A transformer has a .8 or 80% power factor and has 150 MW flowing out on its high
side. How many MWs are flowing into the low side?
a. 187.5 MW
b. 150 MW
c. 120 MW
d. 37.5 MW
b. 150 MW
Your frequency bias is -100 MW / .1Hz. System frequency is 59.95. How much is your
balancing authority contributing to the Interconnection.
a. 100 MW
b. 75 MW
c. 50 MW
d. 30 MW
c. 50 MW
A fault has occurred in your power system. What will the System Operator look for?
a. A condition where a component is not in sync with the rest of the system
b. A condition that causes a device, component, or element to fail
c. A condition of abnormal electric current
d. A condition of abnormal electric current which causes protective relays to operate
d. A condition of abnormal electric current which causes protective relays to operate
What makes up spinning reserves?
a. Generators
b. Synchronous condensers
c. Capacitors
d. Reactor
a. Generators
What does I2R indicate?
a. Voltage
b. Resistance
c. Power Losses
d. Transformers
c. Power Losses
What resists an initial decline in system frequency following a disturbance?
a. Inertia
b. AGC
c. AVR
d. Frequency Bias
a. Inertia
What is the primary AGC control mode that will best indicate a Balancing Authorities
generation-load-interchange balance?
a. Generators on Auto
b. Flat Interchange control
c. Tie Line Bias
d. Constant Frequency
c. Tie Line Bias
When the total generation in an Interconnection is more than the total load, what will
the System Operator will experience?
a. Frequency below 60.00 Hz
b. Frequency above 60.00 Hz
c. Frequency at 60.00 Hz
d. Frequency scheduled change
b. Frequency above 60.00 Hz
When a transmission line is absorbing VARs from the system, which primary
characteristic is the line exhibiting?
a. Inductance
b. Capacitance
c. Resistance
d. Impedance
a. Inductance
What parameters are required to be within range to synchronize to the power system?
a. Frequency and voltage must be identical
b. Frequency, voltage, phase angle
c. Generator speed and voltage
d. Voltage and power angle
b. Frequency, voltage, phase angle
Potential Transformer and Current Transformers are used primary for which purpose?
a. Measure the potential energy
b. Step up the power flow to reduce losses
c. Monitor safety
d. Convert the measured value to a lower value for relays
d. Convert the measured value to a lower value for relays
When isolating electrical equipment, you must have a visible open point usually
provided by which device?
a. Disconnect switches
b. Circuit Breakers
c. Arresters
d. Relay protection
a. Disconnect switches
A System Operator notices voltage decreasing at key stations, what is your first action?
a. Direct generators to produce more reactive power
b. Place capacitors in service
c. Reduce Interchange
d. Re-dispatch
b. Place capacitors in service
What does power factor indicate?
a. The difference between real and reactive power
b. The difference between real and apparent power
c. The ratio between real and apparent power
d. The ratio between generation and load
c. The ratio between real and apparent power
What is the purpose of increasing voltage from generator voltages to transmission
voltages and then decreasing to customer voltages?
a. Minimize power system losses
b. Maximize power system voltage
c. Minimize power system equipment needed
d. Maximize power system customer load
a. Minimize power system losses