NCIDQ INPX - 2-1 Flashcards

NCIDQ - PROJECT COORDINATION

1
Q

What is building commissioning?

A

This is the process of inspecting, testing, starting up, and adjusting building systems and then verifying that the systems are operating as intended and that they meet the design criteria.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does an independent furniture rep differ from a manufacture’s rep?

A

This type of furniture representative is self-employed and may represent more than one manufacture.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of this schedule is this?

A

This is a graphic representation of a critical path method (CPM) schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What client-approved document should be available to the designer before the schematic design process begins?

A

Good business practice requires that a client-approved program be available before this phase of work begins.,

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are five of the most common variables that can affect the cost of a project when bidding occurs?

A

This aspect of a project bid can be affected by the….

  1. actual cost to the contractor and subcontractor
  2. current competitiveness of the market
  3. project schedule
  4. desire of a contractor to get the job
  5. level of profit required by the contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

on an interior construction project, who is responsible for the final electrical drawings?

A

on an interior construction project, the electrical engineer is responsible for this aspect of the plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which consultant is responsible for designing new opening in the floor of and existing building?

A

The structural engineer is responsible for designing in the floor of this type of building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which consultant must assist the interior designer when a project requirements the installation of heavy equip met?

A

A structural engineer must assist the interior designer in determining the installation requirements for this types if equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who may design a building’s sprinkler system?

A

The building component may be designed by a mechanical engineer, a fire protection engineer, or in some case, a fire protection contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In determining the total tie required for a project, who is responsible for estimating the construction time?

A

The constructor is responsible for this aspect of the total project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Who is responsible for determine the accuracy and completeness of dimensions, details, and quantities on shop drawings?

A

The constructor is responsible for these items on shop drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Who is responsible for providing any laboratory test, inspections, and reports required by the contract documents?

A

When these procedures are required by the contract documents, the owner must provide them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is involved in generating a fee projection?

A

In this process, the total fee the designer will receive, after amounts for profit, overhead, and other expenses are deducted, is allocated to the schedule and to the various staff members who will be completing the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what four tasks does interior designer normally perform during the schematic design phase of project?

A
  1. Prepares diagrams and drawings showing the general functional relationship required by the project
  2. Develops preliminary space plans
  3. Prepares design concepts, including colors, finishes, and furniture
  4. Prepares a preliminary statements of probable project costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between a contractor’s general overhead and project overhead?

A

Contractor’s general Overhead:
Cost of running a business
Project Overhead:
Consists of those expenses incurred in completing a specific job that are not labor, material, or equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the parameter method?

A

This method of estimating allows the interior designer to itemize components along with their unit costs.

17
Q

What is life-cycle cost analysis?

A

This is a method of determining the total cost of a building or building component or system. Initial costs are added to the costs of financing, operation, maintenance, and disposal, estimated over the useful life of the material or system.

18
Q

When a project is complete, who takes ownership of the contract documents?

A

At the end of the job, the interior designer retains the rights of ownership to these.

19
Q

What is considered to be the project cost?

A

This is the total cost to the owner of all components of a project, including construction, furniture, equipment, the contractor’s overhead and profit, and the cost of managing or supervising construction.

20
Q

What kind of expense are NOT included in the project cost?

A

These include the designer’s professional fees, consultants’ fees, financing cost, and other costs that are the responsibility of the owner.

21
Q

What type of scheduling chart looks like a bar graph?

A

A Gantt chart look like this