required to have every attendee on the phone to respond with a correct repeat back of the Operating Instruction. Required to confirm or verify that the Operating Instruction was received by at least one receiver of the all call Operating Instruction. Required to have every attendee on the phone to respond with an acknowledgement of the Operating Instruction. None of the above.
Required to confirm or verify that the Operating Instruction was received by at least one receiver of the all call Operating Instruction. Feedback: R7 requires each Balancing Authority, Reliability Coordinator, and Transmission Operator who during an emergency, issues a written or oral single-party to multiple-party burst Operating Instruction to confirm or verify that the Operating Instruction was received by at least one receiver of the Operating Instruction. A one-way single party to multiple-arty burst can be defined as an "All-Call" messaging system.
192
During an emergency situation, a Reliability Coordinator issues an Operating Instruction to a Transmission Operator. The Transmission Operator repeats the Operating Instruction back with a mistake in it. What should the Reliability Coordinator do? Repeat the original statement to resolve any misunderstandings. Assume the Transmission Operator understood but missspoke. Interrupt the repeat back and move on. Repeat only the statement that contained the mistake.
Repeat the original statement to resolve any misunderstandings. Feedback: R5 requires each Reliability Coordinator, Transmission Operator and Balancing Authority who during an emergency, issues an oral two-party, person-to-person Operating Instruction, excluding written or oral single-party to multiple-party burst Operating Instructions, to either: Confirm the receiver's response if the repeated information is correct reissue the Operating Instruction if the repeated information is incorrect or if requested by the receiver, or take an alternative action if a response is not received or if the Operating Instruction was not understood by the receiver.
193
Per NERC COM-002-4, which of the following elements MUST be included in the documented communication protocols for operating personnel that issue and receive Operating Instructions? Select all that apply. Use the English language unless agreed to otherwise. Notify, via individual phone calls, the Reliability Coordinator and all other potentially affected Balancing Authorities and Transmission Operators of the problem. Specify nomenclature for transmission interface Elements and Facilities. Enunciate clearly and distinctly when issuing Operating Instructions.
Use the English language unless agreed to otherwise. Specify nomenclature for transmission interface Elements and Facilities. Feedback: Requirement R1.1 The protocols must require operating personnel who issue and receive an oral or written Operating Instruction to use the English language, unless agreed to otherwise. Requirement R1.6 The protocols must specify the nomenclature for Transmission interface Elements and Transmission interface Facilities when issuing an oral or written Operating Instruction.
194
Which of the following actions would be required in accordance with COM-002-4 when communicating an Operating Instruction? Select all that apply. A Balancing Authority repeats the operating instruction back to the Reliability Coordinator. A Reliability Coordinator confirms the Balancing Authority understood what is to be done. A Reliability Coordinator clearly states the Operating Instruction. A Reliability Coordinator corrects the response if it is not repeated back correctly.
All apply Feedback: Element 1.2: The protocols must require operating personnel that Issue an oral two-party, person-to-person operating Instruction take one of the following actions: Confirm the receiver's response if the repeated information is correct. Reissue the Operating Instruction if the repeated information is incorrect or if requested by the receiver. Take an alternative action if a response is not received or if the Operating Instruction was not understood by the receiver.
195
ERC Standard COM-002-4 states that each Transmission Operator, Balancing Authority, and Generator Operator shall do what at least once every 12 months: Select all that apply. Assess adherence to the documented communication protocols in Requirement R1 by its operating personnel who issue and receive Operating Instructions. Provide feedback to those operating personnel and take corrective action, as deemed appropriate by the entity, to address deviations from the documented protocols. Assess the effectiveness of its documented communications protocols for its operating personnel who issue and receive Operating Instructions and modify its documented communication protocols, as necessary. Discipline and retrain operators who deviated from documented communication protocols.
Assess adherence to the documented communication protocols in Requirement R1 by its operating personnel who issue and receive Operating Instructions. Provide feedback to those operating personnel and take corrective action, as deemed appropriate by the entity, to address deviations from the documented protocols. Assess the effectiveness of its documented communications protocols for its operating personnel who issue and receive Operating Instructions and modify its documented communication protocols, as necessary. Feedback: R4 requires each Reliability Coordinator, Balancing Authority, and Transmission Operator to assess adherence to, and the effectiveness of its documented communications protocols at least once every twelve (12) calendar months. 4.1 Assess adherence to the documented communications protocols in Requirement R1 by its operating personnel who issue and receive Operating Instructions, provide feedback to those operating personnel and take corrective action, as deemed appropriate by the entity, to address deviations from the documented protocols. 4.2 Assess the effectiveness of its documented communications protocols in Requirement R1 for its operating personnel who issue and receive Operating Instructions and modify its documented communication protocols, as necessary.
196
NERC COM-002-4 requires initial training for which operating personnel who either issue and/or receive Operating Instructions? Select all that apply. Reliability Coordinators Generator Operators Balancing Authorities and Transmission Operators Distribution Providers
All apply Feedback: R2 states that each RC, BA, and TOP shall conduct initial training for each of its operating personnel responsible for the Real-time operation of the interconnected Bulk Electric System on their documented communication protocols that were developed in Requirement R1 prior to that individual operator issuing an Operating Instruction. R3 states that each Distribution Provider and Generator Operator shall conduct initial training for each of its operating personnel who can receive an oral two-party, person-to-person Operating Instruction prior to that individual operator receiving an oral two-party, person-t-person Operating Instruction.
197
NERC Standard COM-002-4 states documented communication protocols must require operating personnel who issue an oral or written Operating Instruction to: Select all that apply. Notify the Reliability Coordinator and all other potentially affected Transmission Entities. Use an alternative language for internal operations. Use English language, unless agreed to otherwise. Specify instances that require time identification when issuing an oral or written Operating Instruction and the format for that time identification.
Use English language, unless agreed to otherwise. Specify instances that require time identification when issuing an oral or written Operating Instruction and the format for that time identification. Feedback: NERC Standard COM-002-4 R1.1 The protocols must require operating personnel who issue and receive an oral or written Operating Instruction to use the English language, unless agreed to otherwise. An alternate language may be used for internal operations. R1.5 The protocols must specify instances that require time identification when issuing an oral or written Operating Instruction and the format for that time identification.
198
An operating Instruction is defined as: A command by operating personnel responsible for the Real-time operation of the interconnected Bulk Electric System to change or preserve the state, status, output, or input of an Element of the Bulk Electric System or Facility of Bulk Electric System. An order by a NERC Certified System Operator Planning Electrical Engineer. A discussion of general information and potential options or alternatives to resolve Bulk Electric System operating concerns. An order issued by a Reliability Coordinator only.
A command by operating personnel responsible for the Real-time operation of the interconnected Bulk Electric System to change or preserve the state, status, output, or input of an Element of the Bulk Electric System or Facility of Bulk Electric System. Feedback: The NERC glossary of terms defines an Operating Instruction as: A command by operating personnel responsible for the Real-time operation of the interconnected Bulk Electric System to change or preserve the state, status, output, or input of an Element of the Bulk Electric System or Facility of Bulk Electric System. A discussion of general information and of potential options or alternatives to resolve Bulk Electric System operating concerns is not a command and is not considered an Operating Instruction.
199
Per NERC Standard COM-002-4, when should Distribution Providers and Generator Operators conduct initial training for each of their operating personnel who can receive an oral two-party, person-to-person Operating Instruction? Distribution Providers and Generator Operators do not need initial training as they do not receive Operating Instructions. Annually in their communications training. Prior to that individual operator receiving an oral two-party, person-to-person Operating Instruction. After the individual operator receiving an oral two-party, person-to-person Operating Instruction makes a mistake.
Prior to that individual operator receiving an oral two-party, person-to-person Operating Instruction. Feedback: A Balancing Authority that is experiencing an operating capacity or energy emergency shall communicate its current and future system conditions to its Reliability Coordinator and neighboring Balancing Authorities.
200
hree-part communication is known as which of the following? Select all that apply. The repeat of the statement that contained the mistake. The issuance of an Operating Instruction from one party to another. The repeat back of the Operating Instruction by the receiving party. The acknowledgement by the issuing party that the Operating Instruction was repeated back correctly or, if not, reissuing the Operating Instruction again.
The issuance of an Operating Instruction from one party to another. The repeat back of the Operating Instruction by the receiving party. The acknowledgement by the issuing party that the Operating Instruction was repeated back correctly or, if not, reissuing the Operating Instruction again. Feedback: Three-Part Communication gets its name from the three distinct parts of the process: Issuing an Operating Instruction from one party to another. Repeat back of the Operating Instruction by the receiving party. Acknowledgement by the issuing party that the Operating Instruction was repeated back correctly or, if not, reissuing the Operating Instruction again.
201
Why is it important for Real-time operators to have Situational Awareness? To make hasty decisions To know when to take a break To detect SOL violations and predict what might happen on the power system
To detect SOL violations and predict what might happen on the power system Feedback: Real-time Contingency Analysis (RTCA) tools are used to improve the Situational Awareness for System Operators of contingencies that may impact the operating area. The Transmission Operator uses the results of these analyses to immediately mitigate the SOL violation.
202
Outages have a significant impact on which of the following? The direction of power flow. The distance of power flow. Real and reactive power supply. All of the answers are correct.
All of the answers are correct. Feedback: Facility outages will change the power flow on the power system. When an element is unavailable another element will pick up the load to deliver power as needed.
203
Why should network models include scheduled generator and transmission outages? Because outages affect load Because power flows do not change To simulate accurate power flows and contingency analysis results
To simulate accurate power flows and contingency analysis results Feedback: External network model data that will significantly affect the power flows and contingency analysis results in system should be part of the data specification.
204
Which of the four types of data are needed to support real-time assessments? Select all that apply. Transmission status MW output Market price Weather MVAR output Generator status
Transmission status MW output MVAR output Generator status Feedback: Power Flow consists of MW and MVAR output. Availability of generation and transmission asset determines how much power can be produced or transported reliably.
205
What should be included in a data specification document? List of data needs and the periodicity for providing data. Facility list. List of communication channels.
List of data needs and the periodicity for providing data. Feedback: Each Transmission Operator maintains a data specification document that specifies a list of data, the periodicity for providing data, and deadlines to provide the indicated data.
206
Which two functions have data specification for real-time monitoring and analysis? 1. Generator Operator 2. Balancing Authority 3. Load-Serving Entity 4. Transmission Operator 1 and 2 1 and 3 3 and 4 2 and 4
2 and 4 Feedback: NERC Standard TOP-003 states that the Transmission Operator and Balancing Authority have data needed to fulfill their operational and planning responsibilities.
207
What is the purpose of the conduction system studies? Select all that apply. To identify generator status. To identify sabotage. To predict operations. To identify constraints. To identify weather related impacts.
To predict operations. To identify constraints. Feedback: System studies are used to identify constraints and predict operations. Predicting system operation allows for Situation Awareness and mitigation of problems before they happen.
208
When receiving a data specification, which of the following formats should satisfy the obligations of the documented specification? Select all that apply. Computer satisfying format. Mutually agreeable security protocol. Dedicated data format. Mutually agreeable format.
Mutually agreeable security protocol. Mutually agreeable format. Feedback: Each System Operator receiving a data specification shall satisfy the obligations of the documented specifications using: A mutually agreeable format A mutually agreeable process for resolving data conflicts. A mutually agreeable security protocol.
209
Operational and Planning responsibilities for which of the following entities require monitoring transmission and generation resource, availability, output, power flows, and frequency? Distribution Providers Generator and Transmission Owner Transmission Operators, Balancing Authorities, and Reliability Coordinators
Transmission Operators, Balancing Authorities, and Reliability Coordinators Feedback: Transmission Operators, Balancing Authorities, and Reliability Coordinators work together and perform tasks such as: Monitoring transmission and generation resource availability Reviewing generation output continuously Reviewing transmission power flows continuously Monitoring Interconnection frequency
210
Quality of Real-time data is necessary to perform which reliability tasks? Select all that apply. Communication System restoration Analysis functions Real-time monitoring
Analysis functions Real-time monitoring
211
Data quality is critical to decision making and real-time operations. Which of the following shall be included when addressing the quality of data? State Estimation Calculations of each value Criteria for evaluating the quality of Real-time data Database of limits
Criteria for evaluating the quality of Real-time data
212
These entities shall have an alarm process monitor that provides notifications when a failure of their Real-time monitoring alarm processor has occurred. Select all that apply. Generator Operator Transmission Owner Transmission Operators Balancing Authority
Transmission Operators Balancing Authority
213
Real-time monitoring and assessment are a critical task for Reliability Coordinators, if analysis tools are unavailable due to planned maintenance activities, it is the responsibility of the Reliability Coordinator to have procedures in place that address which of the following? mitigate the effects of analysis tools outages. meet the compliance measures. notification with neighboring Transmission Operators. Energy Management System backup
mitigate the effects of analysis tools outages. Feedback: NERC Standard IRO-002 gives each Reliability Coordinator the authority to approve planned outages and maintenance of analysis tools; including, approvals for planned maintenance. In practice if an outage is necessary that effects their ability to analyze the state of their power system, the RC should have a procedure in place that mitigates the effects of analysis tool outages.
214
Reliability Coordinators are required to have data exchange capabilities with its Transmission Operators and Balancing Authorities, and with neighboring Reliability Coordinators to perform which of the following? Supervisory Control and Data Acquisition (SCADA) Switching Balancing tasks Real-time Assessments
Real-time Assessments Feedback: NERC Standard IRO-002: Each Reliability Coordinator shall have data exchange capabilities with its Transmission Operators and Balancing Authorities, and with other entities it deems necessary for it to Operational Planning Analyses. Communication and data exchange capabilities are required to meet reliability need of the interconnection.
215
The Reliability Coordinator shall have real-time monitoring capability in addition to Operational Planning Analysis of its area to ensure what? System powerflows are controlled. Congestion management procedures are utilized. SOL and IROL exceedances are identified. Control Performance Standards are met.
SOL and IROL exceedances are identified. Feedback: Each Reliability Coordinator shall have detailed real-time monitoring capability of its Reliability Coordinator Area and sufficient monitoring capability of its surrounding Reliability Coordinator Areas to ensure that potential or actual System Operating Limit or Interconnection Reliability Operating Limit violations are identified.
216
What is the value that satisfies the most limiting of the prescribed operating criteria for a specified system configuration to ensure operation within acceptable reliability criteria? System Operating Limit Interconnected Operating Limit Operating Security Limit Interconnected Reliability Operating Limit
System Operating Limit Feedback: System Operating Limit: The value (such as MW, MVAR, Amperes, Frequency, or Volts) that satisfies the most limiting of the prescribed operating criteria for a specified system configuration to ensure operation within acceptable reliability criteria. System Operating Limits are based upon certain operating criteria.
217
Why is it important for Responsible Entities such as Reliability Coordinators and Balancing Authorities to report certain events and/or disturbances that occur in their area? To ensure the news media is informed and has accurate information. To improve the reliability of the Bulk Electric System. Implement corrective actions to minimize repetition of the event in the future. To determine the individual(s) responsible for the disturbance.
To improve the reliability of the Bulk Electric System. Feedback: EOP-004: Purpose: to improve the reliability of the Bulk Electric System by requiring the reporting of events by Responsible Entities.
218
Which of the following is/are reasons that Bulk Electric System disturbances should be analyzed? To help eliminate similar occurrences. To implement corrective actions. To ensure "lessons learned" are documented. All answers are correct.
All answers are correct. Feedback: EOP-004: Event reporting and subsequent analysis, assist in providing lessons learned and to implement corrective actions to minimize a repeat in the future. The lessons learned lead to recommendations for corrective actions by involved parties in the incident. Some recommendations may apply to all parties, not only those involved in the event. Upon implementation of the actions, the recurrence is greatly reduced.
219
Which of the following events would require submitting an event report? A total generation loss of 800 MWs in a 1 minute period. The discovery of copper theft at a major substation. A System Operation Limit (SOL) exceedance for more than 30 minutes. A Balancing Authority making a public appeal for load reduction due to abnormally hot temperatures and expected Energy Emergency.
A Balancing Authority making a public appeal for load reduction due to abnormally hot temperatures and expected Energy Emergency.
220
Which of the following is a reportable event? Select all that apply. BES Emergency requiring system-wide voltage reduction BES Emergency requiring public appeal for load reduction BES Emergency requiring manual firm load shedding Physical threats to a BES Control Center
All apply Feedback: Each of the answers would categorize as a reportable event if the threshold identified in Attachment 1 of EOP-004 were exceeded. For example: For a BES emergency requiring the manual shedding of firm load to be a reportable event, 100 MWs or more would have to be shed.
221
A Transmission Operator has experienced a loss of its ICCP communication, resulting in the inability to perform reliability analysis on its system. While in the process of implementing its Loss of Control Center Functionality plan, ICCP is restored. Which of the following statements is true? 15 continuous minutes or more If analysis capability was unavailable for more than 30 minutes, an event report must be submitted. The Transmission Operator should expect sabotage and implement its Operating Plan on event reporting. An event report is required regardless of the length of time the ICCP was unavailable. An event report would only be required if backup functionality could not be implemented in two (2) hours.
If analysis capability was unavailable for more than 30 minutes, an event report must be submitted. Feedback: EOP-004, Attachment 1: Reportable Events The reporting threshold for loss of monitoring capability affecting a control center such that analysis capability is rendered inoperable is 30 continuous minutes or more. There is not enough information to suspect sabotage
222
On Wednesday at 12:30 p.m., a Balancing Authority experiences partial separation of its area resulting in an island of 150 MWs. The Balancing Authority acts and reconnects his system within one hour. Is this a reportable event, and if so, how long does the Balancing Authority have to report the event to NERC? Since the Balancing Authority reconnected within one hour, it is not a reportable event. It is a reportable event and the Balancing Authority must report it to NERC by the end of the next business day, which would be Thursday at 4:00 p.m. local time. It is a reportable event and the Balancing Authority must report it to NERC within 24 hours of the event occurring., or by 12:30 Thursday. It is a reportable event and the Balancing Authority must report it to NERC within one hour.
It is a reportable event and the Balancing Authority must report it to NERC by the end of the next business day, which would be Thursday at 4:00 p.m. local time. Feedback: EOP-004, Attachment 1 Separation of part of the system resulting in islanding of 100 MWs or more is a reportable event regardless of how long the islanding lasts. R2: Each Responsible Entity shall report events specified in EOP-004-4 Attachment 1 to the entities specified per their event reporting Operating Plan by the later of 24 hours of recognition of meeting an event type threshold for reporting or by the end of the Responsible Entity’s next business day (4 p.m. local time will be considered the end of the business day).
223
Which of the following events would require an event report to be submitted in accordance with EOP-004, Attachment 1? Select the best answer. The sudden loss of a 600 MW generator. A loss of 110 MWs of firm load due to a bus fault. A sudden frequency drop of more than 1 Hz. An under-voltage event resulting in automatic load shed of 125 MWs.
An under-voltage event resulting in automatic load shed of 125 MWs. Feedback: EOP-004, Attachment 1: Reportable Events Loss of generation must exceed 1,000 MWs in ERCOT or 2,000 in the Eastern or Western Interconnections There is no reporting threshold on frequency. However, if part of the system separates into an island of 100 MWs or more, that would be reportable. A loss of firm load must be at least 200 MWs or 300 MWs, depending on the entities previous years' demand. Automatic or manual load shed of 100 MWs or more is reportable, regardless of the cause.
224
A Reliability Coordinator experiences an event requiring evacuation of the primary control center from 2100 to 2215 on Friday night. How long does the Reliability Coordinator have to report the event? Until the end of business the following Monday. Until 2100 Monday morning Within 24 hours No event report is required because the evacuation was less than 2 hours.
Until the end of business the following Monday. Feedback: EOP-004: Each Responsible Entity shall report events specified in EOP-004-4 Attachment 1 to the entities specified per their event reporting Operating Plan by the later of 24 hours of recognition of meeting an event type threshold for reporting or by the end of the Responsible Entity’s next business day (4 p.m. local time will be considered the end of the business day).
225
The Transmission Operator experiences an unexpected line outage which results in the subsequent loading of a parallel line at 101% of its SOL, what action should the Transmission Operator take? Select all that apply. Take the appropriate action to return the system to within normal limits Wait until load decreases Inform the Reliability Coordinator Open the overloaded line
Take the appropriate action to return the system to within normal limits Inform the Reliability Coordinator
226
A Generator Operator receives an Operating Instruction from its Transmission Operator to bring on additional generation to mitigate a low voltage situation. The Generator Operator must comply with the Operating Instruction unless: The operator is in the middle of shift turnover It has serious financial implications It results in safety concerns or environmental violations The Generator Operator disagrees with the Operating Instruction
It results in safety concerns or environmental violations
227
What is an Operating Instruction? A documented procedure or process for addressing an IROL exceedance Managers command to shed load Any conversation between two or more parties related to the reliability of the BES Real-time Operating personnel command to change or preserve the state of an element of the BES
Real-time Operating personnel command to change or preserve the state of an element of the BES
228
A Transmission Operator performs a Real-time Assessment that identifies a SOL exceedance. What should the Transmission Operator do next? Initiate its Operating Plan to mitigate the SOL exceedance Isolate the line with the exceedance Shed load required to return to the SOL limit Contact the Reliability Coordinator and ask for assistance
Initiate its Operating Plan to mitigate the SOL exceedance
229
Following a contingency or other event resulting in an Interconnection Reliability Operating Limit (IROL) violation, the Transmission Operator shall return to within the IROL as soon as possible, but no longer than ______. 60 minutes 15 minutes Its IROL Tv 30 minutes
Its IROL Tv
230
Unless it's an emergency, Transmission Operators should not remove Bulk Electric System facilities from service until which of the following actions is completed? A market benefit analysis is conducted A Real-time Assessment of the transmission facility outage is completed Additional operating reserves are requested A contingency plan is developed
A Real-time Assessment of the transmission facility outage is completed
231
Which of the following actions would a Transmission Operator be expected to take, or direct others to take, to mitigate SOL and IROL violations? Select all that apply. Change the output of generators Reduce Interchange Change limit Disconnect from neighbors Shed load
Change the output of generators Reduce Interchange Shed load
232
A transmission system must be operated so that which of the following will not occur as a result of a single contingency? Power swings Current overloads Transient instability Instability, uncontrolled separation, or cascading outages
Instability, uncontrolled separation, or cascading outages
233
Why is it necessary to report SOL and IROL exceedances to the Reliability Coordinator? To shift responsibility for fixing the issue to the Reliability Coordinator The Reliability Coordinator will then notify neighboring Reliability Coordinators to open various circuit breakers The Reliability Coordinator will then evaluate actions being taken and direct additional corrective actions as needed The Reliability Coordinator will then determine consequences and penalties for the exceedance
The Reliability Coordinator will then evaluate actions being taken and direct additional corrective actions as needed
234
A contingency results in the exceedance of an IROL. What could be the result if the IROL is allowed to be exceeded longer than its Tv? Interruption of power to a large part of the BES Failure of the transmission line Loss of power to a local area Voltage below its normal Operating range
Interruption of power to a large part of the BES
235
Reliability Coordinators and Transmission Operators are required to perform Real-time Assessments to ensure their system is being operated in an N-1 reliable state. How often must they perform a Real-time Assessment? At least once every 30 minutes At least once every 60 minutes At least once every 10 minutes There is no minimum time requirement
At least once every 30 minutes
236
A Transmission Operator has scheduled a short, temporary outage of the SCADA system for a software update at 22:00 tonight. Which of the following actions is required of the Transmission Operator? Notify the Reliability Coordinator and known impacted entities of the outage Request permission from NERC Operating Committee Request a level 1 Energy Emergency Alert Fully implement the Backup Control Center
Notify the Reliability Coordinator and known impacted entities of the outage
237
No IROL can have an IROL TV that exceeds __________? 30 minutes 15 minutes 90 minutes 60 minutes
30 minutes
238
A Transmission Operator notified the Generator Operator to change the MW output of their hydro plant to relieve an overloaded transmission line. That is an example of which of the following? Operating Instruction Operating Plan System Configuration Operating Directive
Operating Instruction
239
A Transmission Operator conducts a study that shows the power flow limit for Line Bravo is 450 MVA. The Reliability Coordinator's study shows that the line's limit is 480 MVA. What should the Transmission Operator do? Use the Transmission Operator's limit and conduct another study Use the Reliability Coordinator's limit and conduct another study Use the average of the two limits Take the line out of service until the difference can be resolved
Use the Transmission Operator's limit and conduct another study
240
To ensure reliability of the system and prevent a SOL exceedance, a generator is set to quickly and automatically reduce its output upon receiving indication of a transmission line trip. This would be an example of which of the following? Remedial Action Scheme (RAS) Generator Protection Relay (GPR) Relay Protection Scheme (RPS) Real-time Assessment Response (RAR)
Remedial Action Scheme (RAS)
241
Which of the following must a Transmission Operator monitor to determine SOL exceedances within its area? Select all that apply. BES Facilities within its TOP area Non-BES facilities within its TOP area identified as necessary Status, voltage, and flow data outside its TOP area identified as necessary Status of Remedial Action Schemes in its TOP area
BES Facilities within its TOP area Non-BES facilities within its TOP area identified as necessary Status, voltage, and flow data outside its TOP area identified as necessary Status of Remedial Action Schemes in its TOP area
242
Maintenance personnel inform you that insulator maintenance must be performed on a 230 kV line and the line must be deenergized to perform the maintenance. In the past, outages of this line on high load days have resulted in a SOL violation on your system. Whom must be informed of this outage? Your Reliability Coordinator and any Transmission Operators or Balancing Authorities that may be impacted by the outage. Only the Reliability Coordinator Only Transmission Operators or Balancing Authorities that are adjacent to your system Only Transmission Operators or Balancing Authorities that participate in the outage
Your Reliability Coordinator and any Transmission Operators or Balancing Authorities that may be impacted by the outage.
243
Which of the following is one thing a Balancing Authority must monitor to maintain balance within its area and support Interconnection frequency? Status of Remedial Action Schemes that impact generator or load All Interchange Transactions in the Reliability Control Area Available synchronous condensers Status of shunt capacitors
Status of Remedial Action Schemes that impact generator or load
244
A transmission line trip results in a SOL exceedance and the Transmission Operator implements the Operating Plan for the SOL. What should the Transmission Operator do next? Make a fresh pot of coffee File event report to NERC within 24 hours Update the map board Inform the Reliability Coordinator of actions taken
Inform the Reliability Coordinator of actions taken
245
Which of the following is an evaluation of projected system conditions to assess anticipated (pre-Contingency) and potential (post-Contingency) conditions for next-day operations, sometimes called a next-day study. Future Planning Assessment Real-time Assessment Real-time Monitoring Operational Planning Analysis
Operational Planning Analysis
246
When another Transmission Operator requests emergency actions to be implemented in your area, what is the expectation? You assist immediately without asking questions The requesting TOP has also implemented emergency actions Uncontrolled cascading outages are imminent The Reliability Coordinator must make the request
The requesting TOP has also implemented emergency actions
247
Which are the three types of limits to consider when determining system limits? Select all that apply. Thermal Angle stability Voltage Impedance
Thermal Angle stability Voltage
248
Transmission Operators, Balancing Authorities, Generator Operators, Distribution Providers, shall comply with Reliability Coordinator Operating Instructions unless such actions would violate which of the following? Regulatory, fair market, standard of conduct requirements Safety, profit, service requirements Equipment boundaries, past procedures Safety, equipment, regulatory requirements
Safety, equipment, regulatory requirements Feedback: Transmission Operators, Balancing Authorities, Generator Operators, Distribution Providers must comply with Reliability Coordinator Operating Instructions unless such actions would violate safety equipment, or regulatory or statutory requirements.
249
Which of the following are tasks of the Reliability Coordinator for its Reliability Coordinator Area? Determine most appropriate generation dispatch. Monitor System Facilities in its RC area and determine any SOL or IROL violations Operate reactive equipment to maintain voltages within limits Determine potential Interchange schedules.
Monitor System Facilities in its RC area and determine any SOL or IROL violations Feedback: A Reliability Coordinator monitors Bulk Electric System facilities and must be able to determine any potential System Operating Limit and Interconnection Reliability Operating Limit violation within its Reliability Coordinator Area and direct actions to mitigate limit exceedance. Bulk Electric System is defined as all equipment connected to 100 kV and above facilities. Reliability Coordinators would not monitor system facilities below 100 kV unless critical to system reliability.
250
If the power flow on the transmission system exceeds acceptable limits, which corrective action(s) can the Reliability Coordinator instruct a Balancing Authority to take? Shedding load Curtail schedules Re-dispatch generation, reduce interchange or shed load Re-dispatch generation
Re-dispatch generation, reduce interchange or shed load Feedback: Corrective Actions include: Re-dispatch generation which includes starting combustion turbines Curtailing schedules Shedding load
251
Each Reliability Coordinator shall have adequate analysis tools to monitor the Bulk Electric system, such as wide area overview displays, state estimation, and which other capabilities? Advanced security applications Newest version of its SCADA systems Contingency analysis capabilities NERC certified personnel
Contingency analysis capabilities Feedback: Wide-Area view is necessary for monitoring a Reliability Coordinator area and each Reliability Coordinator shall have adequate analysis tools; such as state estimation and contingency analysis capabilities (thermal, stability, and voltage) to be aware of what might happen in a pre- and post- contingency situation.
252
If a portion of a Reliability Coordinator Area is experiencing low voltage, which is an Operating Instruction the Reliability Coordinator may issue in this situation? Lower transfers across area and increase generation in area with low voltage. Increase transfers across area and decrease generation in area with low voltage. Lower transfers across area and decrease generation in area with low voltage. Increase transfers across area and increase generation in the RC area.
Lower transfers across area and increase generation in area with low voltage. Feedback: Low voltage is a result of insufficient reactive power and high losses associated with transferring power to load areas. Increasing generation in the area with low voltage reduces losses associated with transferring power. Starting generation will also increase the reactive power supply.
253
Which functional entity provides a big picture view of the power system and acts to address reliability in its area via direct action or by issuing commands? Transmission Operator Balancing Authority Reliability Coordinator Generator Operator
Reliability Coordinator Feedback: The Reliability Coordinator function was established to facilitate coordination and to provide entities with the "big picture" view of the system.
254
An Operating Procedure has been written to mitigate potential System Operating Limit violation on Sunflower 500 kV line. Real-time contingency analysis indicates that Sunflower line will exceed its SOL if the Seed line trips. Which of the below is the most appropriate next step for a Reliability Coordinator of Sunflower 500 kV line? Cancel outage of all transmission lines Discussion of projected loads. Issuing an Operating Instruction per the Operating Procedure Evaluating marketing activity.
Issuing an Operating Instruction per the Operating Procedure Feedback: Operating Procedure - A document that identifies specific steps or tasks that should be taken by one or more specific operating positions to achieve specific operating goal(s). The steps in an Operating Procedure should be followed in the order in which they are presented and should be performed by the position(s) identified. (NERC Glossary of Terms).
255
Reliability Coordinator A anticipates an overload of a high voltage transmission line that interconnects with Reliability Coordinator B's region. Reliability Coordinator A has a procedure on file that calls for Reliability Coordinator A to reduce Interchange Transactions to relieve the issue if it cannot be resolved within 15 minutes. What should Reliability Coordinator A do? Wait the 15 minute period then decide. Shed load. Immediately issue the TLR. Immediately contact Reliability Coordinator B to discuss options.
Immediately contact Reliability Coordinator B to discuss options. Feedback: Since this particular line is critical to the reliability of the Bulk Electric System in both regions, both Reliability Coordinator A and Reliability Coordinator B would immediately discuss the actions that needed to be taken. Regardless of the scenario, or situation, both Reliability Coordinators work very closely together in the resolution of a very potential problem.
256
A 500 kV tie-line between two Transmission Operators also crosses the boundary between two Reliability Coordinators. The substation at one end of the line is just within Reliability Coordinator A's area, while the other end is well within Reliability Coordinator B's area. This line often has voltage problems due to heavy unscheduled flow. Which of the following statements is most correct? The Reliability Coordinators should not be involved because the Transmission Operators are handling the voltage control. Both Reliability Coordinators should have Operating Procedures, processes, or Plans to address voltage control issues on the line. Reliability Coordinator B is responsible for directing voltage control for the line terminals. Reliability Coordinator A is responsible for directing voltage control for the line terminals.
Both Reliability Coordinators should have Operating Procedures, processes, or Plans to address voltage control issues on the line. Feedback: The Reliability Coordinator shall have Operating Procedures, Processes, or Plans in place for activities that require notification, exchange of information or coordination of actions with one or more other Reliability Coordinators to support Interconnection reliability. These Operating Procedures, Processes, or Plans shall address scenarios that affect other Reliability Coordinator Areas as well as those developed in coordination with other Reliability Coordinators. An area that must be addressed is Voltage control, including the coordination of reactive resources for voltage control.
257
Power flow studies conducted by a Reliability Coordinator identifies a planned and approved outage scheduled for later today will possibly cause a SOL violation. What action should the Reliability Coordinator take? Do not allow the outage to proceed. Contact the Outage Planning Coordinator and request permission to delay the outage. No action is necessary, since the next-day studies showed no problems with the outage. Allow the outage and monitor the SOL closely and be prepared to act if exceeded.
Do not allow the outage to proceed.
258
Reliability Analysis studies conducted by Reliability Coordinators should include planned outages. If a previously planned outage causes an issue for a neighboring Reliability Coordinator. What should the RC do? Shed load to tallow the outage to occur Proceed with the outage and notify the RC Discuss with impacted RC and postpone outage No action required
Discuss with impacted RC and postpone outage
259
Reliability Coordinator A has determined there is a problem in his area which requires action by Reliability Coordinator B. Both A and B have agreed upon the problem and solution. What should the Reliability Coordinators do next? Implement the agreed upon solution and notify the involved Reliability Coordinators. Reliability Coordinator A will document the action taken by Reliability Coordinator B. Document and solve the problem. Conference in all Reliability Coordinators,
Implement the agreed upon solution and notify the involved Reliability Coordinators. Feedback: The Reliability Coordinators must agree on the problem and actions to take to prevent or mitigate the problem and implement the agreed upon solution and ensure that the involved Reliability Coordinators are aware of the actions.
260
Studies show there will be an overloaded line on the transmission system in Reliability Coordinator A's area. Reliability Coordinator A has determined that the solution is for Reliability Coordinator B to open a low voltage transmission line in his area. Although Reliability Coordinator B shows that opening the low voltage line will not cause any other issues, he states that his preferred solution is for Reliability Coordinator A to remove the 345 kV transmission line from service. What is the best solution? Since they can NOT agree on the solution, the senior Reliability Coordinator determines the action to be taken. Since Reliability Coordinator A has the problem, his 345 kV line must be removed from service. Remove both lines from service Opening the low voltage transmission line.
Opening the low voltage transmission line. Feedback: If the involved Reliability Coordinators cannot agree on the solution, the more conservative solution shall be implemented.
261
What is a contingency? Unexpected failure of a system component. A change in electrical loading due to a generators output. An assessment of scheduled outages. A condition where resources are exhausted.
Unexpected failure of a system component.
262
What is generation shift factor? Percentage change of loading on transmission due to generator output changes. Percentage change of electrical loading on a line due to change in power transfers from one area to another. Percentage of change of electrical power transfer when a facility is removed from service. A coordinated action to prevent actual loading.
Percentage change of loading on transmission due to generator output changes.
263
Four parallel lines are loaded as indicated below. Line C has an OTDF of 0.3 for the loss of line D. A 50 MW B 200 MW C 200 MW D 200 MW If line D trips what will the loading be on line C? 300 MW 400 MW 240 MW 260 MW
260 MW Feedback: 200 x .3 = 60 plus the 200 already on Line C
264
What tool relies on the State Estimator? SCADA Energy Management System Contingency Analysis ACE
Contingency Analysis
265
An operational analysis indicates a line will overload if another line becomes de-energized. When developing the Operating Plan which actions should a system operator consider? Changing System Operating Limits. Request the Reliability Coordinator handle. Re-dispatch, reconfigure, reduce Don't allow the other line to become outaged.
Re-dispatch, reconfigure, reduce
266
What is Outage Transfer Distribution Factor? Percentage change of electrical loading on a line due to change in power transfers from one area to another. A coordinated action to prevent actual loading. Percentage of change of electrical power transfer when a facility is removed from service. Percentage change of loading on transmission due to generator output changes.
Percentage of change of electrical power transfer when a facility is removed from service.
267
What is Power Transfer Distribution Factor? Percentage change of electrical loading on a line due to change in power transfers from one area to another. A coordinated action to prevent actual loading. Percentage of change of electrical power transfer when a facility is removed from service. Percentage change of loading on transmission due to generator output changes.
Percentage change of electrical loading on a line due to change in power transfers from one area to another.
268
A Reliability Coordinator performs an Operational Planning Analysis for the next day, and studies indicate a scheduled outage will cause an SOL violation. What is the best course of action for the system operator? Deny all requests submitted within that short time frame. Inform the Transmission Operator and delay the decision to approve the outage. Reschedule the outage for a later date. Approve the outage with the understanding the line cannot be out during peak.
Reschedule the outage for a later date.
269
If an Operational Planning Analysis or a Real-time assessment indicates a potential emergency, what is the system operator's first action? Check targets Shed load Let the Reliability Coordinator come up with a plan Develop an Operating Plan to mitigate the emergency
Develop an Operating Plan to mitigate the emergency
270
System operators are responsible for actual and expected system conditions. This responsibility is accomplished by performing which of the following? Real-time assessments Real-time contingency analysis Communication with Reliability Coordinator All the above
All the above
271
What is a Transmission Loading Relief? A coordinated effort to ensure energy emergencies will not occur A coordinated action to prevent actual loading A process to reduce market activities A process identified by each Interconnection to relieve loading on the transmission system caused by power transfers across areas
A process identified by each Interconnection to relieve loading on the transmission system caused by power transfers across areas
272
After a disturbance on the system, a Balancing Authority Area experiences a tie-line loading up. What action should the Balancing Authority take? Shed load Re-dispatch Generation Bring on generation Contact their Reliability Coordinator and discuss mitigation options.
Contact their Reliability Coordinator and discuss mitigation options. Feedback: The question does not indicate the direction of power flow or if this is the deficient Balancing Authority. Therefore, you cannot assume that bringing on generation will help. It may further load the transmission line.
273
Transmission Operators perform Operational Planning Analysis to study next day operations. The results inform the Transmission Operator of which two parameters? Select all that apply. Ensure capacity and energy deficiency. Ensure real and reactive resources are sufficient to meet demands. Identify potential SOLs. Identify potential misoperation.
Ensure real and reactive resources are sufficient to meet demands. Identify potential SOLs. Feedback: An Operational Planning Study must be completed so each Transmission Operator can assess whether the planned actions for the next-day will exceed any of its SOLs. The study will also ensure real and reactive resources are sufficient to meet demands.
274
The goal or purpose of Transmission Operations standards is to ensure Transmission Operators and Balancing Authorities operate within specified limits. The Balancing Authority meets its demand and energy requirements and the Transmission Operator maintains system operating limits in the normal operating range. What should a system operator do when studies indicate limits will be exceeded? Request a mitigating plan from the Reliability Coordinator. Plan to have more reserves. Create Operating Plans that will mitigate the predicted issues. Change the system model.
Create Operating Plans that will mitigate the predicted issues. Feedback: An Operating Plan is required to be created to document the identified group of activities that may be used to achieve some goal. An Operating Plan may contain Operating Procedures and Operating Processes. The plan will require a strategy and coordinator among the impacted entities
275
The Transmission Operator uses the results of the Operational Planning Analysis to determine SOL exceedances. What action would the Transmission Operator perform when the study results in potential SOL exceedance? Mitigate within the next 60 minutes Determine testing schedule Shed load Create an operating plan
Create an operating plan Feedback: The Transmission Operator should specify the data needed to have sufficient information and analysis to determine the cause(s) of SOL violations. This analysis shall be conducted in all operating time frames. The Transmission Operator shall use the results of these analyses to immediately mitigate the SOL violation.
276
A Balancing Authority maintains generation-interchange-load balance for their Balancing Authority Area. How does the Balancing Authority ensure that SOLs are not exceeded? Increase limits based on needs. Ensure generator resources are sufficient to meet demand. Set generation at maximum output. Do not allow unscheduled power flow.
Ensure generator resources are sufficient to meet demand. Feedback: Each Balancing Authority shall notify entities identified in the Operating Plan(s) that address expected generation resource commitment and dispatch, Interchange scheduling, Demand patterns, and capacity/energy reserve requirements as to their role in those plan(s).
277
Operational Planning Analyses were conducted with no reliability issues. An unplanned outage of a transmission line occurs during your shift. As the Transmission Operator which of the following actions would you take first? Create a procedure Perform a Real-time assessment Perform evasive maneuvers Inform impacted entities
Perform a Real-time assessment Feedback: Operational Planning Analysis is an evaluation of projected system conditions to assess anticipated (pre-Contingency) and potential (post-Contingency) conditions for next-day operations. Real-time Assessment is also an evaluation of system conditions using Real-time data to assess existing (pre-Contingency) and potential (post-Contingency) operating conditions. A TOP would need to perform future analysis or current assessments of current conditions.
278
When a transmission line trips, the power flow on that line will be reflected in other transmission lines and equipment. To ensure that the redistribution of power flowing on the remaining elements will not result in further uncontrolled outages and possible cascading outages, system operators should plan on mitigating the consequences of possible contingencies. What method is used to ensure reliability of the power system will be maintained after a contingency? Interconnection agreements Operational Planning Analysis Real-time monitoring Seasonal studies
Operational Planning Analysis Feedback: Operational Planning Analysis is an evaluation of projected system conditions to assess anticipated (pre-contingency) and potential (post-contingency) conditions for next-day operations. The evaluation shall reflect applicable inputs including, but not limited to, load forecasts, generation output levels, Interchange, know Protection System and Special Protection System status or degradation, transmission outages, generator outages, Facility Ratings, and identified phase angle and equipment limitations.
279
The Transmission Operator has written an Operating Plan as a result of a situation identified in their Operational Planning Analysis. Which entities must be notified of the Operating Plan? Reliability Coordinators Information System (RCIS) Entities that have a role in utilizing the plan and the Reliability Coordinator. Operational personnel. NERC Certified System Operators
Entities that have a role in utilizing the plan and the Reliability Coordinator. Feedback: Each Transmission Operator shall notify entities identified in the Operating Plan(s) developed as to their role in those plans as well as the Reliability Coordinator.
280
The Balancing Authorities' Operational Plan for the next day shall include the demand patterns as well as which of the following to ensure capacity and energy reserve requirements? Select all that apply. Control Performance Standard Generation resource commitments Interchange schedules Frequency response expectations
Generation resource commitments Interchange schedules Feedback: Generation resources commitment and dispatch, Interchange schedules, demand pattern, and capacity and energy reserve requirements all must be included in the next day operating plans.
281
In how many minutes must a Transmission Operator return its transmission system to within its IROL or risk uncontrolled and cascading outages? 30 minutes 15 minutes 10 minutes 60 minutes
30 minutes Feedback: A N-1 Contingency will be part of the study process to Identify that following and unplanned outage or other event that may result in a System Operating Limit (SOL) or Interconnection Reliability Operating Limit (IROL) violation. If a SOL or IROL exceedance occurs then the Transmission Operator must return its transmission system to within IROL as soon as possible, but no longer than 30 minutes.
282
Which type(s) of power transformers are affected by GMDs? Direct current (DC) transformers Delta connected transformers Wye connected transformers Generator step-up transformers
Wye connected transformers Feedback: GICs enter a transformer through its ground connection, producing an off-setting DC excitation current. Delta connected transformers do not have a ground connection and therefore are not susceptible to GICs.
283
GMDs have the potential to affect the bulk power system. Which of the following phenomenon produces an effect on the system? The Northern Lights Geomagnetically Induced Radiation Excessive Reactive Power Geomagnetically Induced Currents
Geomagnetically Induced Currents Feedback: Geomagnetically Induced Currents (GICs) caused by Earth Surface Potentials (ESP) can enter the power system through grounded connections, causing an effect on the power system. Note: GMDs and the GICs they produce can cause a loss of Reactive Power, not an excess.
284
Which of the following would you most likely experience during a GMD event? Heavier than normal MW flow on transmission lines Overheating in some transformer cores Tripping of online generating units Excessive reactive power resulting in high voltages
Overheating in some transformer cores Feedback: Wye-connected transformers are susceptible to Geomagnetically Induced Currents (GICs) entering through the grounded connections. These currents can result in saturation of the transformer core causing excessive heating. EOP-010 is only applicable to Reliability Coordinators and Transmission Operators with transformers with a high side wye-grounded winding greater than 200 kV.
285
The NOAA Space Weather Geomagnetic Storm Scale, or G-Scale ranges from G-1 to G-5. Which of the following is(are) possible during a G-5 GMD storm? Select all that apply. Transformer damage Protective system problems Widespread voltage control problems System collapse or blackout
All apply Feedback: In a severe GMD, all of the conditions listed could occur.
286
EOP-010, Geomagnetic Disturbance Operations, is applicable to Reliability Coordinators and Transmission Operators whose area includes which of the following? Select the best answer. Transformer(s) with high side wye-grounded winding 100 kV and above Wye-grounded generators with terminal voltage 100 kV and above Any grounded equipment Transformer(s) with high side wye-grounded winding 200 kV and above None of the above
Transformer(s) with high side wye-grounded winding 200 kV and above Feedback: EOP-010, Applicability 4.1. Functional Entities: 4.1.1 Reliability Coordinator 4.1.2 Transmission Operator with a Transmission Operator Area that includes a power transformer with a high side wye-grounded winding with terminal voltage greater than 200 kV
287
Which of the following are recommended mitigating strategies to be considered when developing a GMD Operating Procedure or Process? Select all that apply. Isolate equipment susceptible to damage, such as transformers Operate generators at maximum real and reactive power output Start off-line generation and/or return outage equipment to service Remove grounds from all grounded equipment Reduce system voltage to allow transformers to operate further from saturation
Isolate equipment susceptible to damage, such as transformers Start off-line generation and/or return outage equipment to service Reduce system voltage to allow transformers to operate further from saturation Feedback: Starting off-line generation and returning outage equipment to service, reducing system voltage to allow transformers to operate further from saturation, and isolating equipment susceptible to damage are all strategies that should be considered when developing a GMD Operating Procedure or process based on your geographic location and system characteristics. Operating generators at maximum Real and Reactive Power output is not a strategy to consider when developing a GMD Operating Procedure or Process. Removing grounds from all grounded equipment is not a feasible option.
288
Which Registered Entity is responsible for disseminating space weather information to the entities identified in their GMD operating plan? The Balancing Authority The Generator Operator The Transmission Operator The Reliability Coordinator
The Reliability Coordinator Feedback: EOP-010 states the Reliability Coordinator is responsible for disseminating space weather information to all entities identified in their GMD Operating Plan. This standard is only applicable to Reliability Coordinators and select Transmission Operators.
289
Which of the following is NOT a requirement of the Reliability Coordinator concerning GMDs? Coordinate the GMD Operating Procedures of Transmission Operators in their area Disseminate information concerning GMDs to entities in the Reliability Coordinator's Operating Plan Identify conflicts in their area's Transmission Operator plans Specify actions to be included in the Transmission Operator's GMD Operating Procedures
Specify actions to be included in the Transmission Operator's GMD Operating Procedures Feedback: Reliability Coordinators are responsible for coordinating the GMD Operating Procedures of the Transmission Operators, disseminating information concerning GMDs to entities, and identifying conflicts in their area's Transmission Operators plans. They are not responsible for specifying actions to be included in the Transmission Operators GMD Operating Procedures.
290
K-index is a measure of the intensity of geomagnetic activity. The electrical power system is typically not affected until the K-index reaches what level? K-7 or higher K-100 or higher K-4 or higher All K-Index levels
K-7 or higher Feedback: Most electrical power systems are not affected by geomagnetic activity level below K-7.
291
According to EOP-010, which of the following must be included in the Transmission Operator's GMD Operating Procedure or Process? Select all that apply. Define steps or tasks on receiving space weather information Disseminating space weather information Identifying conflicts with their Reliability Coordinators Operating Plans Actions to be taken by System Operators based on predetermined conditions Conditions for terminating the Operating Procedure or Process
Define steps or tasks on receiving space weather information Actions to be taken by System Operators based on predetermined conditions Conditions for terminating the Operating Procedure or Process Feedback: EOP-010 is also applicable to Transmission Operators with a Transmission Operator Area that includes a power transformer with a high side wye-grounded winding with terminal voltage greater than 200 kV. If a Transmission Operator falls into this category, they are required to develop, maintain, and implement a GMD Operating Procedure or Operating Process to mitigate the effects of GMD events on the reliable operations of their respective system. The procedure or process must include at least the following: Defined steps or tasks on receiving space weather information Actions to be initiated by System Operators based on predetermined conditions for terminating the Operating Procedure or Operating process This requirement allows each Transmission operator to design procedures or processes based on their assessment of entity-specific factors, such as geography, geology, and topology.
292
Geomagnetically Induced Currents enter the Bulk Power System through __________ equipment. isolated grounded rotating shielded
grounded Feedback: Geomagnetically Induced Currents (GICs) enter the bulk power system through grounded equipment when the impedance of the earth is higher than the impedance of the transmission line. While they may cause some equipment to become isolated, they do not enter the power system through isolated equipment. The most common point to see GICs entering the power system are through Wye connected transformers.
292
An Operating Plan is a document that identifies a group of activities that may be used to achieve some goal. An Operating Plan may contain Operating Procedures and Operating Processes. Which of these is a company-specific example of an Operating Plan that would need procedures and process to support the plan? Personnel readiness Control Center ergonomics System Restoration Under frequency operations
System Restoration Feedback: A document that identifies a group of activities that may be used to achieve some goal. An Operating Plan may contain Operating Procedures and Operating Processes. A company-specific system restoration plan that includes an Operating Procedure for black-starting units, Operating Processes for communicating restoration progress with other entities, etc., is an example of an Operating Plan.
292
What should a Transmission Operator and Balancing Authority do to address the effects of operating situations and mitigate operating emergencies? Request Operating Time-out until a strategy can be developed Disconnect from impacted areas Develop an operating plan Maintain communication
Develop an operating plan Feedback: To address the effects of operating Emergencies by ensuring each Transmission Operator and Balancing Authority has developed Operating Plan(s) to mitigate operating Emergencies, and that those plans are coordinated within a Reliability Coordinator Area.
293
Which of the following would constitute an emergency condition? Select all that apply. System Operating Limit (SOL) exceedance System Restoration Capacity deficiency Failure of Alternative Interpersonal Communication capability
System Operating Limit (SOL) exceedance System Restoration Capacity deficiency Feedback: All selections except failure of Alternative Interpersonal Communication Equipment would be considered an operational emergency. Per COM-001, Alternative Interpersonal Communication Equipment must be tested monthly, and if found to be inoperative, replaced or repaired within two hours, but this would not be considered an operational emergency.
293
State the elements needed in a Transmission Operator's Operating Plan and a Balancing Authority's Operating Plan and why the Reliability Coordinator must review the Operating Plans in its area. 1) Notifications 2) Process to mitigate Emergencies 3) Role and Responsibilities 1 and 2 are needed in an Operating Plan and the Reliability Coordinator will review for wide are reliability 1, 2, 3 are needed in an Operating Plan and the Reliability Coordinator will approve each step 1, 2, 3 are needed in an Operating Plan and the Reliability Coordinator will review for compatibility and inter-dependency and coordination 1 and 3 are needed in an Operating Plan and the Reliability Coordinator will review for completeness
1, 2, 3 are needed in an Operating Plan and the Reliability Coordinator will review for compatibility and inter-dependency and coordination Feedback: The Reliability Coordinator shall review the Operating Plan(s) to mitigate operating Emergencies submitted by a Transmission Operator or a Balancing Authority regarding any reliability risks that are identified between Operating Plans. The Reliability Coordinator will review each submitted Operating Plan(s) on the basis of compatibility and inter-dependency with other Balancing Authorities’ and Transmission Operators’ Operating Plans and review each submitted Operating Plan(s) for coordination to avoid risk to Wide Area reliability.
293
Reliability impacts have been evaluated and mitigation plans have been developed by the Transmission Operator and reviewed by the Reliability Coordinator. The Reliability Coordinator notices that the contingent conditions exist as stated in S-O-P-14. Who should activate the System Operating Plan? The Reliability Coordinator always activates Operating Plans The author of the Operating Plan must initiate the plan Role and responsibilities for activating the Operating Plan should be identified in document S-O-P 14. Anyone can initiate an Operating plan for emergency conditions
Role and responsibilities for activating the Operating Plan should be identified in document S-O-P 14. Feedback: Each Transmission Operator shall develop, maintain, and implement one or more Reliability Coordinator-reviewed Operating Plan(s) to mitigate operating Emergencies in its Transmission Operator Area, including Roles and responsibilities for activating the Operating Plan(s)
294
A Balancing Authority Area is facing extreme cold weather conditions and their load is tracking 1000 MW higher than previously planned. If load reaches 11,000 MW, the BA will have all available resources committed. What should the Balancing Authority consider doing prior to reaching the peak? Discuss with the Reliability Coordinator and initiate an Energy Emergency Alert Level 2 Discuss with the Reliability Coordinator and initiate an Energy Emergency Alert Level 3 Discuss with the Reliability Coordinator and initiate an Energy Emergency Alert Level 1 Discuss with the Reliability Coordinator and wait until the peak hour to issue any Alerts
Discuss with the Reliability Coordinator and initiate an Energy Emergency Alert Level 1 Feedback: Energy Emergency Alerts should be issued when the Balancing Authority realizes that all their resources are committed to native load. While they may still have resources, the Balancing Authority is one contingency away from having to use their reserves and possible Shed Load. The Reliability Coordinator will assist the Balancing Authority by declaring the Energy Emergency Alert and looking for reserves within its area.
294
The primary function of each Balancing Authority is meeting generation-load-interchange balance. Capacity Emergencies and Energy Emergencies are emergency conditions that require an Operating Plan with what purpose? Energy Emergency Alerts is a transmission system process to relief system operating limit exceedances. Energy Emergency Alerts is an Operating Process to maintain generation-load balance in emergency conditions. Energy Emergency Alerts is controlled by the Balancing Authority to request load shed. Energy Emergency Alerts should be used in consecutive order to alert the Interconnection.
Energy Emergency Alerts is an Operating Process to maintain generation-load balance in emergency conditions. Feedback: Attachment 1 - EOP-011 provides the process and descriptions of the levels used by the Reliability Coordinator in which it communicates the condition of a Balancing Authority which is experiencing an Energy Emergency.
295
What would a Balancing Authority experiencing an operational energy or capacity emergency expect from the Reliability Coordinator after contacting their Reliability Coordinator? The Reliability Coordinator will issue Operating Instructions to the Load Serving Entity to reduce load The Reliability Coordinator will declare the Energy Emergency Alerts and obtain assistance The Reliability Coordinator will curtail all sales out of its area The Reliability Coordinator will instruct all their BA to shed load pro-rata
The Reliability Coordinator will declare the Energy Emergency Alerts and obtain assistance Feedback: Each Reliability Coordinator that has a Balancing Authority experiencing a potential or actual Energy Emergency within its Reliability Coordinator Area shall declare an Energy Emergency Alert. The Balancing Authority will discuss their emergency situation and have Operating Plans for Energy Emergencies in place. The Reliability Coordinator will assist the Balancing Authority and request assistance as needed from other Balancing Authorities and Transmission Operator in their Reliability Coordinator Area and neighboring Reliability Coordinators.
296
A Balancing Authority experiences generators that become unavailable to start -up due to fuel shortages. When a large generator trips the Balancing Authority reaches out to its Reliability Coordinator. What would the Reliability Coordinator next actions include? The Reliability Coordinator will issue a TLR as soon as possible The Reliability Coordinator will notify the Balancing Authorities and Transmission Operators within its RC Area within 30 minutes The Reliability Coordinator will notify the Balancing Authorities and Transmission Operators within its RC Area within an hour The Reliability Coordinator will notify neighboring Reliability Coordinators as needed.
The Reliability Coordinator will notify the Balancing Authorities and Transmission Operators within its RC Area within 30 minutes Feedback: Each Reliability Coordinator that receives an Emergency notification from a Transmission Operator or Balancing Authority within its Reliability Coordinator Area shall notify, within 30 minutes from the time of receiving notification, other Balancing Authorities and Transmission Operators in its Reliability Coordinator Area, and neighboring Reliability Coordinators.
297
Several lines have tripped due to a weather event. The remaining lines are heavily loaded, and voltage is 90% and dropping. Which emergency actions should a System Operator consider to mitigate further voltage decay on the power system? Issue an Energy Emergency Alert Shed Load to reduce flow on heavily loaded lines Issue a Voltage Reduction to reduce load Shed Load evenly in your Balancing Area
Shed Load to reduce flow on heavily loaded lines Feedback: Each Transmission Operator shall develop, maintain, and implement one or more Reliability Coordinator-reviewed Operating Plan(s) to mitigate operating Emergencies in its Transmission Operator Area. Load Shedding tools and when to use them would be part of the Operating Plan to mitigate a low voltage situation.
298
Transmission Operators must participate in the Reliability Coordinator's restoration drills, exercises, and/or simulations ________________. quarterly semi-annually annually as requested none of the above
as requested Feedback: EOP-005, R12: Each Transmission Operator shall participate in its Reliability Coordinator's restoration drills, exercises, or simulations as requested by its Reliability Coordinator.
299
Which is NOT a verification method Transmission Operators use to ensure that the System Restoration Plan accomplishes the intended function? Through Contingency Analysis By analyzing actual events By testing Dynamic state simulation With simulation
Through Contingency Analysis Feedback: EOP-005, R6: Each Transmission Operator must verify through analysis of actual events, steady state and dynamic simulations, or testing, that the System Restoration Plan accomplishes the intended function. This verification is to be completed at least once every five (5) years at a minimum.
300
It is the responsibility of the __________ to have a restoration plan for restoring its system following a Disturbance in which one or more areas of the Bulk Electric System (BES) shuts down and the use of Blackstart Resources is required to restore the shutdown area to service. NERC Regional Reliability Organization (RRO) Balancing Authority (BA) Transmission Operator (TOP)
Transmission Operator (TOP) Feedback: EOP-005, R1: Each Transmission Operator is required to have a dated and documented System Restoration Plan, approved by its Reliability Coordinator, to re-establish its electric system in a stable and orderly manner in the event of a partial or total shutdown of its system.
301
How often must a System Restoration Plan be reviewed? Annually As needed Every 6 months Every 2 years Quarterly
Annually Feedback: EOP-005, R3: Each Transmission Operator is required to review their restoration plan and submit it to their Reliability Coordinator annually on a mutually agreed upon schedule. If there are no changes to the previous restoration plan, then the Transmission Operator only needs to confirm annually, on a predetermined schedule, with the Reliability Coordinator that it has been reviewed.
302
To assure the proper execution of the System Restoration Plan, each Transmission Operator must provide a training program for their System Operators with annual training material that includes ______. Select all that apply. Restoration priorities The System Restoration Plan building of cranking paths Synchronizing
All apply Feedback: EOP-005, R10: to assure the proper execution of the System Restoration plan, each Transmission Operator must provide a training program for their System Operators. The annual training material must include: The System Restoration Plan, including coordination with the Reliability Coordinator and the Generator Operators included in the restoration plan Restoration priorities Building cranking paths Synchronizing (the re-energized sections of the System)
303
Each Generator Operator with a Blackstart Resource shall notify its Transmission operator of any known changes to the capabilities of that Blackstart Resource affecting the ability to meet the Transmission Operator's restoration plan within one hour following such change. True False
False Feedback: EOP-005, R15: Each Generator Operator with a Blackstart Resource shall notify its Transmission Operator of any known changes to the capabilities of that Blackstart Resource affecting the ability to meet the Transmission operator's restoration plan within 24 hours following such change.
304
In the event of a partial or total shutdown of its system, it is important for each Reliability Coordinator to have a __________ restoration plan in place to reestablish its electric system in a stable and orderly manner. Reliability Coordinator Area Regional outage Distribution outage All of the above
Reliability Coordinator Area Feedback: EOP-006, R1: In the event of a partial or total shutdown of its system, it is important for each Reliability Coordinator to have a Reliability Coordinator Area restoration plan in place to reestablish its electric system in a stable and orderly manner. The restoration plan must include operating instructions and procedures to cover emergency conditions and the loss of vital telecommunications channels. The scope of the Reliability Coordinator's restoration plan should begin when Blackstart Resources are utilized to re-energize a shutdown area of the Bulk Electric System (BES) or when a separation has occurred between neighboring Reliability Coordinators, or an energized island has been formed on the BES within the Reliability Coordinator Area. The scope should end when all of its Transmission operators are interconnected, and the Reliability Coordinator's Area is once again connected with all of its neighboring Reliability Coordinator Areas.
305
Each Reliability Coordinator must review its neighboring Reliability Coordinator's restoration plan (s) to ensure there are no conflicts between its restoration plan and any of its neighbors. If a conflict is found, the conflict must be resolved within ______ calendar days. 15 30 60 7
30 Feedback: EOP-006, R4: Each Reliability Coordinator must review its neighboring Reliability Coordinator's Restoration Plan(s) to ensure there are no conflicts between its restoration plan and any of its neighbors. On the occasion a conflict is found, the conflict must be resolved within thirty (30) calendar days.
306
Within 30 calendar days of creation or revision, the Reliability Coordinator must distribute its most recent Reliability Coordinator Area Restoration Plan to all of the following EXCEPT ... Its Transmission Operators Its neighboring Reliability Coordinators Its Balancing Authority None of the above
Its Balancing Authority Feedback: EOP-006, R2: The Reliability Coordinator shall distribute its most recent Reliability Coordinator Area restoration plan to each of its Transmission Operators and neighboring Reliability Coordinators within 30 calendar days of creation or revision.
307
The Reliability Coordinator's restoration plan must include... Select the best answer. A high level strategy for restoring the Interconnection Operating processes for restoring the Interconnection Coordination with Transmission Operators and their Restoration Plans All of the above None of the above
All of the above Feedback: EOP-006, R1: The Reliability Coordinator's Restoration Plan must include the following elements: A high- level strategy for restoring the Interconnection Operating processes for restoring the Interconnection Coordination with Transmission Operators and their restoration plans Coordination with neighboring Reliability Coordinators and their restoration plans Criteria and conditions for reestablishing interconnections with Transmission Operators and Reliability Coordinators in their own area as well as in other Reliability Coordinator's Area. Reporting requirements for entities within the areas during a restoration event Criteria for sharing information with neighboring Reliability Coordinators, Transmission Operators, and Balancing Authorities in its area Identification of the Reliability Coordinator as the primary contact for disseminating restoration information within its area and in neighboring areas Criteria for transferring operations and authority back to the Balancing Authority
308
Each Reliability Coordinator shall include within its operations training program ____________ for its System Operators to assure the proper execution of its restoration plan. annual System Restoration training a fiscally responsible meal plan simulation drills All of the above None of the above
annual System Restoration training Feedback: EOP-006, R9: Each Reliability Coordinator shall include within its operations training program, annual System Restoration training for its System Operators to assure the proper execution of its restoration plan.
309
Each Reliability Coordinator shall conduct ___________ System Restoration drill(s), exercise(s), or simulation(s) per calendar year; one two twelve four
two Feedback: EOP-006, R 10: Each Reliability Coordinator shall conduct two System Restoration drills, exercises, or simulations per calendar year. This shall include the Transmission Operators and Generator Operators as dictated by the particular scope of the drill, exercise or simulation that is being conducted.
310
Many possible scenarios could cause the control center to become inoperable. Which of the following would be likely to cause the Operating Plan for backup functionality to be implemented? Hurricane Loss of total ICCP communication Fire All the above
All the above Feedback: EOP-008, R1: Possible scenarios which may result in the implementation of an Operating Plan for backup functionality include fire alarm or fire, bomb threat or detonation, biohazard warning or incident, civil unrest development or occurrence, or adverse weather conditions. Total loss of ICCP communication would render the ability to monitor and perform analysis on the system for reliability purposes and would constitute implementing the Operating Plan as well.
311
Each entity must have primary and backup functionality that are independent of each other for the control center functionality required to maintain compliance with Reliability Standards. True False
True Feedback: EOP-008: Each entity must have primary and backup functionality that do not depend on each other for the control center functionality required to maintain compliance with Reliability Standards.
312
EOP-008 requires certain Reliability Entities to have an Operating Plan for backup functionality in the event the primary control center functionality is lost. Which of the following is(are) required to be part of that plan? Select all that apply. A summary description of elements required for backup functionality An Operating Process describing actions to be taken during the transition period Location and method of implementation Operating Procedures for determining when to implement the Operating Plan for backup functionality
All apply Feedback: EOP-008, R1.2: In many scenarios, data and communications infrastructure may remain functional; however, the Operating Plan for backup functionality must include a summary description of the elements required to support backup functionality, including: Tools and applications to ensure that System Operators have situational awareness of the BES Data communications Voice communications Power source(s) Physical and cyber security
313
Where must each entity have a copy of its current Operating Plan for backup functionality available? Select all that apply Substation Neighboring Transmission Operator's facility Location providing backup functionality Primary Control Center
Location providing backup functionality Primary Control Center Feedback: EOP-008, R2: each RC, BA, and TOP shall have a copy of its current Operating Plan for backup functionality available at its primary control center and at the location providing backup functionality.
314
How often must a Reliability Coordinator review and update their backup functionality Operating Plan? Annually Only when changes are made Every quarter Semi-annually
Annually Feedback: EOP-008, R5: Each Reliability Coordinator, Balancing Authority, and Transmission Operator shall annually review and approve its Operating Plan for backup functionality. 5.1. An update and approval of the Operating Plan for backup functionality shall take place within sixty calendar days of any changes to any part of the Operating Plan described in Requirement R1.
315
Each Balancing Authority and Transmission Operator must have backup functionality sufficient for maintaining compliance with all Reliability Standards that include which elements? Select the best response. Monitoring, reporting, repairing, and alarming Monitoring, control, logging, and alarming Monitoring, logging, and restructuring Monitoring, reporting, logging, and alarming
Monitoring, control, logging, and alarming Feedback: EOP-008, R4: Each Balancing Authority and Transmission Operator must have backup functionality that includes monitoring, control, logging, and alarming.
316
Why do geomagnetic storms pose a threat to the power system? Geomagnetic induced current enter the power system and cause abnormal operations Geomagnetic storms do not threaten the reliability of the power system Geomagnetic induced currents distort the data the SCADA system reads Weather events threaten physical power system structures
Geomagnetic induced current enter the power system and cause abnormal operations Feedback: GICs are primarily direct current induced in the AC system, distorting the magnetic characteristics. GICs enter the power grid through the grounded of a transformer's why side when the impedance of the ground is higher than the impedance of the transmission line, since current flow follows the path of least impedance. High voltage transmission systems have low impedance which allows the GIC flow on the system to increase.
317
System restoration plans must be thought out and methodical for which purpose? Determine new operating parameters Provide warning signs to prevent disturbances Protect the Energy Management System from failure Enable personnel to effectively coordinate and re-establish the interconnection
Enable personnel to effectively coordinate and re-establish the interconnection Feedback: Restoration plans must be established. These plans prepare personnel for effective coordination of the system restoration process. The goal is to methodically restore the power system and re-establish the Interconnection.
318
When an emergency condition occurs in real-time or is predicted to occur due to a contingency, what is the first thing a system operator should do? Shed load Redispatch Contact the Reliability Coordinator Develop an Operating Plan to mitigate the emergency
Develop an Operating Plan to mitigate the emergency Feedback: To maintain reliability the system operator should evaluate system conditions and develop an operating plan when they perform mitigating actions. The operating plan should include notifications, roles and responsibilities, and actions to be performed.
319
Each Transmission Operator and Balancing Authorities determine which Operating Plans need to be developed based on what information? Current or pre-determined operating situation that create a reliability concern Cancellation of transmission outages Reliability Coordinator direction Voice recordings
Current or pre-determined operating situation that create a reliability concern Feedback: Transmission Operator and Balancing Authorities develop operating plans to mitigate emergencies. The Reliability Coordinator reviews the plan.
320
An analysis is conducted to ensure generation will meet expected loads even if a generator trips off line. If sufficient generation is not available to meet load and reserves requirement, what is Balancing Authority's situation? Balancing authority ACE limits are exceeded System Operating Limits are exceeded Capacity and Energy Emergencies Real-time contingency analysis
Capacity and Energy Emergencies Feedback: The responsibility of the Balancing Authority is to meet load with sufficient generating resources for normal operations or in the event a generator trips, i.e. reserves. If they cannot meet load they are in a Capacity and Energy Emergency.
321
Exceeding System Operating Limits during power system operations ____________. Decreases the need for load shed Decreases the risk to the power supply Increases the risk to power system reliability Increases load demand
Increases the risk to power system reliability Feedback: System Operating Limits should not be exceeded. If limits are exceeded the power system is operating in a less reliable state.
322
What must be issued when working in a rapidly changing environment and action must be taken that changes the state of equipment? Operating instructions GMD Discussion EOP
Operating instructions Feedback: During emergency conditions, a system operator may need to issue operating instructions. An operating instruction is a command by operating personnel responsible for the Real-time operation of the interconnected BES to change or preserve the state, status, output, or input of an element or facility of the BES.
323
Loss of a primary control center functionality triggers which emergency situation? Real-time monitoring and assessment Establish backup control center to continue to meet functional obligation and operations Blackouts No real-time contingency analysis
Establish backup control center to continue to meet functional obligation and operations Feedback: Backup control centers are established to ensure continued reliable operation of a control center becomes inoperable. Evacuating the primary control center and resuming operations at the backup center are considered emergency operations.
324
Load Shed programs are available and should be used in which emergency condition? Large power transfers result in a contingency overload Heavy flows to inductive loads are causing voltage drops in excess of 10% A generator trips during peak summer conditions Transmission line is at 95% loading
Heavy flows to inductive loads are causing voltage drops in excess of 10% Feedback: Load shed is used after other options such as redispatch or reduction in interchange are used.
325
What equipment produces reactive power to counter the effects of inductive load? Loads Capacitors Protective relays Reactors
Capacitors Feedback: Voltage control equipment such as capacitors counteract the effects of inductive loads by producing reactive power and supporting voltage.