MRP Flashcards

1
Q

MRP

A

Material requirements planning (MRP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

MRP has the managerial objective of

providing

A

The right part at the right
time” to meet the production
schedules for finished products.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

MRP provides formal plans for each

A

part number–sub-assemblies,

components, and raw materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Independent demands MRP

A

Finished products (end items)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Dependent demands

: MRP

A

sub-assemblies,

components, and raw materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

MRP is planning for items

A

with dependent

demands

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PAB

A

= Projected Available Balance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SR

A

= Scheduled Receipt

represent the 
total planned usage for the 
item from all 
sources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PR =

A

= Planned Receipt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q


POR =

A

= Planned Order Release

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

SS =

A

= Safety Stock requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

LT

A

Lead Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

OH

A

= On-Hand inventory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Lot-for-lot (L4L)

A

Order as much as

needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Fixed 
order quantity (FOQ)
A

Order a multiple of a fixed quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Periodic
order quantity (POQ)
A

Order for requirements over a fixed number of

periods

17
Q

MRP Technical Issues

A
Frequency of MRP Processing

Regeneration vs net change

Firm planned orders

Safety stock and safety leadtime

Planning horizon

Master production scheduling vs. MRP
18
Q

Frequency of MRP Processing

A
Less 
frequent processing results in an out-of
-date picture

More frequent processing increases 
computer costs and may lead to system 
nervousness
19
Q

Regeneration vs Net Change

A

Recalculating all records and requirements is
called
regeneration

Net change
approach only recalculates those
records that have experienced changes

20
Q

Firm Planned Orders

A
Regeneration of the MRP records can lead to a 
large number of planned order changes

To avoid this, a planned order can be 
converted to a firm planned order (FPO)
21
Q

Safety Stock and Safety

Leadtime

A

Safety stock is buffer stock held in addition to the
quantity needed to satisfy gross requirements

Used when quantity uncertainty is the issue

Safety leadtime changes both the release and
due date of shop and/or purchase orders to
provide a margin for error

Used when leadtime uncertainty is the issue

Using safety leadtime is not the same as
increasing leadtime

Increasing leadtime changes only the release date

22
Q

Planning Horizon

A

Planning horizon is the total amount of time
included in MRP calculations

Longer planning horizon increases computational
requirements

Shorter planning horizon may result in less-effective
plans if significant future demand is not visible

At a minimum, the planning horizon should cover the
cumulative lead time for all finished goods items

23
Q

Master Production Scheduling

vs. MRP

A

Master production scheduling and MRP logics are
similar

The only difference is in determining requirements

In master production scheduling, projected requirements
are determined from demand forecasts and customer
orders

In MRP, GRs are determined from production plans of
parent items

Master production scheduling and MRP can be
performed together or separately

24
Q

Bottom-Up Replanning

A

Botton-up replanning means using pegging

data to solve material shortage problem

25
Q

Pegging

A

Pegging relates the gross requirements for
a part to all the planned orders or other
sources of demand that created the
requirements

26
Q

Exception Codes

A

Define exception codes for situations

that need immediate attentions