Module 8: Project Work and Delivery Flashcards

1
Q

Organizational Process Assets (OPA)

A

Pans, Processes, and knowledge procedures that are used by the organization and affect projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Enterprise Environmental Factors (EEFs)

A

Internal and external factors that can influence a project’s success but are usually outside the control of the project

Internal - factors within the organization
External - factors outside of the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Critical Communication Skills

A

Listen actively and effectively
Question and probe to better understand
Set and manage expectations
Motivate to perform an action or provide encouragement/reassurance
Coach to improve performance and achieve desired results
Negotiate to achieve mutually acceptable agreements between parties
Resolve conflict to prevent disruptive impacts
Summarize, recaps, and identify the next steps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Communication Model

A

Sender - sends the message
Receiver - received the message
Message - the information
Medium - how the information is conveyed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Communication Blocker

A

Something that completely stops/prevents communication from happening

Ex:
undelivered emails
acronyms that are not known
the receiver is not attentive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Communication Barriers

A

An obstacle that makes communication more difficult or less effective but doesn’t necessarily stop it entirely

Ex:
poor internet connection
resistant mindset
acceptance of misinformation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Communication Filter

A

The personal biases, perceptions, experiences, and assumptions that influence how a person receives a message

Ex:
cultural differences
psychological and sociological perspectives
dysfunctional emotional behaviors
education differences
traditions (“how it’s always been done”)
talking past one another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Communication Methods

A

Formal Written
Formal Verbal
Informal Written
Informal Verbal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Push and Pull Communication

A

Push - when information is given to someone, lands in their lap (used for high-priority info, high priority stakeholders)
Pull - when information needs to be sources from a location (used for lower-priority information, lower-priority stakeholders)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Communications Management Plan

A

A document that outlines how communication will be managed throughout the lifecycle of a project. Defines the communication requirements, methods, frequency, and responsibilities.

Answers the…
Who is it to?
What is being communicated?
When is it being communicated?
Why is it being communicated?
How is it being communicated?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Earned Value Management

A

Used to assess the project performance by comparing the planned progress with the actual progress and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Planned Value (PV)

A

The estimated value of the work planned to be completed by a specific point in time

PV = planned % of work completed * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Budget at Completion (BAC)

A

The total planned budget for the entire project, from start to finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Earned Value (EV)

A

The value of the work actually completed by a specific point in time compared to the budgeted cost

EV = actual % of work completed * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost Variance (CV)

A

The difference between the earned value (EV) and the actual cost (AC) incurred

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Variance (SV)

A

The difference between the earned value (EV) and the planned value (PV) to determine how ahead of behind schedule the project is

SV = EV - PV

17
Q

Cost Performance Index (CPI)

A

A ratio that measures cost efficiency and financial effectiveness in a project

CPI = EV/AC

CPI > 1 => the project is under budget (efficient)
CPI < 1 => the project is over budget (inefficient)
CPI = 1 => the cost is on budget

18
Q

Schedule Performance Index (SPI)

A

A ratio that measures schedule efficiency

SPI = EV/PV

SPI > 1 => project is head of schedule
SPI < 1=> project is behind schedule
SPI = 1 => project is on schedule

19
Q

Estimate at Completion (EAC)

A

The forecasted total cost of the project at completion based on correct performance

EAC = BAC/CPI

20
Q

Estimate to Complete (ETC)

A

The expected cost required to complete the remaining work of the project

ETC = EAC - AC

21
Q

Variance at Completion (VAC)

A

The difference between the budget at completion (BAC) and the estimate at completion (EAC) showing whether the project is projected to finish over or under budget

VAC = BAC - EAC

+ VAC = project is expected to be under budget
- VAC = project is expected to be over budget

22
Q

Actual Cost (AC)

A

The actual cost for the work completed in the given period

23
Q

Response to Threats

A

Escalate - pass the threat to someone better suited to handle it
Avoid - act to eliminate or protect against the threat
Transfer - shift responsibility of the threat to a third party
Mitigate - take steps to reduce the likelihood or impact of the threat
Accept - acknowledge the threat and choose not to take action

24
Q

Response to Opportunities

A

Escalate - pass the opportunity to someone better suited to handle it
Exploit - take full advantage of the opportunity to capture its benefits
Share - transfer ownership to a third party to share the benefits
Enhance - increase the potential benefits and impact of the opportunity
Accept - acknowledge the opportunity but choose not to take action

25
Q

Addressing Issues Process

A

Identify the Issue - record in issue log
Assign Ownership - assign someone to take responsibility for resolving the issue
Understand Complexity - figure out how to tackle the complexity of the issue
Learn & Improve - link issues back to original tasks and learn from them
Resolve the Issue - gather more information, analyze the situation, and use creative or logical thinking

26
Q

Quality Management Plan (QMP)

A

A document that outlines how a project’s quality will be managed, ensured, and controlled

Predictive Approach: assigned to specific team members
Adaptive Approach: shared among the whole team

27
Q

Problem Solving Steps

A

1) Define the problem
2) Analyze the root cause
3) Generate Solutions
4) Select the best solution
5) Implement the solution
6) Verify the result

28
Q

Prevention Costs

A

Costs incurred to prevent defects and failures

29
Q

Appraisal Costs

A

Costs associated with measuring and evaluating the quality or a product or service during a project to meet the required standards

30
Q

Internal Failure Costs

A

Costs associated with finding and addressing defects BEFORE it gets to the customer

31
Q

External Failure Costs

A

Costs associated with finding and addressing defects AFTER it gets to the customer

32
Q

Quality Management Tools

A

Cause an Effect Diagram - used to identify and analyze cause and effects
Pareto Principle - graph displaying more frequent to least frequent causes (80/20)
Control Chart - shows process behavior over time
Six Sigma - data-driven method for improving processes by removing defects

33
Q

Levels of Stakeholder Engagement

A

Leading
Supportive
Neutral
Resistance
Unaware